MONDAY 04 AUGUST 2003 WELCOME HAIVAN PASS TUNNEL CONSTRUCTION PROJECT.

Similar presentations


Presentation on theme: "MONDAY 04 AUGUST 2003 WELCOME HAIVAN PASS TUNNEL CONSTRUCTION PROJECT."— Presentation transcript:

1

2 MONDAY 04 AUGUST 2003

3 WELCOME HAIVAN PASS TUNNEL CONSTRUCTION PROJECT

4 Table of Contents Background of Project Description of Project Introduction of Each Package Message

5 Background of Project North – South longitudinal arterial in the country as the most important transport infrastructure of the national economy An integral part of international gateway – “East-West Corridor” connecting Thailand through Laos to Danang Port and Dung Quat Industrial Zone  Important role of National Highway No. 1

6 Background of Project  The Haivan pass section of the National Highway No. 1

7 Background of Project  Traffic on Haivan pass Results of Origin-Destination Survey during July 2002 Ho Chi Minh Hanoi 20 % of traffic volumes are between Ho Chi Minh City - Hanoi Danang Hue 30 % of traffic volumes are between Danang - Hue

8 Description of Project Begins at Km. 894+000 near Lang Co Town (Thua Thien–Hue Province) Ends at Km. 914+450 just north of Danang City Runs across the Haivan Pass peak at with an elevation of 475m, with a distance of 20.45 km Haivan Pass section is a very low standard highway. In spite of many efforts of Vietnamese government on upgrading this section, it is still a dangerous highway to drive and many lives lost each year in accidents on this section  The Haivan pass section of the National Highway No. 1

9 Description of Project Estimated Total Amount: USD 143,375,000 Implementation Program: Design stage: July 1998 – July 1999 Tendering stage: June 1999 – present Construction stage: October 2000 – April 2005 Design Standards: TCVN (Vietnam), JHPC (Japan) and AASHTO-1994 (USA) Design Life: Permanent Design Speed: 80 km/h Design Load: H30 – XB80 Construction Contract Packages: 9 packages  Project Outline

10 Description of Project Financing Agency: Japan Bank for International Cooperation (JBIC) L/A No. VNIV-5, March 26, 1997, Loan Amount JPY 5.5 billion L/A No. VNVI-5, March 30, 1999, Loan Amount JPY 10.0 billion L/A No. VNIX-4, March 29, 2002, Loan Amount JPY 3.359 billion Executing Agency: Ministry of Transport and Communication (MOT) Represented by Project Management Unit 85 (PMU85) Consultant Joint Venture of Nippon Koei Co., Ltd (Japan) and Louis Berger International Inc. (USA) In association with Transport Engineering Design Incorporation (TEDI) Vietnam  Organization Structure

11 Description of Project 1. Total Project Length: 12,182 m 2. Number of Traffic Lanes: 2 lanes 3. Tunnel Construction: Main Tunnel: 6,274m long, 2 lanes (3.75m wide/each), 89.0 m 2 Evacuation Tunnel: 6,286m long, 15.5 m 2 Ventilation Adit: 1895m long, 36.2 m 2 4. Bridge Construction: 8 bridges, 1,653 in total length 5. Highway Construction: 4,273m in total length  Major Features

12 Description of Project  Contract Packages NameTitleContractor Amount (1000 USD) Period (month) Construction Services14 724 PKIANorth Tunnel SectionJV Hazama – Cienco 643 25648 PKIBNorth Tunnel SectionJV Dong Ah – Song Da27 86348 PKIIA Lang Co Bridge Section JV Thang Long – Truong Son 4 63330 PKIIB Southern Highway Section JV Cienco 1 – Lung Lo – Vinawaco 3 92030 PKIII Electrical Works JO of ABB – Kinden – Vinainco 20 68626 PKIV Mechanical Works Matsushita – Itochu Consortium 23 05532 PKV 110/22kV Substation and 110kV Transmission Line JO of ABB – Kinden – Vinainco 7 25618 PKVI Procurement of Maintenance Vehicles 2 000 PKVII Infrastructure Development in the Resettlement Areas Construction Company No. 185 41308 TOTAL133 082

13 Description of Project  Implementation Program

14 Description of Project  Location of Contract Packages

15 Package IA – North Tunnel Section North Tunnel Portal

16 Package IA – North Tunnel Section Front Cut Away Section

17 Package IA – North Tunnel Section Cut Away Section

18 Package IA – North Tunnel Section Name of Contractor: Hazama (Japan) – Cienco 6 (Vietnam) Joint Venture Contract Amount: US$ 43,256,000 Contract Period: 48 months (10/2000 – 10/2004) Contract Chronicle: Contract Signing Date: August 17, 2000 Notice of Proceed: September 01, 2000 Commencement of Works: October 01, 2000 Location: Sta. 1+515 to Sta. 5+500  Contract Data and Chronicle

