MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA

Similar presentations


Presentation on theme: "MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA"— Presentation transcript:

1 MINISTRY OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA
ENERGY AS THE STRATEGIC RESOURCES TO FULFILL NATION’S GROWTH AND PROSPERITY, AND THE ROLE AND PROSPECT OF GEOTHERMAL By: Minister of Energy and Mineral Resources Indonesia International Geothermal Convention and Exhibition (IIGCE) 2014 “Enhancing Geothermal Development to Meet Energy Demand Through Policy Breakthrough” Jakarta , 4 June 2014

2 CONTENTS INDONESIAN ARCHIPELAGO 3 BACKGROUND 4
GEOTHERMAL POTENTIAL RESOURCES 5 POLICY AND LEGAL FRAMEWORK 7 CHALLENGES IN GEOTHERMAL DEVELOPMENT 10 INVESTMENT OPPORTUNITIES 11 CONCLUSION 12

3 I. INDONESIAN ARCHIPELAGO
Republic of Indonesia Republik Indonesia Flag National emblem Motto: "Bhinneka Tunggal Ika" (Old Javanese) "Unity in Diversity" National ideology: Pancasila Anthem: Indonesia Raya Capital and largest city Jakarta 6°10.5′S 106°49.7′E Official languages Indonesian Area  -  Land 1,904,569 km2 (15th) 735,358 sq mi  Water (%) 4.85 Population 2011 census 237,424,363 (4th) Density 124.66/km2 (84th) /sq mi GDP (nominal) Total $ billion (16th) Per capita $3,816(105th) Source : Wikipedia (2013)

4 CURRENT ENERGY CONDITION
II. background CURRENT ENERGY CONDITION CURRENT CONDITION 2025 Gov. Reg. NO. 5/2006 INDONESIA AS NET OIL IMPORTER TOTAL PRIME ENERGY: 1176 JUTA BOE Note: NRE = New and Renewable Energy NEP = National Energy Policy NEB = National Energy Board

5 iII. GEOTHERMAL POTENTIAL RESOURCES (1/2)
PLTP LAHENDONG: 80 MW PLTP SIBAYAK: 12 MW PLTP ULUBELU: 110MW PLTP GUNUNG SALAK: 377 MW PLTP WAYANG WINDU: 227 MW PLTP KAMOJANG: 200 MW PLTP DARAJAT: 270 MW PLTP DIENG: 60 MW PLTP ULUMBU: 5 MW No Island Number of Location Total Installed 1 Sumatera 93 12.837 122 2 Java 71 9.757 1134 3 Bali-Nusa Tenggara 33 1.872 7,5 4 Kalimantan 12 145 5 Sulawesi 70 3.153 80 6 Maluku 30 1.071 7 Papua 75 312 28.910 1.343,5 Source: Geological Agency, MEMR (2013) Note: Preliminary Survey Ready to be developed Detail Survey Installed

6 IiI. GEOTHERMAL POTENTIAL RESOURCES (2/2)
Total : 58 GWA Lisence – Issued : 38 GWAs Tender on Progress : 2 GWAs Tender Preparation : 13 GWAs Tender – Failed : 5 GWAs ACEH 2 WKP Jaboi: 70 MW Seulawah Agam: 130 MW NORTH SUMATERA 5 WKP Sibayak – Sinabung: 130 MW Sibual – Buali: 750 MW Sipaholon Ria-ria: 75 MW Sorik Marapi: 200 MW Simbolon Samosir : 155 MW NORTH SULAWESI 2 WKP Kotamobagu: 410 MW Lahendong-Tompaso: 358 MW GORONTALO 1 WKP Suwawa: 110 MW JAMBI 1 WKP Sungai Penuh: 70 MW NORTH MALUKU 2 WKP Jailolo: 75 MW Songa Wayaua: 140 MW SOUTH SUMATERA 2 WKP Lumut Balai: 250 MW Rantau Dedap: 106 MW SOUTH SUMATERA & LAMPUNG 1 WKP Danau Ranau: 210 MW WEST SUMATERA 4 WKP Bukit Kili: 83 MW Gn Talang: 35 MW Liki Pinangawan: 400 MW Bonjol: 200 MW BANTEN 2 WKP Kaldera Danau Banten: 115 MW G. Endut: 80 MW CENTRAL SULAWESI 2 WKP Marana: 35 MW Bora Pulu : 152 MW BALI 1 WKP Tabanan: 276 MW BENGKULU 2 WKP Tmbg Sawah-Hululais: 873 MW Kepahiyang : 180 MW LAMPUNG 4 WKP Gn.Rajabasa: 91 MW Suoh Sekincau: 230 MW Waypanas – Ulubelu: 556 MW Way Ratai :105 MW CENTRAL JAVA 5 WKP Baturaden: 175 MW Dataran Tinggi Dieng: 780 MW Guci: 79 MW Gn. Ungaran: 100 MW Umbul Telomoyo : 72 MW WEST NUSA TENGGARA 2 WKP Hu'u Daha: 65 MW Sembalun : 100 MW MALUKU 1 WKP Tulehu: 100 MW WEST JAVA 10 WKP Ciater - Tgkban Perahu: 60 MW Cibeureum–Parabakti: 485 MW Cibuni: 140 MW Cisolok Cisukarame: 45 MW Gn. Tampomas: 50 MW Gn. Tgkuban Perahu: 100 MW Kamojang-Darajat: 1465 MW Karaha Cakrabuana: 725 MW Pangalengan: 1106 MW G. Ciremai: 150 MW EAST JAVA 3 WKP Blawan – Ijen: 270 MW Gn. Iyang Argopuro: 295 MW Telaga Ngebel: 120 MW EAST NUSA TENGGARA 5 WKP Atadei: 40 MW Sokoria: 30 MW Ulumbu: 199 MW Mataloko: 63 MW Oka Ile Ange : 40 MW CENTRAL JAVA & EAST JAVA 1 WKP Gunung Lawu : 195 MW 6

