Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein,

Similar presentations


Presentation on theme: "Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein,"— Presentation transcript:

1 Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein, J-C. Perez, O. Housiaux, P. Revilak, T. Genestier, E. Cavanna, & all other colleagues involved in the LMF MQXFB activities. International Review of the Inner Triplet Quadruples (MQXF) for HL-LHC Overview for rehearsal

2 -Coil production outlook and status (2016-20??) -Infrastructure and tooling -Infrastructure (Layout, Winding, Furnace, Impregnation) -Tooling (Winding/Curing/ RHT/ IMP) -Coil production: -Process 1 to 1 transfer from USLARP and 927 (only minor modifications on tooling) -Challenging parts (8m interlayer vs 2x4m; Trace 8m (Juan); coil handling) -QA: Procedures and follow up with 11T; Procedures in built up for first coils. -Risk mitigation, Expected process times (reference for schedule) -Conclusion F. Lackner, Status on tooling Content

3 F. Lackner, Status on tooling Open question on production process Expected to present a production plan for 2017 ? Would require to couple the production schedule with LS2 especially concerning the LS2 11T coil production Production slots regarding impregnation machine Machinery planning to be shown ? Procurement to be covered ? Special points being the TRACE Coil pack assembly tooling to be covered ?

4 F. Lackner, Status on tooling Production outlook MQXFB prototypes Pole supply for 2 Prototype magnets from 2016 to 2018 Project coil demand: 16 coils (4 practice; 12 poles) AmountCuRRPPIT 2016422* 2017862 201844 Production starts * low grade Assumed initial production time 100 days/coil

5 F. Lackner, Status on tooling Production goals for 2016 Validation of tooling and infrastructure with practice coils Coil IDtypeSteps by end of 2016 001CuFinished 002CuFinished 101RRP*Reaction heat treatment 102RRP*Winding and curing Coil status * low grade Assumed production time 120 days/coil

6 F. Lackner, Status on tooling Current status „Put in picture“ Coil IDtypeCurrent step 001CuCuring inner layer 002CuCable available for winding 101*Nb 3 Sn 102*Nb 3 Sn Projected coil status * low grade Assumed production time 120 days/coil

7 Cold mass magnetic measurement bench Collared coil magnetic measurement bench Collared coil returning bench Cold mass assembly bench Half Yoke returning bench Welding press for 2m models Pressure/leak bench “Winding house” 15m Collaring press Finishing benches Geometrical measurements 15m Welding press Nb 3 Sn Reaction furnace F. Lackner, Status on tooling Impregnation chamber Yoke assembly bench

8 F. Lackner, Status on tooling Coil winding and curing

9 LMF - Winding house (bldg. 180) F. Lackner, Status on tooling

10 Infrastructure for MQXF -Refurbishment of LHC winding machine (2014-2015) -New 12.5 long furnace (2014-2016) -Impregnation machine (2014-2016) in combination with 11T dipole -Sectorization of curing press (2015) in combination with 11T dipole -Re-arrangement of LHC main dipole production area (2016)

11 Layout of the LMF - Winding House Re-arrangement of existing winding house layout and infrastructure for simultaneous winding operations for 11T and MQXF. MQXF benches designed for double use with LHC main dipoles.

12 MQXFB – refurbishment of machine Refurbishment of previous dipole winding machine for LHC:  Insulated cable is separated on two reels for inner and outer layers  Fixed mandrel & mobile gantry  Integrated strain tension force measurement system  Refurbished control system  Automatic driving F. Lackner, Status on tooling InstalledComissionedIn operation

13 Curing press  Hydraulic sectoring was finalized for full compatibility with the 11T and MQXFB coil design. Curing Press : Re-use of the 15m long press used for NbTi LHC dipole magnets Hydraulic sectoring was required for compatibility with the change in coil length. F. Lackner, Status on tooling InstalledComissionedIn operation

