Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan.

Similar presentations


Presentation on theme: "1 PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan."— Presentation transcript:

1 1 PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan

2 2 400 kV Network KARADENİZ AKDENİZ EREĞLİ AMBARLI BULGARİSTAN FILIPPI H.UĞURLU KAYABAŞI ÇANKIRI TİREBOLU BORÇKA GÜRCİSTAN BATUM ERMENİSTAN GUMRI BALIKESİR SOMA ALİAĞA DENİZLİ YATAĞAN KEMERKÖY OYMAPINAR SEYDİŞEHİR KONYA ADANA ERZİN G.ANTEP ANDIRIN ELBİSTAN KANGAL YEŞİLHİSAR KAYSERİ ÇAYIRHAN GÖLBAŞ I KEBAN KARAKAYA ATATÜRK DİYARBAKIR Ş.URFA BATMAN KARS ÖZLÜCE ERZURUM HORASAN IĞDI R D.BEYAZIT DIMODICHEV SURİYE DERİNER İSKENDERUN İRAN IRAK HALEP PS3 ZAKHO KHOY BAZARGAN BABEK KALKANDERE KOCATEPE TEİAŞ-APK 2010 220 kV EİH 154 kV EİH HES (PLANLANAN) HES (MEVCUT) TS (MEVCUT) TL (MEVCUT) TL (PLANLANAN) TS (PLANLANAN) Y.TEPE ALİBEYKÖY TUNÇBİLEK D.PAŞA KARABİGA ADA-GEBZE PAŞAKÖY OSMANCA GÖKÇEKAYA TEMELLİ SİNCAN BABAESKİ HAMİTABAT ÜMRANİYE BURSA AYDIN YENİKÖY BİRECİK SEYİTÖMER IŞIKLAR ADAPAZARI YUNANİSTAN KIZILTEPE AĞRI Z.KÖY TEPEÖREN UNIMAR HİLVAN ILISU CİZRE VAN ERMENEK MERSİN HATAY İKİTELLİ A.ALANI KAPTAN UZUNDERE SİVAS DEÇEKO YUSUFELİ KAVŞAK İSDEMİR BOYABAT AMASRA BEYKOZ ÇARŞAMBA HOP A VARSAK MANİSA HABİPLER SAMSUN DGKÇ BORASCO ÇAN İÇDAŞ AKSA SİLOPİ TES K.KALE DGKÇ İÇANADOLU DGKÇ BAĞLUM KAYRAKTEPE YEDİGÖZE İSPİR ARKUN AKINCI ORDU-2 SİİRT ÇETİN MUSUL V.ŞEHİR AHALTSIKHE

3 3 Profile of System (end of 2010) NUMBER OF SUBSTATIONS: 400 kV 184 (35020 MVA) 154 kV 1034 (58015 MVA) 66 kV 54 (637 MVA) TOTAL 1272 INSTALLED CAPACITY ( 93672 MVA ) LENGTH OF TRANSMISSION LINES (km): 400 kV 14,623 154 kV 31,932 220 kV 84,5 66 kV 508,5 154 kV Cable 170,9 380 kV Cable 22,3 TOTAL 47,148

4 4 Generation & Demand (for the year of 2010) Installed Capacity 48.500 MW Hydro+Renewable 34.4 % Hydro 32.1 % & Renewables 2.7 % Thermal 65.2 % Annual Consumption 208 TWh Peak Demand 33.500 MW (13 August 2010)

5 5 Topics Brief history of interconnection queue Planning Process by TEIAS Challenges while planning Tariff Policy Queue Management Future Efforts

6 6 Brief History of Queues First WPP commissioned in: 1998 Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW Current Licensed wind generation: 3483 MW Date: 1th November 2007 Number of the wind pp’s: 722 Total capacity: 78.000 MW According to the system available capacity for connecting wind generation which is equal to 8474 MW A bidding code was prepared by TEIAS which includes the requirements for the applications. According to the bidding document the wind owner which will get the right to use the open capacity has to pay an amount to TEIAS for 20 years since connecting to the system which is equal to the amount which will be calculated for per kwh generation of the wind power plant.

7 7 Wind power plant application areas

8 8 Recent Situation for Wind Generation in Turkey 3483 MW of wind applications has been licensed by EMRA 1320 MW is in Operation 2283 MW is Underconstruction 8474 MW is under evaluation The amount of the available wind generation capacity can be connected to the system until 2013 is 12.000 MW In the strategy document it is foreseen that the total wind generation capacity will reach to 20.000 MW until 2023.

