1 Welcome to Timberlake Charles (Charley) F. Hurt, P.E.
Presented by Charles (Charley) F. Hurt, P.E. Charles (Chuck) K. Hurt, P.E. April 19, 2004 The Headforemost Co. Consultant Engineers 408 St. Andrews Circle Lynchburg, VA 24503 (434) Acknowledgements & Thanks Charles Falwell, Falwell Well Corp. The News & Daily Advance Hurt & Proffitt, Inc. Designed by: Betty Anne Hurt

2

3 History Timberlake “the gem of the Piedmont”
70 acres of lake and golf course Developed in the fall of 1926 Developers The Timberlake Corp. Edley Craighill, Engineer F. L. Showalter, Contractor The Dam was designed for the 100-year flood The Timberlake Corp. took bankruptcy in 1930 The Peaksview Corp. bought the property in 1945 The water system was given to CCUSA in 1970 The Homeowners Assn. (HOA) was set up in 1986 and continued until 1990

4 TIMBERLAKE As it was…

5 Timberlake aas it was

6 Sailing

7 Across the Water

8 DAM FAILURE June 22, 1995 Century’s hardest recorded Rainfall
9” in 4 to 5 hours DAM FAILURE

9 Break in Dam Washout from the Dam Failure 6/22/95

10 Break in Dam The Break

11 Southside of Road Over Dam

12 Lake Bed After Dam Break

13 Principle Spillway

14 Boat Caught in Principle Spillway

15 Looking Downstream Thru the Dam Break

16 Reconstruction of Timberlake
An emergency meeting of the Board of Directors of the HOA was called Reconstruction Committee Charlie Falwell, Chair Restoration Fund Bud Colbert, Chair Licensing and Permits George Shrader, Chair Land Assessments Shaeffer Oglesby

17 Rebuild Dam HOA hired Hurt & Proffitt on July11,1995, to design the reconstruction of Timberlake Bid opening for Dam repairs - May 23, 1996 Construction by Counts & Dobyns began on June 2, 1996 Clay core material was found on adjoining property of Bobby Montgomery Hurricane Fran brought heavy rains half-way through the construction Dam completed November 1, 1996 Refilling of Lake on February 17, 1997 Easter Sunday 1997, after 40 days and 40 nights FULL LAKE water flowed thru the primary spillway

18 Creek thru Timberlake Lake Bed a Year Later 1996

19 Dredging Silt From Lake Bottom 1996

20 Construction of New Dam June 1996 Cutting a Keyway to the Dam

21 Installation of Lake Drain Valve

22 Inspection of Drain Outlet by Hurt & Proffitt

23 Dam 50% Complete

24 Cut in Dam Prior to Storm Fran’s Rains

25 Fran Fills the Lake

26 Beginning of Repairs Due to Fran

27 Repairs to Cut Made for Fran

28 Construction of Emergency Spillway
200 ft. wide by 4.5 ft. deep

29 Dam Completion November 1, 1996

30 Dedication of Dam June 21, 1997

31 Memorial

32 Timberlake Again

33

34

35

36

37

38 Good Bye from Timberlake
Presented by Charles (Charley) F. Hurt, P.E. Charles (Chuck) K. Hurt, P.E. The Headforemost Co. Consultant Engineers 408 St. Andrews Circle Lynchburg, VA 24503 (434) Acknowledgements & Thanks Charles Falwell, Falwell Well Corp. The News & Daily Advance Hurt & Proffitt, Inc. Designed by: Betty Anne Hurt