Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013.

Similar presentations


Presentation on theme: "Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013."— Presentation transcript:

1 Project Update Goat Island Park Ph. 2 Town of Cramerton December 19 th, 2013

2 Overall Master Plan – Phase 2

3 Master Plan – Phase 2 Phase 2-Amenities Pedestrian Bridge (3) Cornhole Boards (2) Table Tennis Dog Park Playground Observation Platform Phase 2-Amenities Pedestrian Bridge (3) Cornhole Boards (2) Table Tennis Dog Park Playground Observation Platform

4 Bridge Design Bridge Approach 80’ span Capstone Style Prefabricated Bridge 165’ Center Span, Painted Black with Decorative Lighting Capstone Style Prefabricated Bridge 165’ Center Span, Painted Black with Decorative Lighting Bridge Approach 120’ span Prefabricated Bridge 165’ span

5 Bridge Approach Detail

6 Permitting FERC PERMIT: US ARMY CORP OF ENGINEERS (USACOE) PERMIT (404): NCDENR DIVISION OF WATER RESOURCES, WATER QUALITY PERMITTING (401): NCDENR DIVISION OF ENERGY MINERAL AND LAND RESOURCES, LAND QUALITY SECTION, EROSION AND SEDIMENT CONTROL COAST GUARD PERMIT “NO-RISE” CERTIFICATION: BUILDING PERMIT – GASTON COUNTY

7 Cost Estimate

8 SCHEDULE Project Team MeetingJanuary 9, 2014 Complete DesignJanuary 31, 2014 Advertise for Construction BidsFebruary 5, 2014 Open Construction BidsFebruary 28, 2014 Award Construction ContractMarch 20, 2014 Begin ConstructionApril 5, 2014 Complete ConstructionDecember 15, 2014

9 Questions or Comments? Goat Island Project