City of Bellingham Parks & Recreation Department Project Manager; Jonathan Schilk, RLA 1 Squalicum Creek Park Phase III.

Similar presentations


Presentation on theme: "City of Bellingham Parks & Recreation Department Project Manager; Jonathan Schilk, RLA 1 Squalicum Creek Park Phase III."— Presentation transcript:

1 City of Bellingham Parks & Recreation Department Project Manager; Jonathan Schilk, RLA 1 Squalicum Creek Park Phase III

2 2 Squalicum Creek Park Phase III Site Location

3 3 PHASE TWO PHASE ONE COAST MILLENNIUM TRAIL BIRCHWOOD PARK SQUALICUM CREEK PARK Squalicum Creek Park Phase III Existing Condition BAY TO BAKER TRAIL N

4 4 RESERVED FOR SLEDDING PARKING AREA (52) BASKETBALL COURT LOOP TRAIL PICNIC SHELTER Squalicum Creek Park Phase III Site Plan PARKING AREA (23) PLAYGROUND BALL FIELD FENCED MAINTENANCE AREA FENCED DOG OFF LEASH AREA MULTI USE FIELD

5 Squalicum Creek Park Phase III Site Amenities 5

6 6 Reservable Picnic Shelter Smaller Shelter in the Dog Park Restroom Building Near the Basketball Court Park Sign Squalicum Creek Park Phase III Site Amenities

7 7 Construction Funding $4,000,000 Greenways Three Levy Fund $500,000 Park Impact Fees Squalicum Creek Park Phase III Financial

8 8 Bid Opening November 21, 2013 ConstructionJanuary – December 2014 Squalicum Creek Park Phase III Schedule

9 Thank you! Project Manager; Jonathan Schilk, RLA 9 Squalicum Creek Park Phase III

10 10 Squalicum Creek Park - Public Meetings Pre-Acquisition Meetings 1Wednesday, February 07, 2001Community Meeting 2Monday, April 22, 2002City Council Approves Purchase Master Plan 3Tuesday, April 13, 2004Steering Committee #1 4Tuesday, April 20, 2004Public Meeting #1 5Thursday, May 06, 2004Steering Committee #2 6Thursday, May 20, 2004Public Meeting #2 7Wednesday, June 16, 2004Steering Committee #3 8Wednesday, July 28, 2004Steering Committee #4 9Tuesday, August 24, 2004Public Meeting #3 10Thursday, October 07, 2004Steering Committee #5 11Wednesday, October 20, 2004Public Meeting #4 12Wednesday, January 12, 2005Parks & Rec Advisory Board Approval 13Monday, February 07, 2005Master Plan Adoption by Bellingham City Council Phase One 14Monday, June 06, 2005Public Meeting #1 15Thursday, August 18, 2005Public Meeting #2//Rezone Public Meeting Phase Three 16Wednesday, August 17, 2011Steering Committee Meeting #1 17Tuesday, September 20, 2011Birchwood Neighborhood Assn. Meeting 18Wednesday, September 28, 2011Steering Committee Meeting #2 19Thursday, October 06, 2011Public Meeting 20Wednesday, December 14, 2011Parks & Rec Advisory Board Approval 21Monday, March 12, 2012Resolution by Council to Approve Grant Application 22Tuesday, January 08, 2013Steering Committee Meeting #3 23Tuesday, January 22, 2013Birchwood Neighborhood Assn. Meeting 24February 28, 20013Steering Committee Meeting #4 25Thursday, March 07, 2013Public Meeting 26Thursday, April 04, 2013 GAC Meeting

11 11 RESERVED FOR SLEDDING Squalicum Creek Park Phase III Site Plan SQUALIICUM WAY BAY TO BAKER TRAIL (23) BALL FIELD FENCED MAINTENANCE AREA FENCED DOG OFF LEASH AREA BAY TO BAKER TRAIL RESERVED FOR SLEDDING PARKING AREA (52) BASKETBALL COURT LOOP TRAIL PICNIC SHELTER