19 Package IA – North Tunnel Section

20 A 3,857m long 2-lane main tunnel with 73.26 m 2 cross- section A 3,857m long evacuation tunnel with 15.47 m 2 cross- section parallel to the mail tunnel Two (02) vehicular cross-passageways with 15.47 m 2 cross-section, and seven (07) pedestrian cross- passageways with 8.12 m 2 cross-section A 1,810m long tunnel ventilation adit with 36.20 m 2 cross-section Two 153 meters long each, by-pass type electrostatic precipitator tunnels (north & central) with 57.69m2 cross-section A 128 meters 2-lane tunnel approach A 403 meters long access road to adit building A 80m 2, one-story substation structure (building only) A north tunnel portal plaza and a ventilation adit portal plaza  Scope of Work

21 Package IB – South Tunnel Section South Tunnel Portal Area

22 Package IB – South Tunnel Section Front Cut Away Section

23 Package IB – South Tunnel Section South Tunnel Portal

24 Package IB – South Tunnel Section Name of Contractor: Dong Ah (Korea) – Song Da (Vietnam) Joint Venture Contract Amount: US$ 27,863,000 Contract Period: 48 months (10/2000 – 10/2004) Contract Chronicle: Contract Signing Date: August 17, 2000 Notice of Proceed: September 01, 2000 Commencement of Works: October 01, 2000 Location: Sta. 5+500 to Sta. 8+125  Contract Data and Chronicle

25 Package IB – South Tunnel Section

26 A 2,417 meters long 2-lane main tunnel with 73.26m2 cross-section A 2,429m long evacuation tunnel with 15.47 m 2 cross- section parallel to the mail tunnel Two (02) vehicular cross-passageways with 15.47 m 2 cross-section, and four (04) pedestrian cross- passageways with 8.12 m 2 cross-section A 153 meters long by-pass type electrostatic precipitator tunnels (south) with 57.69m2 cross-section A 208 meters 2-lane tunnel approach A 817 meters long access road to high water reservoir A 1,400m 2, one-story, vehicular maintenance building A south tunnel portal plaza A 58.45 meters long, 2-lane, 2-span post-tensioned girder bridge  Scope of Work

27 Package IIA – Lang Co Bridge Section Lang Co Bridge Area

28 Package IIA – Lang Co Bridge Section Lang Co Bridge

29 Package IIA – Lang Co Bridge Section Name of Contractor: Thang Long – Truong Son Joint Venture Contract Amount: US$ 4,633,000 Contract Period: 30 months (07/2001 – 12/2003) Contract Chronicle: Contract Signing Date: May 03, 2001 Notice of Proceed: June 01, 2001 Commencement of Works: July 01,2001 Location: Sta. –1+8650 to Sta. 1+515  Contract Data and Chronicle

30 Package IIA – Lang Co Bridge Section Lang Co Bridge, 876.390 meters total length; Two lane roadway, 782.610 meters total length A northern toll plaza; and Construction of 187m 2 area enclosed car port  Scope of Work

31 Package IIB – Southern Highway Section General View of Construction Site

32 Package IIB – Southern Highway Section Bridge in Design

33 Package IIB – Southern Highway Section Bridge in Design

34 Package IIB – Southern Highway Section Name of Contractor: Cienco 1 – Lung Lo - Vinawaco Joint Venture Contract Amount: US$ 3,920,000 Contract Period: 32 months (07/2001 – 03/2004) Contract Chronicle: Contract Signing Date: May 28, 2001 Notice of Proceed: June 26, 2001 Commencement of Works: July 26,2001 Location: Sta. 8+125 to Sta. 12+047  Contract Data and Chronicle

35 Package IIB – Southern Highway Section  Scope of Work Six bridges, totaling 959.390 meters length; in which Bridge No. 2 : 334m Bridge No. 3 : 33 m Bridge No. 4 : 175 m Bridge No. 5 : 133 m Bridge No. 6 : 150 m Bridge No. 7 : 133 m Two lane roadway, totaling 2963.067 meters length A southern toll plaza

36 Package III – Electrical Works Medium Voltage Switchboard

37 Package III – Electrical Works SCADA System

38 Package III – Electrical Works RTU used for Power Distribution Monitoring System

39 Package III – Electrical Works Name of Contractor: JO of ABB – Kinden - VINAINCO Contract Amount: US$ 20,686,000 Contract Period: 26 months (02/2003 – 04/2005) Contract Chronicle: Pre-bid Conference: April 18, 2001 Bid Opening Date: June 26, 2001 Bid Evaluation: June 27 – July 11, 2001  Contract Data and Chronicle

40 Package III – Electrical Works  Scope of Work Electrical Systems : Medium Voltage System MV/LV Substations MV Power Distribution Lines Low Voltage Switchboards LV Power Distribution Lines Interior Tunnel Lighting System Exterior (Road and Area) Lighting System Power Supply for the Ventilation and Water Supply Systems CCTV System Lighting Control System Fire Alarm and Detection System Telecom System Traffic Control System Radio Rebroadcast System Tunnel Power Distribution Monitoring and Control System Main Supervised Control and Data Acquisition (SCADA) System

