1 Bulk Water Supply in Limpopo Integrating Infrastructure Delivery towards 2030 Summit Peter Mokaba Stadium 5 and 6 October 2010 A.M. Matukane.

Similar presentations


Presentation on theme: "1 Bulk Water Supply in Limpopo Integrating Infrastructure Delivery towards 2030 Summit Peter Mokaba Stadium 5 and 6 October 2010 A.M. Matukane."— Presentation transcript:

1 1 Bulk Water Supply in Limpopo Integrating Infrastructure Delivery towards 2030 Summit Peter Mokaba Stadium 5 and 6 October 2010 A.M. Matukane

2 2 Contents 1.Growth Points 2.Water Resources -Dams, Transfers, Ground water 3.ORWRDP, MCWAP, GLEWAP, LRGWS -Description, Purpose, Map, Schedule, Risks and Mitigation 4.Regional Bulk Infrastructure Grant (RBIG) 5.Funding 6.Challenges

3 3 Bulk Water Supply in Limpopo Growth Points 1.Polokwane 2.Elias Motswaledi 3.Makhado 4.Lephalale 5.Greater Tubatse 6.Greater Tzaneen Growth Points 7.Phalaborwa 8.Thabazimbi 9.Mogalakwena 10.Marble Hall 11.Musina 12.Lepelle Nkumpi

4 4 Bulk Water Supply in Limpopo The growth points in red are, apart from existing supplies, currently not addressed by either Implementation Ready Studies (IRS) or by constructing of a water resource/services project. The other growth points are covered with an IRS or a phase of a regional bulk water project is under construction to alleviate the water problem The water resources and transfer schemes are to support the development of the different growth points in the province.

5 5 Bulk Water Supply in Limpopo All Growth Points must have water supply schemes: A water resource – surface and/or groundwater A water treatment plant Pump stations Regional Bulk – from source to and including bulk reservoir Internal Bulk– from bulk reservoir outlet to reticulation connection Reticulation– from internal bulk end to household meter

6 6 Bulk Water Supply in Limpopo DWA has constructed many major dams in Limpopo in the past which supply water to people and other users, namely: Nzhelele, Vondo, Damani, Lupepe-Nwanedi in Vhembe Middle Letaba, Ebenezer, Tzaneen, Thabina, Tours, Blydepoort in Mopani Mokolo, Doorndraai, Glen Alpine in Waterberg Houtrivier, Chuene, Molepo in Capricorn Vergelegen, Nkadimeng, Piet Gouws, Flag Boshielo in Sekhukhune

7 7 Bulk Water Supply in Limpopo DWA is developing the major dams in Limpopo: Inyaka (now in Mpumalanga) Nandoni in Vhembe District Flag Boshielo Raising, and De Hoop in Sekhukhune District- construction 50% completed Nwamitwa in Mopani District in planning Possible dam in Olifants river under investigation

8 8 Bulk Water Supply in Limpopo DWA is planning and developing major water transfer schemes in Limpopo from: Inyaka (now in Mpumalanga) to Acornhoek Nandoni in Vhembe District to Makhado, Matoks, Giyani, etc Flag Boshielo to Pruissen at Mokopane De Hoop in Sekhukhune District to Burgersfort, Tubatse, Lebowakgomo and Polokwane (ORWRDP) Crocodile river to Lephalale (MCWAP) Groblersdal to Moutse West

9 9 Bulk Water Supply in Limpopo Major Schemes 1.Olifants River Water Resources Development Project (ORWRDP) 2.Mokolo & Crocodile Water Augmentation Project (MCWAP) 3.Groot Letaba Water Augmentation Project (GLeWAP) 4.Luvuvhu River Government Water Scheme (LRGWS) – Nandoni Distribution Scheme 5.Water Services

10 10 1. ORWRDP PHASE 2: DESCRIPTION & PURPOSE 88m high De Hoop Dam (R3 075 million) on Steelpoort River – Implementation by DWA Extensive bulk distribution systems (pump stations, balancing dams and pipelines) from De Hoop and Flag Boshielo Dams (R million) Implementation by TCTA Primary water supply in Middle Olifants River catchment area – Regional Bulk and Reticulation (R6 812 million) Industrial water for mining on eastern limb of Bushveld Igneous complex

