Cornville Community Park Conceptual Design Recreation Area and Facility Design Class April 9, 2008.

Similar presentations


Presentation on theme: "Cornville Community Park Conceptual Design Recreation Area and Facility Design Class April 9, 2008."— Presentation transcript:

1 Cornville Community Park Conceptual Design Recreation Area and Facility Design Class April 9, 2008

2 Potential Land Acquisition

3 Draft Conceptual Design

4 Section Q - Design

5 Section Q - Revised

6 Section R - Design

7 Estimated Construction Costs  Community Center 75’x75’ = $843,750  Ramada’s (6) 15’x15’ @ $17,000 ea = $102,000  Group Ramada (1) 40’x40’ @ $55,000  Playgrounds (2) 40x40 = $95,000  Benches 15 x $300 = $4,500  Bathrooms $100,000  Lighting (4 poles) $3,000  69,816 sq ft concrete ($750 sq ft) walkway 4’interior/ 8’perimeter= $523,620  Main parking lot 4,800 sq ft ($12 sq ft) = $57,600  Rim parking lot 1,280 sq ft ($12 sq ft) = $15,360  Estimated Cost $1,742,230  Estimated maintenance cost $6,000/acre x 30 acres= $180,000 per year

8 Now What?  Submit final document by the end of April to CCA  Include land acquisition recommendations  Recommend funding sources  Future consulting services