Presentation is loading. Please wait.

Presentation is loading. Please wait.

NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.

Similar presentations


Presentation on theme: "NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE."— Presentation transcript:

1 NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

2 Agenda Welcome, Introductions and Safety Expectations and Goals for Meeting MPRP Project Update Other CMP/EMERA Maine Projects Specific Outage Discussion, Key Fall 2014/Spring 2015 outages Questions CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 2

3 Expectations/Goals Communicate significant planned 2014/2015 Maine transmission equipment outages that could impact generation constraints Communicate specific outage coordination changes to limit impact on potential generation constraints Respond to outage coordination questions from the audience CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 3

4 MPRP Project Statistics 452 miles of new or rebuilt 345kV and 115kV Transmission 183 miles of new 345kV Transmission 105 miles of new 115kV Transmission 5 miles of Rebuilt 345kV Transmission 140 miles of rebuilt 115kV Transmission 8 miles of rebuilt 34.5kV Sub Transmission 11 miles of 345kV and 115kV line terminations 5 new Greenfield Substations Albion, Coopers, Monmouth, Larrabee, Raven 6 Major Substation expansions Maguire, South Gorham, Surowiec, Gulf Island, Belfast, Livermore Falls 50 Remote end substation expansions or modifications 60 - Transmission line crossings CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 4

5 Northern Loop Construction Construction Status – Belfast 115kV tap completed Near term construction activities – Coopers Mills Road Substation energization – Construction of one new 345kV line and one new 115kV line Future construction activities – None 5 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

6 Central Loop Construction Construction Status – Livermore Falls Substation energized – New 115kV line from Rumford to Larrabee Road energized Near term construction activities – Construction of one new 345kV line and rebuild of two 345kV lines Future construction activities – Completion of 115kV rebuilds – Completion of one new 345kV line and rebuild of two 345kV lines – Completion of Coopers Mills Road tie-ins and energization CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 6

7 Southern Loop Construction Status – Maguire Road 345kV energization – Construction of new Maguire Road – Eliot 345kV line complete Near term construction activities – Eliot Substation final energization – Maguire Road Substation final energization Future construction activities – None CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 7

8 CMP/EMERA Maine Capital and Maintenance Work Other Non-MPRP CMP Capital and Maintenance Work that affects the transmission system – Transmission Line Structure Replacements both Capital and Maintenance – System Planning related Substation rebuilds or expansions to support future reliability needs – Substation equipment replacements or upgrades to address maintenance concerns – Transmission Line re-rates or rebuilds to increase capacity – Substation maintenance equipment inspections and relay testing – Regulatory required relay and equipment trip checks CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 8

9 Maine 2014/2015 Transmission Outages Changes to plan typically result in increased construction cost – Costs include overtime, additional contractor resources, expedited material, additional engineering and outage coordination resources, environmental mitigation, schedule and remobilization costs, permitting, etc. Outages that have the potential for significant impact to generators in 2014/2015 will be discussed – Long (greater than one week) duration outages – Significant potential generation constraints CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 9

10 CMP Outage Applications Central Maine Power had 1,400 outage applications in 2013 There have been 517 transmission (>34.5kV) and 185 sub- transmission (34.5kV) outage applications in 2014 The MPRP Project has submitted 975 outage applications for the project through March 19, 2014 The outages range in duration from a few hours to eleven months in length The MPRP team anticipates that there will be an additional 300 – 400 outages needed to finish the program CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 10

11 TRANSMISSION SYSTEM LIMITATIONS All facility in and single facility out conditions CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

12 Transmission System Limits Impact On Generation Constraints Two categories of transmission system interface limits Wide Area – 13 Interfaces – Typically Include 345 kV and 115 kV facilities New Brunswick to New England Interface New England to New Brunswick Interface New England to New Brunswick + Keene Road Export Interface Orrington South Interface Orrington North Interface Orrington Import Interface Maine Yankee South Interface Surowiec South Interface Maine to New Hampshire Interface New Hampshire to Maine Interface Seabrook South Interface Northern New England Scobie & 394 Interface North to South Interface – All lines in limits typically range from ~1000 MW to ~4000 MW – Single Line Out Limits typically reduce limits by ~500 MW to ~800 MW CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 12

13 Transmission System Limits Impact On Generation Constraints Local Area - 7 Interfaces – Typically include 115 kV facilities Keene Road Export Interface Bangor Hydro Export Interface Keene Road + Bangor Hydro Export Interface Wyman Hydro Export Interface Inner Rumford Export Interface Outer Rumford Export Interface Western Maine Export Interface – All lines in limits typically range from ~150 MW to ~500 MW – Single Line Out Limits typically reduce limits by ~50 MW to 100 MW – Most significant recent generations constraints have been from local area constraints CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 13