9 9 The available wind generation capacity around 8474 MW is under evaluation

10 10 Marmara & Thrace Region available wind generation capacity ~ 2745 MW is under evaluation

11 11 Aegean Region available wind generation capacity around 2499 MW is under evaluation

12 12 Hatay Region available wind generation capacity around 190 MW is under evaluation

13 13 Planning Process by TEIAS Turkish Electricity Transmission Corporation responsible from the WPP integration studies and to define the available capacity for connecting wind generation According to the results of load flow, contingency analyses and short circuit power calculations, the estimation for capacity for each substation and each region which will be available for connecting wind generation are defined by TEIAS Concentrated small wind generations in one region are collected in one substation (example: Çeşme Region) We have a specific grid code which defines the connection criteria for wind generation but it will be revised for future power system conditions.

14 14 ÇEŞME REGION WIND PROJECTS: 460 MW 380/OG kV Karaburun SS Karaburun RES 120 MW 380/OG 125 MVA ~ 380/OG 150 MVA OG 154/OG 50 MVA 380/154 kV Uzundere SS ~ ~ ~ ~ Sarpıncık RES 32 MW Yaylaköy RES 15 MW Mordoğan RES 30,75 MW Mordoğan RES 13,8 MW Zeytineli-2 RES 49,5 MW ~ ~ ~ Urla RES 15 MW Seferihisar RES 14 MW Seferihisar RES 16 MW Korkmaz RES 24 MW Demircili RES 40 MW Çeşme RES 16 MW Alaçatı RES 16 MW Ovacık RES 18 MW Germiyan RES 10,8 MW OG Karadağ RES 16,25MW 21 km 380 kV 3 Cardinal 16,2 km 380 kV 2 Cardinal 26 km 17 km 12 km 10 km OG 7 km 14 km 10 km 4 km 9 km 11 km ~ ~ ~ ~ ~ ~ 55 km 380 kV 3 Cardinal 380/OG Çeşme HAVZA SS Urla RES 13 MW 13 km ~ 154/OG 50 MVA 154/OG 50 MVA 31 km 154 kV 2x1272 MCM OG 6 km 11 km 9 km 10 km 5 km 154/OG URLA HAVZA SS SS TOTAL CAP: 211,55 MWSS TOTAL CAP: 139,55 MWSS TOTAL CAP: 109 MW ~ ~

15 15 Challenges While Planning Available system reserve The required reinforcements for connecting WPP’s into power system. The difficulty to guess their production time of wind power plants. Who pays the investments and how it will be recovered Beside load flow, voltage profile, short-circuit and contingency studies; the %5 of the short circuit power of the substation which WPP will be connected is applied as a restriction criteria in order to keep the overall system security by now. Detailed dynamic studies for determining the connection capacities are going on.

16 INCENTIVES FOR RENEWABLE POWER PLANTS The Turkey’s Parliament approved a new law on 29 December 2010 for regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of: Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3 US$ /MWh is guaranteed Geothermal PPs are paid at system marginal price, but minimum 10.5 US$ /MWh is guaranteed Biogas PPs and Solar PPs are paid at system marginal price, but minimum 13.3 US$ /MWh is guaranteed Those tariffs shall be valid for the PPs which came into service between 18 May 2005 to 31 December 2015 and will be applied for 10 years. After 31 December 2015, new tariff shall be given by the Government but the new tariff shall not exceed the tariff above.

17 17 Queue Management Process: 1.The available capacity for connecting wind generations are published by TEİAS. 2.WPP applications are forwarded to EMRA (Turkish Regulatory Agency) for these capacities. 3.These applications are forwarded to TEIAS for studying connection opportunities. 4.TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications. 5.If there are multiple applications, bidding process is done by TEIAS to determine the owner of the capacity. 6.After taking license the investor sign a connection agreement with TEIAS. 7.Project will be approved by MENR after the realization of the project System Usage Agreement will be done with TEIAS.

18 18 Queue Management Principle of connection cost sharing between TSO and investor: If the investor pays for the connection line then the TSO will pay back to the investor this amount in 10 years from the investment budget. Otherwise, TSO will put the required investment for the connection of the power plant in it’s yearly investment plan (will be approved by state planning organization) and these procedures takes approximately 3-5 years for bidding (plus constructing period)

19 19 Future Efforts WIND FORECAST SYSTEM The wind forecast system has been developed by Turkish State Meteorological Service which is available to provide information about the wind forecasts for different heights and for 48 hours with 4 km solubility all around Turkey. The trial tests are going on in order to improve the system WIND MONITORING SYSTEM Specific monitoring system for wind generation will be installed and the procedures are going on with consultant company

20 20 Thank You for Your Attention !


Download ppt "1 PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan."

Similar presentations


Ads by Google