Community Soccer Fields Parks and Recreation Division December 3, 2013.

Similar presentations


Presentation on theme: "Community Soccer Fields Parks and Recreation Division December 3, 2013."— Presentation transcript:

1 Community Soccer Fields Parks and Recreation Division December 3, 2013

2 Presentation Outline  Purpose  Background  Funding  Potential Projects  Next Steps  Board Direction

3 Purpose Discuss community soccer fields throughout the county and seek BCC direction on funding and development of future soccer fields.

4 Background  October, 2013 BCC approved funding MLS Stadium  Orlando City Soccer agreed to fund O&M for up to 15 years at $200,000 per year  Other items agreed in MLS soccer stadium discussions – Donate property adjacent to Barber Park – Offer outreach programs to youth – Provide scholarships for youth soccer

5 Background  The County currently operates 15 athletic fields dedicated to youth soccer  Nine soccer fields have lights (7 regulation size)  Fields utilized by youth sports organizations – Rush Soccer Club at West Orange Park – South Orlando Soccer Club at Barber Park – Orlando City Youth Soccer League at Little Econ Soccer Complex and Arcadia Acres Park

6 Background Existing Soccer Field Locations

7 Funding Parks Impact Fee Fund

8 Funding Parks Impact Fees Fund Balance FY 2013-14 Land Acquisition Balance $ 500,000 Fund Reserves (excluding 5% target) $3,416,191 Available Funding $3,916,191 FY 2014-15 Projected New Revenue $3,100,000 Total Available Funding $7,016,191

9 Potential Projects Potential Community Soccer Field Locations

10 Potential Projects Potential Community Soccer Field Locations

11 Potential Projects New Parks Already Under Development Young Pine Park Includes 3 soccer fields, playgrounds, picnic pavilions, and associated infrastructure John Young Park Includes 2 soccer fields, playgrounds, picnic pavilions, and skateboard facility

12 Potential Projects Proposed Community Soccer Fields Barber Park  Located next to Barber Park  Finalize discussions to transfer property from City of Orlando  Construct 3 fields, lights, restroom, and infrastructure  Development Cost: $800k - $1.4m  Park Impact Fees may not be eligible

13 Potential Projects Proposed Community Soccer Fields Morgran Property  Will acquire through Developers Agreement  Located off of Alafaya Trail and Avalon Park Blvd.  Construct 3 fields, lights, restroom, and infrastructure  Development Cost: $800k - $1.4m

14 Potential Projects Proposed Community Soccer Fields Barnett Park  Located in Pine Hills Community  County owns 159 acres  Construct 1 field, lights, restroom, and infrastructure  Development Cost: $260k - $470k

15 Potential Projects Proposed Community Soccer Fields Dorman Property  Located on Ficquette Rd. in Horizon West  Currently in negotiations to purchase property  Construct 2 soccer fields, lights, restroom, and infrastructure  Development Cost: $800k - $1.4m

16 Potential Projects Proposed Community Soccer Fields East Orange Park  Located on Hwy. 50 in Christmas  County owns 243 acres  Construct 3 fields, lights, restroom, and infrastructure  Development Cost: $800k - $1.4m

17 Potential Projects Proposed Community Soccer Fields SJRWMD Property  Located on the North Shore of Lake Apopka  Determined to be surplus land by SJRWMD  In negotiations to donate to the County  Construct 2 fields, lights, restroom, and infrastructure  Development Cost: $800k - $1.4m

18 Potential Projects Park Development Costs Barber Park * 3 fields$800k – $1.4 mil Morgran Park3 fields$900k – $1.5 mil Barnett Park1 field$260k – $470k Dorman Property2 fields$665k – $1.4 mil East Orange Park 3 fields$855k – $1.3 mil SJRWMD Property2 fields$600k – $1.2 mil Totals: 14 fields $4.1 mil – $7.3 mil Parks Impact Balance FY 2013-14 FY 2014-15 Total $3,916,191$3,100,000$7,016,191 * Park Impact Fee Funds may not be eligible for park development costs. Project may be budgeted as part of future CIP.

19 Potential Projects Annual Operation and Maintenance Costs ($20k per field, $70k for staff, $10k utilities, per park) Barber Park (currently staffed)3 fields$ 60k Morgran Park3 fields$140k Barnett Park 1 field$ 20k Dorman Property2 fields$120k East Orange Park 3 fields$140k SJRWMD Property2 fields$120k Totals: 14 fields $600k Orlando City Soccer Contribution $200k($400k)

20 Next Steps  Continue with Park Development of John Young Park and Young Pine Park  Begin land acquisition and agreements  Initiate the design process  Budget amendment in January 2014  Bid and construct fields 2014/2015  Grand Openings – 2016

21 Board Direction  Allocate Park Impact Fee funds as indicated to develop community soccer fields  Finalize negotiations for the acquisition of Lake George Park from the City of Orlando


Download ppt "Community Soccer Fields Parks and Recreation Division December 3, 2013."