Tender for EC-Units assembly Sylvie Dagoret-Campagne EC-Design Review, March 1st 2012, LAL1
2
The tender Phase 1 : mechanical prototype – At least 4 fake MAPMT – The mold design and production – Tools Phase 2 : electronical prototype Phase 3 : 9 FM EC-Units EC-Design Review, March 1st 2012, LAL2
3
Validation and corrections 15 days for LAL checking the proto 15 days to correct the proto EC-Design Review, March 1st 2012, LAL3
4
Cost Element MATRARESAAXINTECA Phase 1 proto-mécafaux PMT100020001350 Outillage-Etude enrobage3500450001350 assemblage1400100001350 enrobage 450 Total5900570004500 Phase 2 proto- electronique Outillage-Etude enrobage2000 assemblage14003100450 enrobage 450 total34003100900 Phase 3 FMpar unité8303100900 pour 97470279008100 par rechange14003100900 pour 2280062001800 total10270341009900 TOTAL Toutes les phases 195709420015300 EC-Design Review, March 1st 2012, LAL4
5
Time ElementMATRARESAAXINTECA Phase 1proto-méca10 weeks18 weeks4 weeks Phase 2proto-electronique2 weeks3 weeks2 days Phase 3EC-rate1/week1,5/week1 day 9-FM8 weeks13,5 week9 days 2-spares5 weeks3 weeks2 days TOTAL without spare20 weeks34,5 weeks6 weeks TOTAL with spare25 weeks37,5 weeks EC-Design Review, March 1st 2012, LAL5
6
Comment Very different propositions – AXINT, very fast and very cheap – RESA, very slow and very expensive Interactions – Deep technical discussions with RESA Need a carefull analysis of technical solutions with AXINT and MATRA EC-Design Review, March 1st 2012, LAL6