Presentation is loading. Please wait.

Presentation is loading. Please wait.

County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation.

Similar presentations


Presentation on theme: "County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation."— Presentation transcript:

1 County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 15, 2016 Tom Biesiadny, Director Fairfax County Department of Transportation

2 County of Fairfax, Virginia Department of Transportation 2 Making Progress on Transportation Silver Line Status Report Silver Line Phase II Garages –Herndon and Innovation Center Stations Pedestrian and Bicycle Improvements –Reston Metrorail Assess Group –Herndon Metrorail Station Access and Mobility Study Improvements to Route 28 Follow Up from New Comprehensive Plan Amendment for Reston –Network Analysis –Transportation Funding Plan Other Projects –Bike Share –Soapstone Connector

3 County of Fairfax, Virginia Phase 1 Punchlist – Ongoing (VDOT, WMATA, and Fairfax County) Fairfax County 274 items, ~30 open Most to be addressed by the end of 2016 Old Meadow Road Realignment Significant number of VDOT items remain Phase 2 Total Project Status (all bid packages) Overall Project – 33% Design – 98% Construction – 19% Highlights Herndon, Innovation Center and Airport Stations under construction Aerial Guideway at Dulles Airport under construction Rail Yard at Dulles Airport under construction Herndon and Innovation Center garages will be bid this fall and Budget - $2.778B Total Contingency - $551.M (Remaining $475.3M)

4 County of Fairfax, Virginia Silver Line Phase II Garages Herndon Station –2,006 parking spaces –Pedestrian & vehicular connections to the existing parking garage –Pedestrian and bicycle amenities –Future Transit Oriented Development (TOD) on the west side –Stormwater pond modifications to accommodate new facility and regulations –Road widening and improvements on site and on Sunrise Valley Drive –Additional access road from Sunrise Valley Drive to the existing garage –Existing garage modifications to accommodate the bridge connections from the new garage, new pedestrian path to Metro elevator, accessible parking spaces, addition of revenue collection system and IT rooms for security equipment 4

5 County of Fairfax, Virginia Silver Line Phase II Garages Site and building plan permit reviews in process Construction start in fall 2016 and completion in winter 2019 Ongoing coordination with MWAA for construction interface on garage, Metrorail facilities, road improvements, bus and vehicular operations during construction FCDOT scope of additional work for overall site improvements being reviewed for incorporation into scope 5

6 County of Fairfax, Virginia Herndon Garage Budget/Schedule Total Project Estimate$56.7 million $7.8 million funded to date $48.9 million funding balance Schedule Design: June 2014 – December 2015 Permitting: September 2015 – August 2016 Bid:June – July 2016 Construction Award:October 2016 Construction:November 2016 – February 2019 Ready for Occupancy:Spring 2019 6

7 County of Fairfax, Virginia Innovation Center Station Garage 2,070 spaces Pedestrian and bicycle amenities Real estate exchange and development agreement with Rocks Engineering for joint development Integration with the overall site with the private development Shared infrastructure design and construction for the garage, retail, residential and office development The overall partnership project includes the design and construction of roads, stormwater management, plaza, and other amenities for the 15-acre TOD Design Development phase and Value Engineering Complete VE recommendation approved to raise garage above grade, required PCA/FDPA PCA/FDPA approved by Board in February 2016 7

8 County of Fairfax, Virginia Innovation Center Station Garage Garage design process currently at 50% Construction Documents phase Site Permit package is currently under review Building permit application in July 2016 Real Estate Exchange and Reciprocal Easement Agreements were final in March 2016 Infrastructure construction in progress with rock blasting & removal Common infrastructure project to provide a clear, rough graded, pre- blasted “garage site” for County – Scheduled for Fall 2016 Onsite coordination and cooperation will be required as MWAA will be working on County parcel and Nugget will be working on neighboring parcels and roads 8

9 County of Fairfax, Virginia Innovation Center Budget/Schedule Total Project Estimate$57.4 million $14.4 million funded to date $43.0 million funding balance required Schedule Design: August 2014 – November 2016 PCA to Raise Garage:February 2016 Real Estate Exchange: March 2016 Permitting:January 2016 - October 2016 Bid:November 2016 – December 2016 Construction Award:February 2017 Construction:March 2017- March 2019 Occupancy:Spring 2019 9

10 County of Fairfax, Virginia Pedestrian and Bicycle Connections Reston Metrorail Access Group Recommendations More than 30 pedestrian and bicycle recommendations Implementation underway 17 projects completed 5 projects under design 3 project under construction Status on County website Additional projects - Phase II –Most scoped; initiating design http://www.fairfaxcounty.gov/fcdot/silverline/restonimp.htm Department of Transportation 10

11 County of Fairfax, Virginia Herndon Metrorail Station Access Management Study Similar to Reston effort Area around Herndon and Innovation Center Metrorail Stations Identified multimodal challenges and possibilities around stations Looking at missing links and needed pedestrian and bicycle connections Funding allocated FCDOT prioritizing projects Board approved projects Scoping underway Department of Transportation 11

12 County of Fairfax, Virginia Improvements to Route 28 Northern Virginia Transportation Authority allocated funding to multiple projects in the Route 28 corridor with HB 2313 revenues FY 2014 priorities included two construction projects on Route 28 –Widen from 6 to 8 Lanes SB (Dulles Toll Road to Route 50) –Widen from 6 to 8 Lanes NB (McLearen Road to Dulles Toll Road) –Construction activities underway FY 2015-16 priorities included design found for widening Route 28 from the Prince William line to New Braddock Road. –Survey work underway Other projects in Loudoun and Prince William Cos. Department of Transportation 12

13 County of Fairfax, Virginia New Reston Comprehensive Plan Since February 2014, County staff has been working to implement the comprehensive plan amendment for Reston –Network Analysis –Funding Plan Advisory Group providing input Tier I and II mitigation applied Working on Tier III mitigation Initial funding suggestions developed Public meeting on June 27; Hunter Mill District Office; 7 p.m. Department of Transportation 13

14 County of Fairfax, Virginia Other Projects Bikeshare –13 location identified in Reston –Equipment ordered –Development of marketing plan underway –Fall 2016 Implementation Soapstone Connector –Sunset Hills to Sunrise Valley Drive –Between Reston Parkway and Wiehle Avenue –Preliminary Engineering and Environment Document underway –Public Meeting: June 15; South Lakes HS; 6:30 to 8:30 Department of Transportation 14

15 County of Fairfax, Virginia Questions? Department of Transportation


Download ppt "County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation."

Similar presentations


Ads by Google