Presentation is loading. Please wait.

Presentation is loading. Please wait.

Brine Concentration Pilot Project (AquaSel) Update

Similar presentations


Presentation on theme: "Brine Concentration Pilot Project (AquaSel) Update"— Presentation transcript:

1 Brine Concentration Pilot Project (AquaSel) Update
Khos Ghaderi, P.E. Director of Water Operations June 17, 2015

2 Overview Generated Brine Volume: Loss of Valuable Water Resources:
Menifee Desalter MGD Perris Desalter MGD 2.3 MGD Loss of Valuable Water Resources: Presently – 2,500 AF/year Future – 4,000 AF/year Goals: Maximize available water resources Reduce costs Improve reliability

3 Evaluation of Emerging Technologies
Uses Gypsum Crystals to prevent salt precipitation on membrane surfaces Large footprint high TDS product 60% recovery SPARRO Seeded Slurry SAL-Proc GE Processors Inc. Recovers by-products (gypsum, magnesium hydroxide, etc.) for marketing Low flux No manufacturers 65% recovery Membrane Distillation (MD) Passage of water vapor through the membrane Good for lower TDS brine 80% recovery Forward Osmosis (FO) Uses chemical potential to draw water through the membrane Bench scale testing by University of Nevada, Reno Zero Discharge Desalination (ZDD) Use Electrodialysis Metathesis (EDM) Developed by Dr. Davis of UTEP Uses Electrodialysis Reversal (EDR) and Precipitator AquaSel Ongoing pilot testing

4 AquaSel Pilot Evaluation Objectives
Demonstrate ability to reliably treat EMWD’s brine Provide for a higher percentage of brine recovery Verify and validate preliminary cost estimates Identify any operational and maintenance issues Develop appropriate treatment train design for a demonstration scale plant based on findings

5 Impact of Recovery on Brine Concentration
33 97 25 96 95 20 Level of difficulty increases exponentially at higher brine concentrations 90 10 Concentration Factor 6.7 85 5 80 75 4 2 1 50 Percent Recovery

6 AquaSel Pilot Progress Update
November 30, First full day of operations processing RO concentrate December 3, 2014 to February 3, 2015 Experienced several operations and water quality related issues Silica fouling Calcium carbonate fouling (scaling) Modified and tested treatment train to address hydraulic and membrane fouling issues February 3, Pilot unit was placed back in operation with addition of pre-treatment (ferric chloride, multimedia, and cartridge filter) April 13, Achieved steady state operations Continued experiencing occasional starts and stops due to scale formation on the membranes

7 AquaSel Pilot Progress Update (cont’d)
Phase I – 97 Percent Overall Recovery 507 hours of operation Desalters at 71 percent recovery AquaSel at 90 percent recovery Occasional fouling of the EDR membranes Product water quality high in TDS (3,000 mg/L) Phase II – 95 Percent Overall Recovery 200 hours of operation Desalters at 75 percent recovery AquaSel at 80 percent recovery Product water quality varied but achieved 1,500 mg/L TDS Operation was less reliable than Phase I and required additional maintenance Transitioning to EMWD staff’s operating the pilot unit

8 Comparison of Desalter Recovery Rates

9 Replaced Anion Membranes
Performance Overview Replaced Anion Membranes IEBL Shutdown Power Outages Adjusted Recovery

10 Summary of Testing to Date
Membrane fouling and hydraulic issues were mitigated Promising operational performance 1,300 hours of operation 320 hours of continuous run time Stable operation since April 13, 2015 with occasional downtime Overall brine recovery of 95 percent has been achieved

11 Additional Evaluation Under Phase II Conditions 7/30/2015
Next Steps Additional Evaluation Under Phase II Conditions /30/2015 Continue pilot testing at 95 percent recovery Verify and validate cost estimates Evaluate water quality and reliability Complete Draft Project Report /31/2015 Peer review by USBR and MWD Complete Final Project Report /15/2015

12 Recommendations Extend testing through July 30, 2015 to obtain additional data and improve water quality Approve and authorize the following: Amend the AquaSel™ pilot rental agreement with GE Water & Process Technologies for an additional $35,000, for a total contract cost not-to- exceed $187,000; Amend Contract Number with Carollo Engineers for brine management technical support for an additional $55,000, for a total contract cost not-to-exceed $150,000; and Additional appropriation of $90,000 for the AquaSel™ Brine Concentration Pilot Study, which brings the total estimated project cost to $512,508.

13 Khos Ghaderi, P.E. Director of Water Operations (951) , extension 6240


Download ppt "Brine Concentration Pilot Project (AquaSel) Update"

Similar presentations


Ads by Google