7 iv. Policy and LEGAL FRAMEWORK (1/3) GEOTHERMAL BUSINESS PROCESS
Determination of GWA Tender Process IUP Issuance Government/ Local Gov./ Business Entities Business Entities Geothermal Potential Preliminary Survey Feasibility Study Exploration Exploitation Utilization Geothermal Business Permit (IUP) Note: - GWA : Geothermal Working Area (concession)

8 IV. Policy and LEGAL FRAMEWORK (2/3)
Law No. 27/2003 On Geothermal. Government Regulation No. 59/2007 on Geothermal Bussiness Activities. Presidential Regulation No. 04/2010 on Assignment to PT. PLN (Persero) to Accelerate The Development of Power Plant from Renewable Energy, Coal and Gas Ministry Regulation of Minister of Energy And Mineral Resources MR No. 11/2008 on the Procedure for GWA Determination MR No. 02/2009 on Guidelines for Geothermal Preliminary Survey Assignment (as amendment of MR. 05/2007) MR No. 11/2009 on Guidelines for Implementation of Geothermal Business , jo. MR No. 18/2012 MR No. 21/2013 on Revision of MR No. 15/2010 on The List of Power Plant Acceleration Projects Using Renewable Energy, Coal, and Gas and Related Transmission

9 IV. Policy and LEGAL FRAMEWORK (3/3)
Improving and harmonizing regulations in Geothermal Business; Developing a comprehensive pricing structure; Provide fiscal incentives for geothermal development; Joint agreement between Ministry of Energy and Mineral Resorces and Ministry of Forest; Acceleration program in electricity generation, geothermal power is expected to contributed 4,965 MW; Government guarantees on the feasibility of PT. PLN.

10 V. CHALLENGES IN GEOTHERMAL DEVELOPMENT
Land-use Issues Most identified reservoirs lie underneath forestry areas. It is estimated that up to 70 percent of the potential geothermal resources are located within forestry areas (conservation forest, protected forest and production forest). Solution: Improving and harmonizing regulations regarding geothermal (Amend Law No. 27/2003 on Geothermal). Pricing Electricity price from geothermal energy still considers has not reached its economic value; Restructure the tariff model based on region and commercial on date (New MR for new geothermal energy tariff).

11 VI. INVESTMENT OPPORTUNITIES
Recent Updates: Determined of 9 new WKPs with potential of MW: Graho Nyabu: 200 MW Gn. Talang – Bukit Kili: 65 MW Gn. Arjuno Welirang: 185 MW Gn. Pandan: 60 MW Gn. Wilis: 50 MW Songgoriti: 35 MW Gn. Gede Pangrango: 85 MW Gn. Hamiding: 265 MW Talaga Ranu: 85 MW 9 WKPs are going to be tendered in the near future; 12 Preliminary Survey Assignment on new prospect area.

12 VII. CONCLUSION Indonesia holds tremendous geothermal power potential;
Installed capacity of geothermal power plant is only1,343.5 MW; Optimum utilization will significantly reduce dependence on fossil fuel and improve national energy security; Restructuring Geothermal Business to allow private participation in geothermal development; Whilst some supporting policies are in place, acceleration of geothermal development in Indonesia needs international support in terms of finance, technology, human resources as well as technical assistance.

