Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 By Assoc. Prof. Dr. Ahmet ÖZTAŞ Gaziantep University Department of Civil Engineering CE 533 - ECONOMIC DECISION ANALYSIS IN CONSTRUCTION CHP 7 -Benefit/Cost.

Similar presentations


Presentation on theme: "1 By Assoc. Prof. Dr. Ahmet ÖZTAŞ Gaziantep University Department of Civil Engineering CE 533 - ECONOMIC DECISION ANALYSIS IN CONSTRUCTION CHP 7 -Benefit/Cost."— Presentation transcript:

1 1 By Assoc. Prof. Dr. Ahmet ÖZTAŞ Gaziantep University Department of Civil Engineering CE 533 - ECONOMIC DECISION ANALYSIS IN CONSTRUCTION CHP 7 -Benefit/Cost Analysis and Public Sector Projects

2 2 CHP 7. Benefit/Cost (B/C) Analysis 1.Public Versus Private Sector Projects 2.Benefit/Cost Analysis 3.Incremental B/C Evaluation of Two or More Alternatives 4.Using Excel for B/C Analysis Topics

3 3 Learning Objectives 7.1 Public Sector Analysis 7.2 Benefit Cost Analysis 7.3 Alternative Selection 7.4 Spreadsheets Using the B/C Ratio Approach

4 4 7.1 Public versus Private Sector Projects Public Sector: Ownership – by citizens- the public Public Sector Projects: Provide needed services to the public and “no profit”

5 5 7.1 Types of Projects Hospitals Parks and recreation facilities Highways, dams, bridges Courts, schools, prisons Public housing Many other types

6 6 7.1 Characteristics – Compared CharacteristicPublic SectorPrivate Sector Size of Investment LargerSome Large; medium to small Life EstimatesQuite Long: 30-50 years Shorter: 2-25 years Annual Cash Flow Estimates No Profit: costs and benefits Revenues – profit cost estimates

7 7 7.1 Attributes Public Sector Projects do not have “profits”. Projects can have certain undesirable consequences associated Thus, can be controversial in nature Draw media attention – debated on pros and cons

8 8 7.1 Estimating for Public Projects: Costs Basic elements for public projects: Costs Construction, operations, maintenance less est. salvage values Initial costs fairly well know Future O&M are less known and must be estimated

9 9 7.1 Estimating: Benefits BENEFITS to the public (users) must be estimated in terms of periodic dollar values Very difficult to do Benefits = the advantages to the public stated in $$ Owners – generally the public

10 10 7.1 Estimating: Disbenefits Disbenefits Expected undesirable (negative) consequences to the owners (public) Assuming the project is undertaken May be indirect economic disadvantages to the public Very hard to estimate and convert to $ amounts

11 11 7.1 General Principle For public projects we find: It is very difficult to estimate and reach agreement on the economic impacts of benefits and disbenefits for public sector projects.

12 12 7.1 Funding Sources – Compared CharacteristicPublic SectorPrivate Sector FundingTaxes, fees, bonds, pvt. funds Sale of new stock, bonds, loans, ret. earnings Interest RateTends to be lower Higher: At market cost

13 13 7.1 Funding Public Projects Generally low interest charges Public entities do not pay taxes Project investments basically backed by public agencies Cost-sharing arrangements often exist Less perceived risk with public projects Interest rate is determined differently than in the private sector: Called the social discount rate

14 14 7.1 Additional Comparisons CharacteristicPublic SectorPrivate Sector Selection criteria Multiple or many Rate of return or present value Environment of the evaluation Political arena (debated, pressure groups) Primarily economic

15 15 7.1 Selection Process Not as “clean” as in the private sector Involves interest and pressure groups Often draws media attention Involves many different viewpoints: Citizen The tax base Number of students in the school district Creation and retention of jobs. Economic development potential

16 16 7.1 Evaluation Process The viewpoint finally adopted will: Determine the estimates of.. Costs Benefits Disbenefits Note: the viewpoint must be established before the economic evaluation

17 17 7.2 B/C Analysis – Single Project Historical Point B/C analysis philosophy was instituted and promoted by the Flood Control Act of 1936 Introduced to promote a sense of objectivity in an analysis

18 18 7.2 B/C Formulations Assignable life, N - years Estimate costs ($) Estimate benefits in ($) Estimate disbenefits in ($) Assign an interest rate – i (%/year)

19 19 7.2 B/C Formulations Then convert all amounts to either a Present Worth – PW(i%) Annual Worth – AW(i%) Future Worth – FW(i%) Then calculate a B/C ratio in one of three ways…..

20 20 7.2 B/C Ratios: 3 Formats Three acceptable formats are:

21 21 7.2 Notes Regarding Signs By convention: Revenues are assigned (+) signs Costs are assigned (+) signs Salvage values are subtracted from costs Disbenefits are treated more than one way

22 22 7.2 Handling Disbenefits 1.Disbenefit values are subtracted from benefits 2.Disbenefit values are added to costs 3.Either approach will result in a consistent analysis – but be consistent throughout an analysis

23 23 7.2 Decision Rule If B/C ratio (=>) 1.00 Conditionally accept the alternative If B/C ratio (<) 1.00, conditionally reject the alternative If B/C ratio “close” to 1.00, then intangible factors may sway the decision to accept or reject There are 3 B/C formula:

24 24 7.2 Conventional B/C Ratio 1) Conventional B/C Ratio is:

25 25 7.2 Modified B/C Ratio 2) Modified B/C ratio: It subtracts the maintenance and operations (M&O) costs in the numerator Initial investment

26 26 7.2 Convention vs. Modified? It makes no difference which approach is used However, the ratio values will differ (magnitude) But, the same absolute (accept/reject) decision will be taken.