11 11 1. ORWRDP (DE HOOP) REGIONAL BULK AND PRIMARY RETICULATION TO HOUSEHOLD FEASIBILITY STUDIES Bulk and Internal Bulk (Rand million) Reticulation (Rand million) Total (Rand million) MOOIHOEK TO TUBATSE AND BURGERSFORT DE HOOP TO JANE FURSE AND NEBO PLATEAU PRUISSEN TO MOKOPANE AND MOGALAKWENA LM OLIFANTSPOORT TO CAPRICORN (LEPELLE- NKUMPI) OLIFANTSPOORT TO POLOKWANE (OLIFANTS SAND) OLIFANTSPOORT SOUTH (FETAKGOMO) LEBALELO TOTAL

12 12

13 13 1. ORWRDP PHASE 2: SCHEDULE (Subject to availability of funding) 2A: June 2007 – Mar B: Jul 2011 – Dec C: Jul 2011 – June 2013 (Steel Bridge: July 2012) 2D: Jul 2011 – June E: April 2012 – March F: April 2012 – March G: April 2012 – March H: Incorporated by March 2013

14 14 1. ORWRDP PHASE 2: PROJECT RISKS & MITIGATION Level of commitment by mines and municipalities due to effects of ongoing global recession High social demands Affordability High cost of scheme Reliance on electricity for pumping Alignment of completion of water resources & services infrastructure Implement GWW with government funding Implement WC & DM Government funding Step wise implementation within funding constraints Align with Eskom’s developments Aligned planning and water supply agreements

15 15 2. MCWAP: DESCRIPTION & PURPOSE Augmented water supply in the Lephalale area to meet the water requirements of the Medupi Power Station, and the future water requirements related to the expected growth in the Lephalale Municipality Industrial water for possible CTL plant by Sasol Phase 1 (R2 059 million) includes a new pump station at Mokolo Dam and pipeline to Medupi and Matimba Power Station, Exxaro mine and Lephalale town Sub-phase 2A (R million): Abstraction works at Vlieëpoort and BDS to Steenbokpan and Lephalale areas Sub-phase 2B (R1 590 million): Duplication of BDS Social/Commercial portion on/off-budget TCTA implementing agent Regional Bulk and Reticulation (R 330 million)

16 16

17 17 2. MCWAP: SCHEDULE (Subject to environmental authorisation and Integrated Resource Plan (IRP) for electricity) MCWAP-1: July 2011 – July 2013 MCWAP-2A: Jan 2013 – Dec 2016 MCWAP-2B and further phases: Depends on IRP and investment decisions by the private sector and other stakeholders

18 18 2. MCWAP-1 AND 2A: PROJECT RISKS & MITIGATION Likelihood of appeals against environmental authorisation high Very tight construction programme Affordability of water by social users Delayed IRP for electricity High dependence on single resource, i.e. Mokolo Dam Concerted efforts to deal swiftly with possible appeals Efficient implementation strategies and contract management Government funding Co-operative governance Investigate and implement additional and alternatives sources

19 19 3. GLeWAP: DESCRIPTION & PURPOSE 36m high Nwamitwa Dam (R1 262 million) on Groot Letaba River – Implementation by DWA 3m raising of Tzaneen Dam (R84 million) Regional Bulk Water supply (R410 million) Provide primary water requirements in Mopani District To implement the preliminary Reserve in compliance with the National Water Act To stabilise the assurance of supply to the existing irrigation farming To improve water availability for the establishment of resource- poor irrigation farmers

20 20

21 21 3. GLeWAP: SCHEDULE (Subject to environmental authorisation and funding) Tzaneen Dam Raising: 2013/14 Nwamitwa Dam: 2016/17 Regional Bulk: 2015/2016

22 22 3. GLeWAP: PROJECT RISKS & MITIGATION RISKSMITIGATION Likelihood of appeals against environmental authorisation Concerted efforts to deal swiftly with possible appeals Very tight construction programme Efficient implementation strategies and contract management Affordability of water by social users Government funding Funding constraintsPhased implementation & rescheduling Skills shortageTraining programmes