13 Thank You Go Green Indonesia ! www.ebtke.esdm.go.id
MINISTRY OF ENERGY AND MINERAL RESOURCES DIRECTORATE GENERAL OF NEW RENEWABLE ENERGY AND ENERGY CONSERVATION Pegangsaan Timur Street No. 1A Cikini, Jakarta 10320; Phone/Fax :

14 GEOTHERMAL DEVELOPMENT POLICY AND STRATEGIES
Roadmap of GEOTHERMAL development until 2025 Road Map of Geothermal Development until 2025 can be described in the following table : Development Plan Installed (MW) Development Plans (MW) 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Addition power plant capacity (MW) 1.343,5 115,0 2,5 62,0 35,0 279,0 553,5 1.223,5 1.420,0 890,0 264,0 339,0 690,0 30,0 75,0 Total Development Capacity (MW) 1.341,0 1.405,5 1.440,5 1.719,5 2.273,0 3.486,5 4.926,5 5.816,5 6.080,5 6.419,5 7.109,5 7.139,5 7.214,5 The development plans can be achieved with the following note: To harmonized regulation across sectors (MEMR, Forestry, Finance, Local Government, etc.); Simplification of licensing in the geothermal sector; Optimizing the geothermal potential at large fields managed especially PGE’s GWA; The price of electricity from geothermal energy, fit to the economic development of the field; The policies of national banking that support geothermal development; Adapun Roadmap dari pengembangan energi terbarukan sampai dengan tahun 2015 dapat dilihat pada tayangan. Untuk biomassa dapat dibagi menjadi 2, yaitu bahan bakar nabati (BBN) dan biomassa sampah. Kapasitas BBN pada tahun 2011 sekitar 0,4 Juta KL dan akan dikembangkan mencapai 11,8 Juta KL pada tahun Sedangkan biomassa sampah pada awal tahun ini sebesar 520 MW, akan dikembangkan mencapai MW. Adapun kapasitas panas bumi pada tahun 2011 sekitar MW dan akan dikembangkan mencapai MW pada tahun 2015. Sedangkan kapasitas energi air pada tahun 2011 sebesar MW, akan dikembangkan mencapai MW pada tahun 2015. Disamping itu, kapasitas energi laut pada tahun 2011 sekitar 0,002 MW dan akan dikembangkan mencapai 2,2 MW pada tahun 2015. Sedangkan kapasitas energi matahari pada tahun 2011 sebesar 24 MW akan dikembangkan mencapai 773 MW pada tahun 2015. Untuk energi angin dan Energi Terbarukan lainnya, kapasitas pada tahun 2011 sebesar 3 MW dan akan dikembangkan mencapai 737 MW pada tahun 2015.

15 PERFORMANCE ACHIEVEMENTS OF GEOTHERMAL ENERGY SECTOR DEVELOPMENT YEARS 2009 – 2014
Prominent development / leading program for geothermal sector for the last 6 years are : 58 Geothermal Working Areas (GWA) has been stated consist of : 19 existing GWA; dan 39 GWA after Indonesian Law No 27 Years 2003. Geothermal power plant Installed capacity reached 1,343,5 MW in 2014; Total steam production from 2009 to 2014 reached 419,868,437 Tons; Total electricity production from 2009 to 2014 reached 56,452,771 MWh; Realization of Investment from 2009 to 2013 reached IDR Trillion; Realization of Revenues of Government Shares Realisasi from 2009 to 2013 reached IDR 4.734,76 Billion, consist of: Component of Tax amount IDR 1, billion ; State revenue (non-tax revenue) amount IDR 2, billion.

16 PERFORMANCE ACHIEVEMENTS OF GEOTHERMAL ENERGY SECTOR DEVELOPMENT YEARS 2009 – 2014
No. Indikator Kinerja Satuan Tahun 2009 2010 2011 2012 2013 2014* 1. GWA Determination Amount GWA 5 3 8 6 2. Geothermal Power Plant Installed Capacity MW 1.189 1.226 1.336 1.343,5 1.405,5 3. Steam Production Thousands Ton 68.059,9 69.391,2 68.723,4 68.769,7 69.295,6 75.628,4 4. Electricity Production GWh 9.184 9.259 9.253,8 9.355,9 9.332,3 10.067,6 5. Realization of Investment IDR Billion 2.437 2.327 2.457 2.077 4.514 7.348 6. Revenues of Government Shares 821,15 803,36 898,46 1.140,00 1.071,79 579,65 Note : Currency 1 USD = IDR *) Target