Presentation is loading. Please wait.

Presentation is loading. Please wait.

DVM PLUS III INSTALLATION

Similar presentations


Presentation on theme: "DVM PLUS III INSTALLATION"— Presentation transcript:

1 DVM PLUS III INSTALLATION
(Preliminary)

2 DVM PLUS III line up

3 Space requirements 1) Single installation 2) Group installation

4 Installing outdoor unit

5 Anchor bolt position

6 Remove stopper ■ Remove stopper
√ 10 Ton : 4 pieces of stopper in legs of compressor The stopper is just using only for transportation, not operation

7 Piping layouts (HP) ■ Y joint only ■ Y joint with Header joint

8 EEV Kit

9 Piping length (HP) Y joint Main pipe 1st Refnet Joint

10 Piping length (HP)

11 Piping length (HP)

12 Main pipe 1 size increasing
Examples Example) 34 HP With 1 bigger size, it can increase cooling capacity by 16.8 %.

13 Selection the refrigerant pipe
1. 명기된 사양은 개발진행에 따라 변경 될 수 있습니다. 2. 배관은 미주 지역에서 구입 가능한 배관으로 선정되어 있습니다. 현지에서 구매가 불가능한 배관을 제외(1, 1 ¼, 1 ½ )하였기에, 배관 선정 사양이 기존의 DVM PLUS 2 대비 해서, 변경될 소지가 있으니 참고 하시길 바랍니다. (위에 말씀 드린 것처럼 첨부된 문서의 설치 사양은 변경될 소지가 있습니다.)

14 ■ Definitions A1 Branched pipes from outdoor joints to outdoor A2
Outdoor unit A1 Branched pipes from outdoor joints to outdoor A2 Branched pipes between outdoor joints A3 Main Pipes Branched pipes between branch joints B C Pipes to indoor units D Outdoor joints E, F Branch joints (Indoor joints)

15 ■ Step 1 – Select pipes to outdoor units from ‘outdoor joints’
Piping Diameter for each Outdoor unit (A1) Ton HP Liquid Gas H.P. Gas mm inch 6 7.5 9.52 3/8 19.05 3/4 15.88 5/8 8 10.0 22.23 7/8 10 12.5 12.70 1/2 28.58 1 1/8 A1 Piping Diameter for between outdoor joints (A2) Ton HP Liquid Gas H.P. Gas mm inch 6 7.5 9.52 3/8 19.05 3/4 15.88 5/8 8 10.0 22.23 7/8 10 12.5 12.70 1/2 28.58 1 1/8 12 15.0 14 17.5 16 20.0 18 22.5 20 25.0 34.93 1 3/8 22 27.5 24 30.0 26 32.5 28 35.0 30 37.5 ■ Step 2 – Select pipes between outdoor joints A2

16 Piping Diameter for “Main” pipes (A3)
■ Step 3 – Select “Main” pipes Piping Diameter for “Main” pipes (A3) Ton HP Liquid Gas H.P. Gas mm inch 6 7.5 9.52 3/8 19.05 3/4 15.88 5/8 8 10.0 22.23 7/8 10 12.5 12.70 1/2 28.58 1 1/8 12 15.0 14 17.5 16 20.0 18 22.5 20 25.0 34.93 1 3/8 22 27.5 24 30.0 26 32.5 28 35.0 30 37.5 A3

17 Main Pipe Diameter (A3) in case of the farthest indoor unit over 90m
■ Step 3 – Upsizing “Main” pipes, When? Main Pipe Diameter (A3) Ton HP Liquid Gas H.P. Gas mm inch 6 7.5 9.52 3/8 19.05 3/4 15.88 5/8 8 10.0 22.23 7/8 10 12.5 12.70 1/2 28.58 1 1/8 12 15.0 14 17.5 16 20.0 18 22.5 20 25.0 34.93 1 3/8 22 27.5 24 30.0 26 32.5 28 35.0 30 37.5 Outdoor unit A3 The farthest indoor unit Main Pipe Diameter (A3) in case of the farthest indoor unit over 90m Ton HP Liquid Gas H.P. Gas mm inch 6 7.5 12.70 1/2 22.23 7/8 19.05 3/4 8 10.0 28.58 1 1/8 10 12.5 15.88 5/8 12 15.0 34.93 1 3/8 14 17.5 16 20.0 18 22.5 20 25.0 22 27.5 24 30.0 26 32.5 28 35.0 41.28 1 5/8 30 37.5 If the piping length between outdoor to the farthest indoor unit is over 90m (295ft), use right table. A3