23 23 4. LRGWS – Nandoni Distribution Scheme: Description & Purpose The Nandoni Dam and Distribution scheme forms part of the larger Luvhuvhu River Government Water Scheme (LGWS) which also includes the Xikundu scheme The project was initiated to provide potable water to the area between Thohoyandou and Makhado after the completion of the Nandoni Dam The Nandoni Distribution projects were started in 2005 in conjunction with the Nandoni WTW after completion of the Nandoni Dam and includes: –3 bulk pipelines takes water from Nandoni WTW to various reservoirs –NR6 and NN20B pipelines takes water in a northerly direction –3 bulk pipelines takes water from Nandoni WTW to various reservoirs –NR5 pipeline takes water in a southern and western direction Estimated cost for the completion Nandoni Distribution Scheme is R701 million

24 24

25 25 4. LRGWS: SCHEDULE DWA approved the accelerated plan to complete the Nandoni Distribution Scheme’s bulk water pipelines up to the Valdezia Reservoir Tender for PSPs to redesign the bulk water pipelines did close Water delivery dates are as follows: –Thohoyandou CBD (via NR6 Reservoir and Rising Main) by October 2011 –Mavambe to Gumbani and Mudabula (via Mavambe to Gumbani Rising Main, Gumbani Reservoir and Pump Station). Water was already being delivered as from 17 June 2010 Greater Vuwani Area(Vuwani (NR7) Reservoir and Rising Main) by August 2012 –Valdezia Area (Valdezia Reservoir and Rising Main) by November 2012 –Mushiri, Mahagala and Lambani (Lambani Gravity Main) by October 2011 –Peri-urban areas east of Thohoyandou (NN20B Reservoir and Rising Main) by October 2011 The water from the bulk distribution systems will feed into the existing local reticulation systems

26 26 4. LRGWS: PROJECT RISKS & MITIGATION RISKSMITIGATION Quality control of constructionAdequate site supervision including dedicated Resident Engineer Productivity of local labourImplementing management controls to increase productivity Condition of existing municipal water infrastructure Municipal infrastructure refurbished or replaced by Municipalities where critical e.g. control valves at reservoirs Extended lifespan of bulk water infrastructure (quality of materials and installation) Independent 3 rd party inspectors and warrantees

27 27 Bulk Water Supply in Limpopo - RBIG Scheme District Municipality (Water Services Authority) Total Project Costs RBIG Expenditure to date (2007/8/9/10) RBIG Budget 2010/11 RBIG Budget 2011/12 RBIG Budget 2012/13 Olifantspoort WTW Capricorn 303,527,528173,000,00023,000,00020,000,0000 Specon BWS Capricorn 74,316,00039,500,00019,000,00000 Mametya Sekororo Mopani 214,000,00010,000,0007,000,00048,000,00051,789,000 Giyani BW Supply Drought Relief Mopani252,000,000054,000,00000 Groblersdal Lukau BWS Greater Sekhukhune 36,208,00030,508, Nebo BWS Greater Sekhukhune1,379,480,00053,934,76928,000,00060,000,00077,000,000 Mooihoek/Tubatse BWS Greater Sekhukhune1,000,000,00050,956,72813,000,00048,000,00070,000,000 Sinthumule Kutama BWA Vhembe 454,979,47534,314,59516,000,00051,000,00044,500,000 Mogalakwena BWS Mogalakwena1,530,000,00066,571,83227,000,00060,000,00082,700,000 5,244,511,003458,786,447187,000,000287,000,000325,989,000 Table 1: List of RBIG projects and funding for 2010/11, 2011/12 and 2012/13

28 28 Bulk Water Supply in Limpopo - RBIG Estimated total cost of 9 projects R Minus RBIG expenditure 2007/8/9/10 R Minus RBIG Budget 2010/11/12/13 R R Shortfall for 9 current projects to be completed R

29 29 Bulk Water Supply in Limpopo - RBIG In addition to the projects being implemented, Table 2 illustrates projects at feasibility, or implementation ready study stage that were funded through the RBIG.

