Singleton Project New 8-ine breaker-and-a-half 345-kV station. Increase North-Houston limit by approximately 700 MW. Increase switching flexibility and.

Similar presentations


Presentation on theme: "Singleton Project New 8-ine breaker-and-a-half 345-kV station. Increase North-Houston limit by approximately 700 MW. Increase switching flexibility and."— Presentation transcript:

1 Singleton Project New 8-ine breaker-and-a-half 345-kV station. Increase North-Houston limit by approximately 700 MW. Increase switching flexibility and shorten line lengths. Construction Outages started Spring 08 Remaining Outages to energize station are planned for 3/4/2009 to 4/21/2009

2 Singleton Current Configuration (line model)

3 Singleton Outages: Jewett-THW GC - RP

4 Singleton Outages: GC – Singleton Jewett – Singleton Completed: Singleton-THW

5 Singleton Completed: GC – Singleton Jewett – Singleton THW - Singleton

6 Singleton Completed: GC – Singleton Jewett – Singleton THW – Singleton Outages: Jewett – Tombal

7 Singleton Completed: GC – Singleton Jewett – Singleton THW – Singleton Jewett -Singleton Tombal – Singleton RP - Singleton

8 Singleton Completed: GC – Singleton Jewett – Singleton THW – Singleton Jewett -Singleton Tombal – Singleton Outages: GC - Obrien

9 Singleton Completed: GC – Singleton Jewett – Singleton THW – Singleton Jewett -Singleton Tombal – Singleton Outages: GC - Obrien

10 Singleton Mid-April 2009 Final Configuration (line model)


Download ppt "Singleton Project New 8-ine breaker-and-a-half 345-kV station. Increase North-Houston limit by approximately 700 MW. Increase switching flexibility and."