14 2014 Maine Major Outages - Update 115 kV Outage Condition B Western Maine – 3 rd Qtr 2013 – 4 th Qtr 2013 ~ 3 month duration (Completed) – 2 nd Qtr 2014 ~ 2 week duration (Completed) 345 kV Outage Condition L Northern Maine Area – 1 st and 2 nd Qtr 2014 ~ 7 weeks (Completed) 115 kV Outage Condition M Western Maine – 2 nd Qtr 2014 ~ 1 week (Completed) 345 kV and 115 kV Outage Condition N Central Maine – 2 nd Qtr 2014 ~ 1 week (Completed) 345 kV Outage Condition O Northern Maine – 1 st outage 3 rd Qtr 2014 ~ 1 week (Completed live line) CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 14

15 2013-14 Maine Major Outages – Update (cont.) 345 kV Outage Condition O Northern Maine – 2 nd outage 3 rd Qtr 2014 ~ 2 weeks (completed) – 3 rd outage 1 st Qtr 2015 ~ 1 week 345 kV Outage Condition P Southern Maine – 3 rd Qtr 2014 ~ 1 week (completed) – 4 th Qtr 2014 ~2 weeks 345 kV Outage Condition Q Southern Maine – 4 th Qtr 2014 ~ 4 weeks 15

16 2013-14 Maine Major Outages – Update (cont.) 345 kV Outage Condition R Southern Maine – 1 st Outage 3 rd Qtr 2014 ~ 4 weeks (completed) – 2 nd Outage 4 th Qtr 2014 ~ 5 weeks 115 kV Outage Condition S Central Maine – 4 th Qtr 2014 through 1 st Qtr 2015 ~ 2 months 345 kV Outage Condition T Central Maine – 1 st Qtr 2015 ~ 2 weeks 16

17 345 kV Outage Condition O Northern Maine Most difficult outage to coordinate in New England – Historically Requires: Many contingencies result in controlled islanding of the Maritimes Must run specific generators Do not exceed limits on specific generators Minimum New Brunswick-New England Interface transfers Maximum Orrington South Interface transfers Results in almost all generators inside the Bangor Hydro + Keene Road Export Interface cannot operate Interface Limits – New Brunswick-New England Interface MINIMUM 200 MW – 300 MW – Orrington South Interface limit 200 MW – 300 MW 17

18 345 kV Outage Condition O Northern Maine (cont.) Potential options to be assessed, partial MPRP completions: – Assess if some of the outage can be accomplished live-line – Will assess a completely different approach to the outage to determine if it is more reliable, increases transfer capabilities, reduces impacts on generators ability to operate Eliminates 1 st contingency controlled islanding of the Maritimes Reduces must run of specific generators Reduces do not exceed limits on specific generators Generators inside the Bangor Hydro + Keene Road Export Interface able to compete for limited transfer capability 18

19 345 kV Outage Condition O Northern Maine (cont.) 3 rd outage 1 st Qtr 2015 ~ 1 week – This outage has been repositioned to occur after additional key MPRP facilities are completed that will increase limits – Planning to perform the outage with a completely different approach – Interface Limits New Brunswick-New England Interface Limits ~ 350 MW, also slave to Orrington South Interface Limits Orrington South Limits ~350 MW - 500 MW Keene Road Export Limit 155 MW 19

20 345 kV Outage Condition P Southern Maine 2 nd Outage 4 th Qtr 2014 ~ 2 weeks – Interface Limits Original Plan – Surowiec South Interface limits 50 MW – 400 MW Current Plan – Temporary transmission reconfiguration option utilized » Surowiec South Interface limits 500 MW – 650 MW » Orrington South Interface limits 450 MW » Wyman Hydro Export Interface limits 220 MW 20

21 345 kV Outage Condition Q Southern Maine 4 th Qtr 2014 ~ 4 weeks – Interface Limits Original Plan – Surowiec South Interface Limits 50 MW – 400 MW Current Plan – Temporary transmission reconfiguration option utilized » Surowiec South Interface limits 500 MW – 650 MW » Orrington South Interface limits 450 MW » Wyman Hydro Export Interface limits 220 MW – Outage timing has environmental considerations – Moved to overlap other outages Overlap reduces duration of significant interface limits There is less exposure to southern interface congestion – 2 nd Outage R » Maine-New Hampshire Limit of 1000 MW – 1700 MW » Northern New England Scobie + 394 Interface Limits 1300 MW – 2950 MW 21

22 345 kV Outage Condition R Southern Maine 2 nd Outage 4 th Qtr 2014 ~ 5 weeks Original plan for outages – Interface Limits » Maine-New Hampshire Interface Limits 200 MW – 300 MW Outage moved significantly until key MPRP facilities are completed Interface Limits – Maine-New Hampshire Interface Limits 1000 MW – 1700 MW – Northern New England Scobie + 394 Interface Limits 1300 MW – 2950 MW Moved to overlap other outages – Overlap reduces duration of significant interface limits – There is less exposure to southern interface congestion – 2 nd Outage 4 th Qtr 2014 » Outage Q - Surowiec South Interface Limits 500 MW – 650 MW Outage duration extended to complete additional maintenance work not related to MPRP 22

