Presentation is loading. Please wait.

Presentation is loading. Please wait.

MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014.

Similar presentations


Presentation on theme: "MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014."— Presentation transcript:

1 MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014

2 MKDV up-grade Motivation Proposed solution Present status Risks Cost estimation

3 Extraction and dilution of the beam

4 Present configuration Two 2 Ohm magnets driven by 3 composite switches from three 3 Ohm PFNs PFN nominal voltage of 60 kV; magnet current 15 kA with ±15% ripples In case of sparking energy of all 3 PFNs goes into spark and results in a total loss of kick

5 Magnet damage due to sparking Serious damage to magnet in case of sparking due to high energy stored in PFNs (5 kJ/PFN @ 50 kV) Machine down time to re-condition or repair magnet Irradiation of downstream equipment

6 Proposed solution Complete separation of 2 magnets: PFN – Switch – Magnet – TMR: Safer operation: keeping at least ½ of kick in case of sparking in one magnet Less energy in spark and hence less damage to magnet Possibility of individual PFN voltage adjustment in case of magnet weakness Replacement of gas switches by semiconductors: due to I.t product (+50 % compared to 3 switches) more robust thyratron would be necessary - risk of obsolescence; semiconductor switches preferred Reduction of complexity of supporting electronics (PS for heaters, reservoirs) Reduction of restart time (no heat-up time); Elimination of mercury hazard (ignitrons)

7 Present status Self healing capacitors for new PFN developed, produced and tested (AVX) Prototype of 2 Ohm PFN with adjustable coils built and tested Test of single ring gate GTO with PFN prototype and real magnet done Design of GTO stack ongoing (2 stacks of 10 GTOs in series; 2 branches of 2 series stacks in parallel); 40 GTO per PFN Design of fast triggering transformer with reduced stray inductance (topology similar to MKD one) ongoing Preliminary measurements shows magnet field rise time (2% - 85%) of ~ 1.2 – 1.3 µs (~ 100-200 ns longer compared to composite switch) Test of current compression with saturation ferrite under preparation with the goal to gain ~ 50 ns of field rise time

8 New PFN with self-healing capacitors Use of self-healing capacitors (higher energy density) allowed to store 50% more energy in 30% less space (still many of old capacitors) Possibility to incorporate semiconductor switches into PFN

9 Adjustable coil with reduced stray field Original design with possibility to adjust coil inductance within +-5% Reduced stay field and hence coils mutual coupling and PFN cover influence Simplifies PFN adjustment

10 Solid state switch development

11 Measurement setup Magnetic field measurement with a pickup coil inside magnet and integration of the induced voltage by scope T_rise measured between 2% and 85% of the kick

12 GTO triggering current influence to Trise Trise = 1.288 µs @ Itrig = 500 A & Vpfn = 2500 VTrise = 1.188 µs @ Itrig = 1000 A & Vpfn = 2500 V Strong influence of the GTO trigger current on T_rise observed Very slow initial field build-up due to low GTO commutation speed

13 T_rise dependence on GTO voltage UPFN [V]1002005001000200025003000 T_rise [µs]1.181.1641.1561.1521.1761.1881.196 Umag [V]60124321.6648.6128915911879 GTO commutation starts very slowly compared to thyratron resulting in slower field rise around lower threshold of the T_rise measurement (2% level) In order to keep the rise time below 1.2 µs, the PFN output cell was modified compared to optimised simulation (output cell more capacitive) resulting in a field distortion and a peak voltage at the magnet entry ~ 13% higher than simulated one

14 In progress/ to be done Triggering transformers + semiconductor switchesdesign in progress Triggering system: depending on test of MKD type PTM - design of higher voltage/current triggering might be necessary Surveillance – discussion ongoing Control system: upgrade done during LS1; heavy modifications not expected GTO ~ 150 pcs to be acquired (50 GTO already delivered) Mechanical modification of existing 3 PFN tanks (1 done)

15 Provisionnal Budget

16 Conclusion Preliminary test shows magnetic field Trise (2% - 85%) < 1.2 µs within the range 100 V – 3 kV per GTO Full scale measurement to be done Importance of GTO triggering (>1 kA needed) Compromise between Trise and magnet entry voltage to be done Abort gap duration will need to be increased by ~ 100 - 200 ns Some T_rise reduction expected with saturation coil (~ 50 ns)


Download ppt "MKDV upgrade LIU-SPS ABT meeting V. Senaj, L. Ducimetiere, P. Faure November 4 th 2014."

Similar presentations


Ads by Google