Introduction Transition of Management Initial Challenges Revival and Restoration Production for 2013 Year 2014 Major Works Production Mobile plant Projections.

Similar presentations


Presentation on theme: "Introduction Transition of Management Initial Challenges Revival and Restoration Production for 2013 Year 2014 Major Works Production Mobile plant Projections."— Presentation transcript:

1

2 Introduction Transition of Management Initial Challenges Revival and Restoration Production for 2013 Year 2014 Major Works Production Mobile plant Projections

3

4 The road network continues to be the key to Guyana’s continuous development. Over the years, the government has taken initiatives to ensure the sustainability of this infrastructure by ensuring budgetary allocations towards the rehabilitation and maintenance of the nation’s roads. In order to ensure that the works are executed in a proper manner the MPW through the T&HD was responsible for the management and operation of a plant that produces Asphalt Concrete to specification required for road works. In the latter days of its operation, the Ministry was unable to reach its objective. As a result, the decision was taken to have management and operation of the Asphalt plant transferred to the DHBC.

5 Installed in 2009 Supp. by VINAYAK Eng., India. Installed in 2009 Supp. by VINAYAK Eng., India. Specifications Model No.DM 50 TypeDrum Mix Capacity at 3% Moisture60-90 TPH No. of Bins4 Feeding Capacity120 TPH Fuel TypeDiesel Burner Capacity200 liters per hour GOB Hopper1 ton Control PanelFully Computerized

6

7 Major Issues: Defective Asphalt Plant Defective Equipment and Machinery Decrepit buildings Inadequate Staffing Poor Accountability Poor OHS practices

8 StaffAmount Admin3 Trades Men3 Operator (s)1 Labourers4 Security3 Total14 Guard Hut Main Office Scale Hut

9 Main Office Breaker Exhaust Fan Mixer Fan Plant Main Breaker Room

10 Burner Housing Damaged Plant Motors Generator

11 Approval was granted for a loan of G$ 25M from the DHB Account to conduct repairs and purchasing of raw materials.  Structural and Mechanical Repairs: Burner Housing, Conveyor Belts, Trunnion Rollers and Bearings, Gearboxes, Elevator Rollers, Dryer Barrel Chain, plant Motors etc.  Equipment Repairs: Front End Loader and other vehicles.  Electrical Repairs: replaced Power Supply Cables and Breakers.  Serviced and Procured Plant Motors  Purchasing of Raw Materials and Fuel

12 Fabricated Burner Housing Insulated Burner Housing with fireproof mix Repaired Front End Loader Serviced and Repaired AC & DC Motors Replaced Power Supply Cables Raw Materials purchased

13 MONTH PRODUCTION (tons) January1,130.01 February953.53 March1,834.19 April1,217.12 May909.83 June- July- August704.27 September632.03 October1,453.96 November1,747.72 December1,954.69 TOTAL12,537.35 Asphaltic Concrete was sold at the following rates:-  @ GYD$37,500.00 for the Ministry of Public Works  @ GYD$39,500.00 for Private Contractors

14

15

16 Increase staffing capacity StaffAmount Engineering3 Admin4 Stores2 Trades Men3 Operator3 Labourers8 Security7 TOTAL30

17 Provision of uniforms and safety gears Fire response and extinguishing training

18 Listed are major works executed during 2014:  Refurbished Main office, Guard Hut, Workers section and Scale room.  Purchased a new Backhoe and repairing Front End loader.  Installed New Generator.  Installed new Totalizer and probe sensors.  Relocated Transformer.  Installed Communication Tower.  Replaced Asphalt Plant trunnion tyre and roller, mixer fan, exhaust fan, flights and gear boxes.  Serviced all AC and DC motors.

19 New Backhoe Front End Loader overhauled Installation of New Generator Relocated GPL Transformer The Main Office and Security Hut after refurbished New Power Distribution Room

20 New Totalizer Installed New Probe Sensor for Exhaust New Mixer Fan InstalledNew Exhaust Fan to be installed Installing New Kiln Burner Unit Welding Flights New conveyor belt installed

21 New Trunnion Roller, Tire & support New Gear Box Installing Tower

22 Amount : 48,408.88 tons Monthly Avg.: 4,034 tons Months Amount (tons) January1,815.20 February2,505.71 March3,511.91 April3,265.89 May3,243.40 June4,198.21 July5,070.74 August4,923.80 September5,544.30 October6,547.89 November3,655.45 December4,126.38 TOTAL48,408.88

23 400% increase

24  Supplied by GAJJAR Equipment PVT Ltd.  Cost: US$109,000.  Includes bag house and silos for storage Specification Model No.DM 25 TypeMobile Drum Mix Capacity (3% moisture and 150 degree Celsius) 15-25 TPH No. of Bins4 Feeding Capacity45 TPH Fuel TypeDiesel/Kerosene Burner Capacity150 Lph GOB Hopper0.5 ton Control Panel Fully Computerized Pollution ControlBag house Mineral Filler Unit1 Ton

25  Environmentally Friendly  Mineral Filler Unit  Easy to transport and set up  Accessibility to rural areas allows for rehabilitating or building new roads.  Increase Production Capacity

26

27 No.Activities 1Construct Fuel Bunds 2Establish a Materials Testing lab 3 Install Security Cameras and increase security manpower 4Building of Wharf 5 Procure additional equipment:- batch mix plant, bitumen tanker, front end loader and delivery trucks and generator. 6Construct Drying Area 7Renovate and Construct buildings / Scale