27 27 7.2 Benefit-Cost Difference 3) B – C difference: B-C difference is not a ratio B-C difference is: (Benefits – Costs) (as a PW or AW) The “B” represents the Net Benefit Benefits – Disbenefits

28 28 7.2 Example 7.2

29 29 7.2 Example 7.2 Applies all three approaches to the same problem situation

30 30 7.2 Example 7.2 B/C = 0.51 (reject) Mod B/C = 0.39 (reject) (B-C) = $-0.24 million (< 0…reject) Result: Same decision with varying magnitudes of the ratio.

31 31 7.3 Incremental B/C for Multiple Projects Select from two or more mutually exclusive alternatives Same approach as that in Chapter 6, Section 6.6 Remember, the Do Nothing alternative always exists and should be evaluated as an alternative. Requires a proper ordering of alternatives Order alternatives on the basis of Total Costs

32 32 7.3 Incremental B/C for Multiple Projects If  (B/C) (=>) 1.00, select the higher- cost alternative Otherwise select the lower-cost alternative! If you are using a PW to determine equivalency, then you must have an equal- life model or LCM of lives. Or, apply AW on a typical cycle for the alternatives and the repeatability assumption applies.

33 33 7.3 Incremental B/C for Multiple Projects There are 2 types of benefits: 1) Usage cost estimates, 2) Direct benefit estimates. Before conducting the incremental evaluation, classify alternatives. Usage cost: implied benefits based on the difference in costs between alternatives. Evaluate these alternatives only against each other. Direct benefit: Benefit amounts estimated. First evaluate against DN, then, against each other.

34 34 A procedure for comparing multiple, mutually excluive alternatives using conventional B/C ratio: For eachalternative, determine the equivalent PW, AW or FW for costs C and benefits [or (B-D) if disbenefits are considered]; Order alternatives by increasing total equivalent costs. For direct benefit alternatives, add DN as the first alternative Determine the incremental cost (  C) and benefits (  B) between first two alternatives. 7.3 Incremental B/C for Multiple Projects

35 35 For usage cost alternative,  B = usage cost of 2 - usage cost of 1 4.Calculate incremental conventional B/C ratio using below equation  B/C =  (B-D)/  C 5. If  (B/C) => 0, eliminate 1; 2 is survivor. otherwise 1 is survivor. 6. Continue to compare alternatives using step 2 through 5 until one alternative remains as survivor. 7.3 Incremental B/C for Multiple Projects

36 36 7.3 Example 7.3 (Incremental B/C) the addition is estimated at 30 years. Use conventional B/C ratio ananlysis to select A or B. XXXXXXXXXXXXXXX 800,000 1,050,000

37 37 7.3 Example 7.3 (Incremental B/C) 1) AW 1 = 10,000(A/P,5%,30)+35= 685,500 AW 2 = 15,000(A/P,5%,30)+55= 1,030,750 2) Add DN and order: DN, 1, 2. 3) Compare 1-to-DN which is alt. 1 4) Calculate incremental (  B/C) ratio  B/C = 800,000/685,500 = 1.17 5) Since 1.17 > 1.0 design 1 is survivor. 6) Compare 2-to-1:  B = 1,050,000 - 800,000= 250,000  C = 1,030,750 - 685,500= 345,250  B/C = 250,000/ 345,250 = 0.72 < 1.0 Design 2 eliminated, and design 1 is selection for bid.

38 38 7.3 Example 7.4 (Incremental B/C)

39 39 7.3 Example 7.4 (Incremental B/C)

40 40 7.3 Example 7.4 (Incremental B/C) 4 Alternatives { 1,2,3, and 4} Ranked on total cost as shown Analysis Summary: (2 -1) B/C = 2.24 …Go with {2} (3-2) B/C =0.62…Reject 3, stay with {2} (4-2) B/C = 1.83 Go with 4, final winner

41 41 7.3 Example 7.5 (Incremental B/C)

42 42 7.3 Example 7.5 (Incremental B/C)

43 43 7.3 Example 7.5 (Incremental B/C) DN 0 -

44 44 Chapter Summary B/C is primarily a public-sector analysis technique Uses PW or AW with a social cost of capital interest rate (specified before the analysis is conducted) B/C ratio greater than 1 indicates economic desirability Results may depend upon viewpoints that define costs and benefits Applied within the political arena

45 45 End of Chapter 7


Download ppt "1 By Assoc. Prof. Dr. Ahmet ÖZTAŞ Gaziantep University Department of Civil Engineering CE 533 - ECONOMIC DECISION ANALYSIS IN CONSTRUCTION CHP 7 -Benefit/Cost."

Similar presentations


Ads by Google