Presentation is loading. Please wait.

Presentation is loading. Please wait.

Ornulv (Arnie) Sonsteby, PE Penn State / FAA Airport Conference 2007

Similar presentations


Presentation on theme: "Ornulv (Arnie) Sonsteby, PE Penn State / FAA Airport Conference 2007"— Presentation transcript:

1 Ornulv (Arnie) Sonsteby, PE Penn State / FAA Airport Conference 2007
INSTALLATION OF IN-PAVEMENT LIGHTS IN CONCRETE PAVEMENT & IMPACT ON LIGHT PHOTOMETRICS Ornulv (Arnie) Sonsteby, PE & Doron Lean Penn State / FAA Airport Conference 2007

2 IPRF-03-1 Project Best Practices Guide for
In-Pavement Lighting, PCC Pavement Estimated Completion: 2007 PI & Contact: Ornulv (Arnie) Sonsteby, P.E. Sponsored by: FAA, in Cooperative Agreement with Innovative Pavement Research Foundation (IPRF)

3 GUIDE CONTENT Coordination between disciplines
Installation in new vs. existing PCC Products, methods, tolerances Boxouts / blockouts Deficiencies and corrective alternatives Strength and load transfer

4 Preparing Light Base & Jig

5 Light Base Installation
“Anchor” function (preparation for paving) (b) “Strengthening” function (completed installation)

6 INSTALLATION ISSUES Coordination between disciplines Selecting:
Methods & procedures lighting products Pavement materials Tolerances & verification

7 CCOORDINATION IN DESIGN
Light location vs. pavement joints Materials and method QC/QA Tolerances and Consequences

8 PCC JOINT CONFLICTS Touch Down Zone Lights
Lead-off / Lead-on TW CTL Lights TW CTL Lights at curves / intersections In-pavement RGL / Stop Bar Lights

9 MATERIALS & METHODS Light Base, Conduit, Pavement materials
Installation procedures and “structure” -- in new or existing pavement Surface finish (“cookie cutter” vs. Core)

10 QC / QA The quality of installation depends on:
Good design by engineer Good craftsmanship by installer Close coordination between disciplines Inspection / verification of compliance

11 Tolerances and Consequences
Pavement vs. Base tolerances Light Base: Location, Height, Azimuth, Level When to modify, when to replace

12 ** Paving elevation tolerance -- + ½”
Light Tolerances Location: Per AC. Depends on type and function of light. Height: Fixture edge even with pavement, (low side): +0”, -1/16. Azimuth: Within ± ½ degree. Level: With horizon. No tolerance specified. ** Paving elevation tolerance -- + ½”

13 Level Tolerance? Pavement has longitudinal grade & cross slope (up to 1.5% major R/Ws) No tolerance in AC. Engineer may establish tolerance (varies) Tolerance applied in wrong direction worsens condition Consider 

14 Level !! TRANSVERSE SLOPE LONGITUDINAL GRADE Ht D Ht D
Deg Grade for 12” for 6” Ht D Ht D 1/ % ” ” % ” ” O LONGITUDINAL GRADE

15 COORDINATION IN CONSTRUCTION
Survey Materials and method QC/QA Tolerances and Consequences

16 Survey Coordinate survey activities Survey to: Locate light
Install light base Verify before paving

17 Selecting Materials & Methods
Submittals review for compliance Establish installation sequence and responsibilities Inspection --- more inspection Protect lights while completing paving

18 Conduit in pavement base layer Setting base “in space”
Light base Conduit in pavement base layer Setting base “in space”

19 Setting bases in “fill-in” lane

20 RW Edge Light, Toe-In Installation in existing PCC Pavement

21 QC / QA Verify light location
Verify height, azimuth & level while securing light base Check tolerances prior to paving Inspect surface finish Protect light while paving, grooving, sweeping, and marking

22 2’ from Joint Issue AC 150/5340-30 Modeling: (by Tigerbrain)
R/W CTL: “The line of lights is offset a maximum of 2’ from the runway centerline to the edge of fixture.” T/W CTL: “Fixtures should be installed so that their nearest edge is approximately 2’ from any rigid pavement joint.” Modeling: (by Tigerbrain)

23 σ - bottom of 18” thick 20’x20’ slab B-777 (254K edge loading).

24 σ - top of 18” thick 20’x20’ slab B-727 (corner loading).

25 Joint Issue Comments Pavement Design is conservative (edge stress, no load transfer). Modeling (with no load transfer between slabs, no bonding to underlying layer): Dowels generally reduced max edge stress by ~ 20%. With 2 dowels omitted, max edge stress reduced by ~ 12%.

26 (Joint Issue Comments continued)
Hence: Inside 2’, with 1 or 2 dowels omitted has minimal impact on slab-slab load transfer. Load transfer between light base and pavement – assessment suggests non-issue. Embedded steel can help control cracking close to joint. Alternative: Boxout

27 PCC Joints Light base 18” 7” Light near PCC joint

28 Details, details !! PCC Joint Cracks In-Pavement Light Conduit Kerf

29 T/W CTL Light Boxout at PCC joint

30 Normal joints Crack Doweled joint for Boxout Boxout at PCC joints !

31 Threshold Light Bar “boxout”

32 A few Related concerns

33 for full section of kerf !
KERFS PCC Joint Maintain existing pavement joints - for full section of kerf !

34 Conduit below !! Longitudinal crack center T/W slab T/W Centerline
Light

35 Faulty sealing

36 Fate of out-of-tolerance
light bases!

37 Doron


Download ppt "Ornulv (Arnie) Sonsteby, PE Penn State / FAA Airport Conference 2007"

Similar presentations


Ads by Google