14 F. Lackner, Status on tooling Contract launched in April 2015 – reception April 13 th, 2016 In-house acceptance: June 2016 Plateaus 210°C; 400°C; 665°C; +-3°C Heated length Ø1 m; l 10,5 m; 700 kg/m Width < 4 m; l < 30 m; h< 4 m 40 probe TCs Evacuation at RT to 10-2 mbar; 700 l/s Loading and unloading automatic 20mm/s2, 0,5 mm/m Oxygen reduction in < 10 h Heat treatment start oxygen level < 10 ppm 52 weeks delivery Allows simultanious reaction of two coils LMF - Reaction furnace RHT – redundancy will be given by the MQXF furnace: Final in-house acceptance June 2016

15 Specific benches F. Lackner, Status on tooling InstalledComissionedongoing

16 Actions:  Impregnating coils Tooling:  VPI machine, currently under commissioning Three short model coils (sm201, sm114, sm115) already impregnated. The first 5.5 m copper coil impregnation is currently in preparation. F. Lackner, Status on tooling Impregnation system InstalledComissionedIn operation

17 F. Lackner, Status on tooling Specific tooling for MQXFB

18 Specific tools required for coil winding Dedicated tools coming from short models experiences, specially in the heads zones: Heads upper pushers Lateral pushers Upper guides Cable « strain gauge » to monitor the winding tension Interlayer template F. Lackner, Status on tooling

19 Curing tool Curing mould and heaters are available Different pics from 1st curing

20 F. Lackner, Status on tooling Blank assembly completed Will be used for CERN acceptance tests of the new reaction oven Geometric monitoring plan of plates and blocks implemented after each reaction cycles Reaction and impregnation fixtures

21 F. Lackner, Status on tooling Coil metrology

22 F. Lackner, Status on tooling Actions:  Geometrical assessment of coil Tooling:  Measurement table – delivered  FARO-Arm (Coil metrology)  Lasertracker (Cold mass metrology) Metrology instruments  The laser tracker Leïca LTD500 will be replaced by AT-402 or AT-930.  Axyz software is being substituted by Spatial Analyser.  The Magnet Geometrical Measurement automated process (MGM-SA) is being programmed with EN-STI-ECE leaning on past developments (MGM).  Faro edge 2.7 will be used inside the winding house, delivery: already received  Granite table for winding house metrology, delivery: May 2016 Finishing benches and metrology Procurement and modification in progress

23 F. Lackner, Status on tooling Production processes

24 F. Lackner, Status on tooling Processes Processes are transferred from CERN MSC-MDT section and US LARP programm, only with minor adjustments to tooling and infrastructure and experience feedback from 11T dipole prototype Processes are currently being written and drafted with LMF QA team

25  A CERN number is given for each machine.  All technical documentation relevant are archived inside EDMS:  Certificate of conformity, User manual, Drawings…  A preliminary safety report is prepared by QA,  A safety diagnose is made by a certified company,  The working procedure written by QA includes the safety instructions,  Finally the workspace safety is analyzed by TE department. 25 Safety and quality aspects Covered in detail by R. Principe & T. Otto

26 F. Lackner, Status on tooling Winding4 – 5 weeksOnly 1 winding machine Curing3 days1 curing tool Reaction heat treatment 14 days1 furnace suitable Impregnation3 – 4 weeks1 system – bottle neck in the production flow Risk mitigation and redundancy

27 F. Lackner, Status on tooling Conclusion

28 F. Lackner, Status on tooling Conclusions  Production line preparation is close to finalization  Winding house – Transition to Nb 3 Sn coil production is well advanced, finalization in summer 2016  Heat treatment – Reaction furnace commissioned, in-house acceptance ongoing, 2 nd pair of reaction and impregnation fixtures will be ordered once the production process has saddled and no modifications are needed  Impregnation – Commissioning of impregnation system is ongoing  Continuous improvement is necessary for reducing onsite preparation time  Assembly tooling – Design was launched  Validate all remaining assembly process and tooling during first prototype assembly

29 Thank you