One Way to Develop Top 3 Critical Paths Angelo Arcoleo 18 May2011 1.

Similar presentations


Presentation on theme: "One Way to Develop Top 3 Critical Paths Angelo Arcoleo 18 May2011 1."— Presentation transcript:

1 One Way to Develop Top 3 Critical Paths Angelo Arcoleo 18 May2011 1

2 2

3 3

4 1- Select your program end-deliverable as your Primary CP end-task. 4 Using Gantt Chart view, select end-deliverable task to define Primary Critical or Driving Path

5 Use the ‘Find Path to Selected Task’ icon to run macro and find controlling predecessors 5

6 Use the Driving Path Widget to find controlling predecessorsDriving Path Widget 6 The Driving Path Widget locates all predecessor tasks that drive a specific task. Have you ever looked at a long list of predecessor tasks in a project and wondered which one is causing the schedule delay? With the Driving Path Widget, you will stop wasting time manually checking tasks to identify a path of predecessors that determine any given task’s schedule. Just select a task and push the "Driving Path" toolbar button. Available from: Project Widgets The Driving Path Widget locates all predecessor tasks that drive a specific task. Have you ever looked at a long list of predecessor tasks in a project and wondered which one is causing the schedule delay? With the Driving Path Widget, you will stop wasting time manually checking tasks to identify a path of predecessors that determine any given task’s schedule. Just select a task and push the "Driving Path" toolbar button. Available from: Project Widgets

7 Select Yes when warning pops-up. Four fields (2-Text, 2-Flag) are used in this macro; Then select View 09 - Path Gantt Chart to view results FYI: Here’s what these fields are titled… 7

8 Use View 09 – Path Gantt Chart, to see path leading to that task 8 Sort by DP, Then by Finish

9 Select PS-UID Column in MS Project Copy and Paste into Excel for DP numbering then Copy DP # and Paste into DP field 9 Smart DP numbering helps to define subsystem, automatically define DP/CP and sort tasks in sequential order Driving path step subsystem

10 Add Formula for CP, if missing… CP will populate as a function of DP In a Master Shell environment, using a subsystem prefix in DP field helps identify what subsystem a paths lies. 10

11 Review and adjust DP order to eliminate schedule “knots”, then Sort by DP, Then by Finish 11 Schedule “knots” are out-of-sequence tasks. Manual renumbering smart DP ID fixes this situation.

12 2- Setting a temporary deadline on selected end-deliverable task, 2 months before contract end-date Set task Deadline: 2 months earlier, to create a negative TS condition… 12 Deadline can be set earlier, depending on the level of “sensitivity” you want to temporarily “push” TS.

13 3- Performing Total Slack analysis to determine remaining Critical or Driving Paths Select view Total Slack Analysis 13

14 Filter-out CP#1 (CP contains blank) 14

15 Copy PS-UID for Secondary Critical or Driving Path, Paste in Excel and Number Driving Path 15 Review and adjust DP order to eliminate any schedule “knots”, Sort by DP, Then by Finish

16 Define Tertiary Critical Path You can manually number DP for short paths You may need to further “push” the deadline to define 3 rd DP 16 Review and adjust DP order to eliminate any schedule “knots”, Sort by DP, Then by Finish

17 4- View Top 3 Critical Paths Select view 08 – Top 3 Critical Paths 17

18 4- View Top 3 Critical Paths Select view 08 – Top 3 Critical Paths 18

19 Reset Deadline 19

20 View Top 3 Critical or Driving Paths 20 Done!

21 Key Concepts Driving Path vs. Critical Path Smart Driving Path Numbering Critical Path formula Standard Views Gantt Chart Total Slack Analysis Path Gantt Top 3 Critical Paths Smart PS-UID Total Slack in Calendar Days 21 THANK YOU! View Top 3 Critical or Driving Paths This concludes (one way ) “How to Perform Critical Path Analysis” and Develop a Top 3 Critical Path Chart Questions?

22 Credits: Driving Path Macro – Created by Ken Jamison, Project Widgets Corp: Fax: Delivering Microsoft Project consulting, training and software solutions. Sponsor –Joanne Greene-Blose, PMPPresident and CEO The Project Solvers of America, Inc. One Grove St, Suite 216A, Pittsford, NY Presenter:Angelo Arcoleo, PMP Cell: View Top 3 Critical or Driving Paths

23 ANGELO ARCOLEO brings over 30 years experience in engineering, project management, planning and trainer assisting organizations by leading projects and teams to plan and help execute critical projects. Angelo brings many years of program and business experience and best practices to every Project. His passion for what he does, self-motivation, quiet-leadership and ability to work with many people and teams assures program success. He is a professionally trained Civil Engineer, BS, Rochester Institute of Technology; Town of Webster Planning Board member and Master Scheduler for ITT – Geospatial Systems Division; Orange Belt in Microsoft ® Office Project; and President of MPUG (Western New York Chapter, Microsoft ® Project Users Group)


Download ppt "One Way to Develop Top 3 Critical Paths Angelo Arcoleo 18 May2011 1."