23 115 kV Outage Condition S Central Maine 4 th Qtr 2014 through 1 st Qtr 2015 ~ 2 months – Original plan Interface Limits – Wyman Hydro Export Interface Limits ~50 MW – ~75 MW Substantial impact to generators for a long duration – Current plan Construction sequencing modified to mitigate this exposure Interface Limits – Wyman Hydro Export Interface Limits ~150 MW – ~275 MW – Expecting ~150 MW limit for ~ 2 weeks in 4 th Qtr 2014 – Expecting close to ~275 MW limit for ~ 6 weeks 23

24 345 kV Outage Condition T Central Maine 1 st Qtr 2015 ~ 2 weeks – Original plan Interface Limits – Orrington South Interface limit ~ 500 MW – This outage has been repositioned to occur After additional key MPRP facilities are completed that will increase limits Overlap 3 rd Outage O for 1 st week – Overlap reduces duration of significant interface limits – 3 rd Outage O limits are more restrictive on the Orrington South Interface ~ 500 MW Outage T for 2 nd week – Interface Limits » Orrington South Interface limit ~600 MW 24

25 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 25

26 REFERENCES MPRP Geographic Overview Significant Maine Interfaces

27 MPRP Geographic Overview CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 27

28 Wyman Hydro Export Interface Wyman Hydro Export – All lines in-service limits do not currently exist – Single facility out limits exist Based upon two 115 kV lines remaining after limiting contingency – Limits due to stability performance (damping) 200 MW – 290 MW – Behind the constraint... ~ 360 MW of generation ~ 215 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 28

29 Inner Rumford Export Interface Inner Rumford Export – All lines in-service limits do not currently exist – Single facility out limits exist Limit based upon one 115 kV line remaining after limiting contingency – Limits due to stability performance (damping, unit stability and post-fault voltage recovery) 75 MW – 215 MW – Behind the constraint... ~460 MW of generation ~ 255 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 29

30 Outer Rumford Export Interface Outer Rumford Export – All lines in-service limits do not exist – Single facility out limits exist Limit based upon one 115 kV line remaining after limiting contingency – Limits due to stability performance (damping, unit stability and post-fault voltage recovery) 75 MW – 215 MW – Behind the constraint... ~645 MW of generation ~ 255 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 30

31 Western Maine Export Interface Western Maine Export – All lines in-service limits do not exist – Single facility out limits exist Limit based upon one 115 kV line remaining after limiting contingency – Limits due to stability performance (damping) 300 MW – 500 MW – Behind the constraint... ~1050 MW of generation ~ 470 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 31

32 Keene Road Export Interface Keene Road Export – All lines in-service limit 175 MW Based upon one 115 kV line remaining after limiting contingency – Limits due to stability (post- fault voltage recovery) – Facility out limits 0 MW – 120 MW – Behind the constraint... ~320 MW of generation ~ 90 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 32

33 Bangor Hydro Export Interface Bangor Hydro Export – All lines in-service limits do not exist – Single facility out limits exist Limit based upon two 115 kV lines and one or two 345/115 kV TX remaining after limiting contingency – Limits due to stability performance (damping, instability) 200 MW – 440 MW – Behind the constraint... ~940 MW of generation ~270 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 33

34 Bangor Hydro + Keene Road Export Interface Bangor Hydro + Keene Road Export – All lines in-service limits do not exist – Single facility out limits exist Limit based upon two 115 kV lines and one or two 345/115 kV TX remaining after limiting contingency – Limits due to stability performance (damping, instability) 200 MW – 580 MW – Behind the constraint... ~1250 MW of generation ~ 360 MW more proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 34

35 Orrington Import Interface Orrington Import – All lines in-service limits do not exist – Single facility out limits exist Limit based upon one 115 kV line remaining after limiting contingency – Limits due to stability performance (post fault voltage recovery, inter Area instability) 250 MW – 1250 MW – Behind the constraint... ~ 320 MW of generation ~ 1000 MW New Brunswick ~ 240 MW More proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 35

36 Orrington South Interface Orrington South – All lines in-service limit is 1050 MW - 1200 MW – Single facility out limits exist Numerous combinations – Limits due to thermal, voltage and stability performance 200 MW – 1200 MW – Behind the constraint... ~ 1120 MW of generation ~ 1000 MW New Brunswick ~ 510 MW More proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 36

37 Surowiec South Interface Surowiec South – All lines in-service limit is 1150 MW – Single facility out limits exist Numerous combinations – Limits due to stability performance (damping, unit stability and post-fault voltage recovery) 300 MW – 1150 MW – Behind the constraint... ~ 2480 MW of generation ~ 1000 MW New Brunswick ~ 1160 MW More proposed CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 37


Download ppt "NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE."

Similar presentations


Ads by Google