30 30 Bulk Water Supply in Limpopo - RBIG Scheme District Municipality (Water Services Authority) Total Project Costs RBIG Expenditure to date (2007/8/9/10) RBIG Budget 2010/11 RBIG Budget 2011/12 OhrigstadGreater Sekhukhune Lebalelo Central & North RWS Greater Sekhukhune Nwamitwa RWS Scheme(Great Letaba) Mopani Nzhelele Valley BWSVhembe Makhado West and Extension to Nandomi Dam Vhembe Matoks RWSCapricorn Glen Alphine RWSCapricorn Lephalale - Bulk Water Augmentation(Eskom) Waterberg Magalies Water to Waterberg Waterberg Sub Total

31 31 Bulk Water Supply in Limpopo - RBIG Minus RBIG expenditure 2007/8/9/10 R Minus RBIG Budget 2010/11/12/13 R R Estimated total cost of 9 IRS projects to implement R Shortfall for 9 current projects to be completed R Shortfall for 9 current IRS projects to be constructed R Total ShortfallR

32 32 Bulk Water Supply in Limpopo FUNDING The dams are funded by National Treasury Funds not so easily available for RBIG and Reticulation through MIG Example: De Hoop is funded at R3 billion by National Treasury. Bulk Distribution and reticulation to Households require R20 billion. R1.2 billion is available from 2007 to 2013 through RBIG and MIG. Shortfall of R18.8 billion is needed to serve 2 million people and mining. Mines and Municipalities not in a position to sign off take agreements with DWA.

33 33 Bulk Water Supply in Limpopo Example: RBIG is funding a pipe line from Steelbridge to Jane Furse – 70% completed Sekhukhune DM with MIG is on tender for WTW at Steelbridge and 10 Megaliter reservoir at Jane Furse for completion July DWA has to do Phase 2C pipe from De Hoop Dam to Steelbridge for completion July 2012 depending on funding from National Treasury.

34 34 Life cycle planning Cost of the Business PlanningDesignProcureConstructOperateMaintainRefurb. 0,2%2%17%44% Typical % of Total Cost over the Life of Water Supply Infrastructure 37% Financing Cost Based on actual local government case study (Paul le Roux)

35 35 Limpopo Picture Rand (bil) Identified Projects including:59.3 ORWRDP (De Hoop) MCWAP (Lephalale) GLeWAP (Nwamitwa) Waste Water Treatment Works Capital = 20%60.0 O&M 20 years = 40%120.0 Financing 20 years = 40%120.0 Total300.0

36 36 Needs Classification/Definition – Water Services Community with no water services at all Extension Upgrade Infrastructure needs O&M needs Resource needs Management Refurbishment Demand management Local source development Regional Bulk Internal Bulk Sewerage works Purification plants Interim Permanent Illegal settlement Formal rural Housing Program Backyard dwelling Shared services

37 37 Needs Classification/Definition - Sanitation Households with no sanitation services at all RDP – Pit/less than VIP Basic but not appropriate Infrastructure needs O&M needs Existing Services that needs to be replaced Management Refurbishment Buckets Other Other Programmes Health Sanitation needs Schools Sanitation needs Interim Permanent Illegal settlement Formal rural Housing Program Backyard dwelling Shared services

38 38 Backlog on Water: Households Priority (Infrastructure Status)Priority Adequate0 No Water Services1 Inadequate Infrastructure: Need Extensions2 Inadequate Infrastructure: Need Upgrade3 Inadequate Resources4 Inadequate Management: O & M5 Inadequate Management: Refurbishment6 Inadequate Housing: Interim7 Inadequate Housing: Permanent8

39 39 LIMPOPO WATER CHALLENGES EQUITABLE SHARES Currently R5 / kiloliter (1000 liters) ORWRDP at Nebo estimated R25 / kiloliter (1000 liters) 85% indigents to get 6 kiloliter free households (4 people / hh) x 6kl x 12months x R20 = R288 mil per year

40 40 STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND CHALLENGES Total Water Business – Industry, Agriculture, Tourism and People Single Purpose Dams Water Services Provider – Cross Border Issues WSDP requirements – Water Resource Planning & Internal Strategic Perspective Priorities of backlogs Eradicate per priority Water Resource shortfall (De Hoop) Funding shortfall – RBIG, MIG, ACIP Water Services Reference Framework - MIG Projects outstanding Redesign EQUITTABLE SHARE formula

41 41 STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND CHALLENGES Cont….. Materials availability Manpower Inexperienced PSPs and Contractors Supply Chain Not enough resources to support Population Growth Population development require higher water needs

42 42 THANK YOU Bernie Badenhorst Tel Cell c\:My Documents\Dept Premier\Premier’s Intergovernmental Forum