Presentation is loading. Please wait.

Presentation is loading. Please wait.

Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January.

Similar presentations


Presentation on theme: "Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January."— Presentation transcript:

1 Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January 6, 2004

2 OUTLINE  Introduction  Research Objective  Literature Review  Research Methodology  Results and Analysis  Conclusions and Recommendations

3 INTRODUCTION  The issue of time in construction projects is important for both the owner and the contractor.  Construction Contract Duration (CCD) is the amount of time given to the contractor to execute the work described by the plans and specifications.  It is a very important issue of any construction contract documents.

4 RESEARCH OBJECTIVES  To investigate the available methods used to set CCD and the factors affecting the determination process.  To study and evaluate the current practice applied for set CCD for public projects in Saudi Arabia.  To make recommendations related to the practice of setting CCD in the Kingdom.

5 SCOPE AND LIMITATIONS  The scope of this research will be limited to public construction projects in Saudi Arabia (owner’s point of view).  Projects that the Government Department (project owner) has authority to decide on the setting of CCD.  Projects that have value of SR 100 million or less will be under discussion in this research.

6 LITERATURE REVIEW  There is a relationship between time and cost.  In general, the time dependent costs increase linearly with the passage of time.  Examples of time dependent costs: cost of supervision and site office utilities.  CCD is normally expressed in either working days, calendar days, or a fixed date for completion.

7 LITERATURE REVIEW  Methods for setting CCD  Construction season limits: project must be finished prior to a certain season  Quantity or production rate: breaking the project down into the major controlling work items  Work flow technique: large complicated projects where a lot of coordination effort is needed (CPM)  Estimated cost: related to contract time or working days required to complete a particular project

8 RESEARCH METHODOLOGY  Interviews and telephone calls were performed with some of government officials.  A questionnaire was developed in order to collect the data needed for the research. It consists of 18 questions.  The total population consists of 70 authorities (government departments responsible for executing public construction projects).  A total of 47 completed questionnaires were used for analysis. SAS software were used.

9 RESULTS AND ANALYSIS  Who set CCD:  91% of the respondents reported that CCD is set at their department by either top management, engineering department, or by hired consultant.  Attention paid to setting CCD:

10 RESULTS AND ANALYSIS  Methods of setting CCD:  Budget allocations (30%)  the need for the project (18%)  Past experience (13%)  Critical Path Model (CPM) (8%)  Joint work of the engineering department and a consultant (8%)  Contractors are requested to submit CCD with their bids (6%)  The majority of respondents (87%) expressed the need to apply a method to set CCD.

11 RESULTS AND ANALYSIS Negative Consequences for Short CCDRank Poor performance by contractors resulting from inadequate time allocation to work items 1 Excessive administrative burden resulting from delay claims 2 High bid prices3 Positive Consequences for Short CCD Raising contractor’s awareness of the importance of time 1 Promoting effective management2 Low prices due to short CCD3

12 RESULTS AND ANALYSIS Negative Consequences for Long CCDRank Encouraging contractors to bid more work than can be handle in a timely manner 1 Discourage effective management and innovation2 Leading to poor performance resulting from discontinuous operations (relaxed schedule) 3 Positive Consequences for Long CCD Good coordination with other agencies1 Permitting more contractors to bid2 Low bid prices3

13 RESULTS AND ANALYSIS  Factors affecting the setting of CCD: 1. Project size 2. Site conditions 3. Project design 4. Top management assessment of the city need of the project 5. Project type  Factors affecting CCD can be grouped into three main categories: project,contractor,and environmental characteristics.

14 CONCLUSION  There seems to be no systematic engineering methods or at least formal procedures followed by Government Authorities to set CCD for public projects.  CCD is currently set by engineering department, hired consultant, or top management of the government agencies.  Several factors affects setting CCD. Among the most important factors are project size, design, budget allocations, type, and site conditions.

15 RECOMMENDATIONS  The Government procurement Regulations should address the setting of CCD. Articles have to be written to establish guidelines to improve the current practice of setting CCD.  Engineering methods should be developed and used to set CCD. Concerned Government Authorities such as Ministry of Housing and Public Works should take the initiative to develop such methods.  The engineering department of concerned Authorities should participate in the setting of CCD.

16 RECOMMEND GUIDELINES TO SET CCD  Step 1: Determine a CCD range. Based on:  The project’s tender documents.  Factors affecting CCD.  The experience gained from constructed projects.  Using the above inputs and utilizing scheduling techniques (CPM, PERT, Bar chart), production rates, or any other approach, a reasonable CCD range can be estimated.

17 RECOMMEND GUIDELINES TO SET CCD  Step 2: Check weather the setting of CCD is under the authority of the project owner.  If there is any preplanned completion date established by higher authorities to meet special operational or public needs.  The project owner can discuss CCD with decision makers based on the range established in step #.1

18 RECOMMEND GUIDELINES TO SET CCD  Step 3: If the project owner is authorized to set CCD, then he can proceed to check weather budget allocation constraints exist or not.  Step 4: In the case where there is no budget allocation constraint, the project owner is to identify his objectives of CCD.  Objectives include: at least possible bid price, at shortest possible CCD, or an optimal total cost CCD.

19 RECOMMEND GUIDELINES TO SET CCD  Step 5: The set CCD, produced by either steps #3 and 4, should be reported to top management for approval.  Step 6: The approved CCD is to be incorporated in the tender documents.

20 THANK YOU


Download ppt "Determination of Construction Contract Duration for Public Projects in Saudi Arabia By: Ahmed Saleh Al-Sultan, June 1989 Presented by Sameh Elish January."

Similar presentations


Ads by Google