18 ■ Step 4 – Select ‘Outdoor joints’
Model Name Outdoor unit’s capacity Liquid & low Pressure gas pipe MXJ-T3819K 12 ~ 30 Ton High Pressure gas pipe MXJ-T3100K D ■ Step 5 – Select the first ‘Branch joints’ Model Name Outdoor unit’s capacity Liquid & low Pressure gas pipe Joints MXJ-YA2512K 6, 8,10 Ton MXJ-YA2812K 12 Ton MXJ-YA2815K 14,16,18,20 Ton MXJ-YA3119K 22, 24, 26, 28 Ton MXJ-YA3819K 30 Ton High Pressure gas pipe Joints MXJ-YA1500K 6 Ton MXJ-YA2500K 8, 10, 12, 16, 18 Ton MXJ-YA3100K 20, 22, 24, 26, 28, 30 Ton E

19 ■ Step 5 – Example RVXVHT100FE RVXVHT125FE RVXVHT125FE
Liquid : 1/2 Gas : 1 1/8 Liquid : 1/2 Gas : 1 1/8 (A1) (A1) Liquid : 3/8 Gas : 7/8 Liquid : 5/8 Gas : 1 1/8 (A1) (A2) A2 capacity = A1 capacity + A1 capacity Example) A1 : 7.5 HP → Liquid : 3/8”, Gas : 3/4” A2 : 15.0 HP → Liquid : 1/2”, Gas : 1 1/8”

20 ■ Step 6 – Select branched pipes between ‘branch joints’
Total indoor unit's capacity Pipe Diameter (OD, mm/inch) Liquid Gas H.P. Gas mm inch 51 MBH↓ 9.52 3/8 15.88 5/8 51 ~ 79 MBH 19.05 3/4 79 ~ 96 MBH 22.23 7/8 96 ~ 138MBH 12.70 1/2 28.58 1 1/8 138 ~ 160 MBH 160 ~ 240 MBH 240 ~ 336 MBH 19.50 34.93 1 3/8 336 ~ 468 MBH B ■ Step 7 – Select ‘Branch joints’ Model Name Total indoor unit's capacity Liquid & low Presssure gas pipe Joints MXJ-YA1509 51 MBH and below MXJ-YA2512 Over 51 MBH ~ 138 MBH and below MXJ-YA2812 Over 138 MBH ~ 160 MBH and below MXJ-YA2815 Over 160 MBH ~ 240 MBH and below MXJ-YA3119 Over 240 MBH ~ 336 MBH and below MXJ-YA3819 Over 336 MBH ~ 468 MBH and below High Pressure gas pipe Joints MXJ-YA1500K 79 MBH and below MXJ-YA2500K Over 79 MBH ~ 240MBH and below MXJ-YA3100K Over 240 MBH ~ 468 MBH and below F

21 Pipe Diameter (OD, mm/inch)
■ Step 8 – Select pipes to indoor units Indoor unit's capacity Pipe Diameter (OD, mm/inch) Liquid Gas mm inch 6 ~ 20 MBH 9.52 3/8 12.70 1/2 24 ~48 MBH 15.88 5/8

22 Additional refrigerant
√ Additional refrigerant has to be charged according to the length and size of liquid pipe. Liquid pipe size (O.D. mm) Additional refrigerant charging (lbs/ft) Φ 1/4 (Φ 6.4) Φ 3/8 (Φ 9.5) Φ 1/2 (Φ 12.7) Φ 5/8 (Φ 15.9) Φ 3/4 (Φ 19.1) Φ 7/8 (Φ 22.2) MCU lbs Each MCU 1.1 Liquid line after expanding (From Sing EEV kits, or From MCUs) Each liquid line 0.022

23 Outdoor joint (HP, HR) Ex) MXJ-T3819*, MXJ-T4422 - Liquid connection
- Gas connection

24 Outdoor joint (HR Only)
Ex) MXJ-T3100* - High pressure gas connection

25 Y- joint (HP, HR) Ex) MXJ-YA1509

26 Y- joint (HR Only) Ex) MXJ-YA1500 ~ MXJ-YA3800

27 Header- joint (HP only)
Ex) MXJ-HA2512

28 Outdoor units piping  ■ Refrigerant piping should be the same level or lower than connecting position. Correct piping work Wrong piping work Accumulating of oil

29 Outdoor units piping  ■ Refrigerant piping should be connected with side direction. Correct piping work Wrong piping work Unbalancing of Ref. & oil distribution Refrigerant can excessively leans to one direction.

