1 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA 01-186 Small Diameter Bomb (SDB) Program Public Overview Briefing Current As of: 24.

Similar presentations


Presentation on theme: "1 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA 01-186 Small Diameter Bomb (SDB) Program Public Overview Briefing Current As of: 24."— Presentation transcript:

1 1 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Small Diameter Bomb (SDB) Program Public Overview Briefing Current As of: 24 August 2001 Air Armament Center Lethal Strike JPO Eglin Air Force Base, FL

2 2 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Disclosure & Disclaimer Statements DISTRIBUTION A: This briefing has been cleared by AAC/PA (Public Affairs) for public release. This is briefing is UNCLASSIFIED. This presentation is for information only. No US Government commitment to sell, loan, lease, co-develop or co-produce defense articles or services is implied or intended.

3 3 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA OVERVIEW PROGRAM BACKGROUND PROGRAM BACKGROUND OPERATIONAL REQUIREMENTS OPERATIONAL REQUIREMENTS PROGRAM SCHEDULE PROGRAM SCHEDULE

4 4 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Program Background MMC Mission Need Statement, ACAT Level II, Oct 97 MMC Mission Need Statement, ACAT Level II, Oct 97 –Increase kills per sortie –Increase aircraft loadout –Accommodate current and future aircraft –Kill fixed, relocatable and mobiles targets Milestone 0 decision Feb 98 Milestone 0 decision Feb 98 –Perform concept and trade studies –Evaluate both weapons and carriage systems HQ ACC, AAC, and AFRL performed Analysis of Alternatives (AoA) HQ ACC, AAC, and AFRL performed Analysis of Alternatives (AoA) –22 approaches evaluated –Government and Industry proposed methods

5 5 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Program Background (con’t) Air Force Research Lab Munitions Directorate (Eglin AFB FL) demonstrated technologies Air Force Research Lab Munitions Directorate (Eglin AFB FL) demonstrated technologies Four Concept Study Contracts awarded 1999 ($250K each) Four Concept Study Contracts awarded 1999 ($250K each) –Boeing, Lockheed Martin, Northrop Grumman, Raytheon –Conducted trade studies, defined concepts Four contracts modified 2000 (adding $1.3M each) Four contracts modified 2000 (adding $1.3M each) –Develop and tested seeker and ATR algorithms –Characterized seeker/ATR in operational environment –Continue algorithm development

6 6 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA REQUIREMENTS

7 7 MMC Umbrella SDB Fixed SDB Mobile Miniaturized Munitions Concept Phase I Phase II Wide Area Search Autonomous Attack Miniature Munition (WASAAMM) Future Common Carriage System SDB Program Covers Phase I and Phase II

8 8 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Requirements Schedule #1 Priority: field systems soonest Schedule #1 Priority: field systems soonest Cost #2: Affordability, obtain price commitments Cost #2: Affordability, obtain price commitments Performance #3 Performance #3 –Phase I: GPS/INS-like accuracy (fixed/stationary) –Phase II: Seeker/ATR-like accuracy (mobile/relocatable) 2 KPPs: 2 KPPs: –Loadout –4 weapons per 1760 aircraft station is threshold –Interoperability –Common carriage system & interface across aircraft –Compatible with C4ISR infrastructure

9 9 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Requirements (con’t) Evolutionary approach to fielding systems Evolutionary approach to fielding systems –Phase I: Effective in GPS Jammed Environment –Phase II: Target Recognition for Autonomous Engagement in Limited Search Area ORD Will Remain DRAFT until Milestone B decision ORD Will Remain DRAFT until Milestone B decision –KPPs are only non-tradables –CAIV : performance trades between MS A and MS B –HQ ACC finalize performance “thresholds” after seeing cost & schedule impacts to program

10 10 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Requirements (con’t) Aircraft Integration Aircraft Integration –Threshold Aircraft: –Phase I: F-15E –Phase II: F-15E, F-16C/D and B-1B –Objective Aircraft: –Phase I: A-10, F-16, F-117, F-22, JSF, B-1, B-52, B-2, UCAV –Phase II: A-10, F-117, F-22, JSF, B-52, B-2, UCAV Aircraft Loadouts Aircraft Loadouts A-10 F-15E F-16 F-22 F-117 JSF B-1 B-2 B-52 UCAV Stations TBD Threshold* TBD Objective TBD *Threshold: 4 SDB weapons per 1760 interface

11 11 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Commonality across all threshold and objective aircraft Commonality across all threshold and objective aircraft –Standard test equipment, training, containers, loading procedures, etc. –Compatibility with B-2 Smart BRA MIL-STD-1760 interface MIL-STD-1760 interface –Minimize aircraft OFP impact, single update –Must support individual weapon targeting, fuze programming, weapon release initialization, weapon status reporting and weapon software reprogramming Individual and ripple release against one or more targets Individual and ripple release against one or more targets –No single use devices for weapon ejection system Carriage System Requirements

12 12 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA PROGRAM SCHEDULE

13 13 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA SDB Program Schedule FY02FY04FY05FY06FY03FY07FY08 LRIP FY01 OCT JANAPRJULOCT JANAPRJULOCT JANAPRJULOCT JANAPRJULOCT JANAPRJULOCT JANAPRJULOCT JANAPRJULOCT JANAPRJUL CAD Development & System Integration System Development & Demo – 1 LRIP Phase 1 Fixed Target SDB Common Carriage System Phase 2 Mobile Target SDB System Development & Demo – 2 LRIP Production Prod Seeker/ATR Advanced Development SysInt Seeker Design & Maturation GPS/INS Variant MS A MS B MS C2 MS C1 = Decision Review Downselect RFP CA

14 14 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Development & System Integration 2 Contractors = 24 months 2 Contractors = 24 months –Design and test warhead, fuze, GPS/INS guidance, carriage for fixed target SDB –Develop common aircraft ICD –Verify system level performance requirements are achievable for fixed target variant –Concurrent development and maturation of seeker/ATR algorithms –Develop and test Seeker/ATR –Verify costs are below threshold amount for fixed target SDB and delta for mobile target variant

15 15 Dist A: UNCLASSIFIED, Cleared for unlimited Public Release AAC/PA Further Questions & Inquiry Mail to: AAC/YV Attn: Small Diameter Bomb Program Office Suite West D. Ave. Eglin AFB FL DSN Prefix: 872 Voice Phone: (850) x2233 Data Fax