41 Package IV – Mechanical Works Ventilation System

42 Package IV – Mechanical Works Jet Fans for Tunnel Ventilation

43 Package IV – Mechanical Works Motor Control Center of Ventilation System

44 Package IV – Mechanical Works Name of Contractor: Matsushita – Itochu Consortium Contract Amount: US$ 23,055,000 Contract Period: 36 months (03/2002 – 03/2005) Contract Chronicle: Contract Signing Date: January 18, 2002 Notice of Proceed: February 12, 2002 Commencement of Works: March 12, 2002 Commencement of Works: November 01, 2002  Contract Data and Chronicle

45 Package IV – Mechanical Works  Scope of Work Water Supply and Treatment System consisting of Water catchment and pre-treatment system Pump station and treatment system High water reservoir Fire suppression pipe with hydrans Tunnel Ventilation System consisting of Three (03)sets of electrostatic precipitator Two (02)sets of air supply fans and exhaust fans Thirty-two (32) sets of jet fans Ventilation control system Ventilation building

46 Package V – 110/22kV Substation and 110kV Transmission Line Power Transformer

47 Package V – 110/22kV Substation and 110kV Transmission Line GIS 110 KV, 2500 KA – 40 MA

48 Package V – 110/22kV Substation and 110kV Transmission Line Diesel Generator 1000 KW

49 Package V – 110/22kV Substation and 110kV Transmission Line Name of Contractor: Joint Operation of ABB – Kinden - Vinainco Contract Amount: US$ 7,256,000 Contract Period: 18 months (12/2001 – 06/2003) Contract Chronicle: Contract Signing Date: September 15, 2001 Notice of Proceed: October 18, 2001 Commencement of Works: December 21, 2001  Contract Data and Chronicle

50 Package V – 110/22kV Substation and 110kV Transmission Line  Scope of Work Construction of 110/22 KV indoor substation and tunnel control system Design, manufacture, install, erect and commission a 110/22KV Gas Insulated Switchgear (GIS) substation and substation control center Design, manufacture, install, erect and commission a 110 Transmission Line

51 Package VI – Procurement of Maintenance Vehicles Aerial Platform Truck

52 Package VI – Procurement of Maintenance Vehicles Road Sweeper

53 Package VI – Procurement of Maintenance Vehicles Water Sprinkler Truck

54 Package VI – Procurement of Maintenance Vehicles  Contract Data and Scope of Work Contract Amount: US$ 2,000,000 (estimated) The equipment and vehicles to be supplied 1. Tunnel Superintendent Staff Car : 03 units 2. Patrol Car : 02 units 3. Road Maintenance Vehicle (Van Type) : 02 units 4. Road Maintenance Vehicle (Station Wagon Type) : 01 unit 5. Water Sprinkler Truck : 01 unit 6. Road Sweeper : 01 unit 7. Vacuum Cleaner with High Pressure Washer : 01 unit 8. Sign Truck : 01 unit 9. Lift Truck : 01 unit 10. Aerial Platform Truck : 01 unit 11. Multi Service Vehicle with Side Wall Cleaning Attachment : 01 unit 12. Cargo Truck with 3-ton Crane : 01 unit 13. Wrecker Truck : 01 unit 14. Ambulance Car (Van Type) : 01 unit 15. Fire Fighting Car (Pickup Truck Type) : 01 unit 16. Workshop Equipment and Tools : 01 lot

55 Package VII – Infrastructure of Resettlement Area Construction of Drainage System – November 2001

56 Package VII – Infrastructure of Resettlement Area Construction of Embankment – November 2001

57 Package VII – Infrastructure of Resettlement Area Construction of Treatment Reservoir – November 2001

58 Package VII – Infrastructure of Resettlement Area Name of Contractor: Construction Company No. 185 Contract Amount: US$ 413,000 Contract Period: 8 months (09/2001 – 04/2002) Contract Chronicle: Contract Signing Date: June 09, 2001 Notice of Proceed: August 01, 2001 Commencement of Works: August 31, 2001 Issuance of Taking-over Certificate: April 29, 2002  Contract Data and Chronicle

59 Package VII – Infrastructure of Resettlement Area  Scope of Work Construction of Internal Road Construction of Embankment Construction of Water Supply System Construction of Drainage System Construction of Electricity System Construction of Treatment Reservoir Construction of Kindergarten

60 Conclusion This Presentation is made for purpose to give out a basic introduction of Haivan Pass Tunnel Construction Project Hoping that this Presentation will be of some help toward better implementation of the Project Homepage of Project: http://haivan.cup.com Email: hvt-com@dng.vnn.vn

61 Thank you and Have a good time