30 Refrigerant can excessively leans to one direction.
Outdoor units piping  ■ Refrigerant piping should be connected with side direction. Correct piping work Wrong piping work Refrigerant can excessively leans to one direction.

31 Outdoor units piping  ■ Refrigerant piping should be installed in a horizontal direction. Correct piping work Wrong piping work Be horizontal Min. 4 inch

32 Outdoor units piping Vertical trap ■ Vertical trap Correct piping work
Wrong piping work 8 ~ 12 inch 40 inch 80 inch Vertical trap 80 inch

33 ■ Connecting the outdoor unit pipe
Outdoor units piping  ■ Connecting the outdoor unit pipe Single installation Module installation Front connection Front connection Oil valve size : 1/4 inch Bottom connection Bottom connection

34 Refnet Y Joint Installation
Horizontally installed Vertically installed Vaporized refrigerant leans to upper direction in Y joint. For uniform refrigerant distribution

35 Header joint installation Refnet Head Joint Installation
Liquid head Joint Vaporized refrigerant leans to one of direction in branch joint. Header Joint Gas head Joint Do not install vertically.

36 Header joint installation
Connect according to larger capacity of indoor unit in order

37 Piping work Taping Nitrogen replacement before brazing
Without nitrogen gas blowing With nitrogen gas blowing

38 Insulation work ※ Application condition : indoor temperature : 80℉, 80% RH

39 Insulation work

40 Insulation work

41 Wiring work 3 Phase 3 wires Caution
Be sure to install the switch and the fuse to the power line of each equipment. (Field wiring work)

42 Use ring terminal for wiring terminal block
Wiring work Caution of wiring work 208 ~ 230V 208 ~ 230V 208 ~ 230V Hold wiring with using cable tie Note Use ring terminal for wiring terminal block

43 Wiring work

44 Leak test

45 Oil piping should be performed a vacuum
Vacuum drying Oil piping should be performed a vacuum

46 Setting option switch PCB Outdoor’s control part BLDC Fan Driver
Transformer Filter PCB Magnet CT Sensor BLDC Fan Driver Power TB Outdoor-indoor unit communication Outdoor – outdoor unit communication

47 Setting option switch Sensor 220 V output

48 Setting option switch

49 conventional flare tool
INSTALLATION TOOLS – Exclusive Use to R410A Tool Using reason Specification Manifold gauge    R410A is composed H-F-C as different as R22 is composed C-F-Cl. Don't use mineral oil when gauge pressure to prevent contamination. Only for R410A. High pressure gauge : -0.1~5.3㎫ Low pressure gauge : -0.1~3.8㎫ Connection port diameter : 5/16 flare No oil used Manifold charging hose Change in service port diameter R410A has high pressure as compared with R22. It should be made of materials are not affected a using refrigerant. Working pressure : 5.08㎫ Bursting pressure : 25.4㎫ Vacuum pump     R410A is used with a ploy ester oil but a vacuum pump uses a conventional mineral oil. The degree of vacuum is  5torr Ÿ Need a check valve to prevent reverse oil flow if using a conventional vacuum pump Flaring Tool Need a flare gauge for R410A. When using a conventional flare tool, the pipe extension margin should be 1.0~1.5mm or 1.5~2.0. Torque spanners Increase a connecting torque. *Adding a proper torque to the pipe using R410A when connect pipes to flare nuts. Refrigerant oil Coat the connection with refrigerant oil film. If not, leakage is possible because of the pressure of R410A. Coat after flare work on pipe connection. All refrigerants are available as using a synthetic oil High rust resistance Long stability over long period time Gas leak tester       Since R410A don't have chlorine, the tester must can detect Hydrogen. R410A,R407C(E),R404A,R507A,R134a,R12,R22,R502,R500 are detected. Available in the range of 0 to 40℃. D A(㎜) flare tool fit on R410A conventional flare tool clutch type wing nut type 6.35 0~0.5 1.0~1.5 1.5~2.0 9.52 12.70 15.88 nominal dimension Torque (N·m) 6.35 14.2~17.2 9.52 32.7~39.9 12.70 49.5~60.3 15.88 61.8~75.4


Download ppt "DVM PLUS III INSTALLATION"

Similar presentations


Ads by Google