Presentation is loading. Please wait.

Presentation is loading. Please wait.

August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote.

Similar presentations


Presentation on theme: "August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote."— Presentation transcript:

1 August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote

2 2 2 TPTF8/11/2008 Agenda EDS Follow-ups from last meeting EDS 2 –Release 3: Telemetry & State Estimator EDS 3 –Release 5 & 6: SCED / LFC Registration Status

3 3 3 TPTF8/11/2008 Frequency Plot 6/25/08

4 4 4 TPTF8/11/2008 7/15 ICCP Site fail-over results Denton & College Station TSPs, and Exelon QSE, had not set up their Taylor links. LCRA TSP was only able to support one link at a time. STEC TSP’s link had to be cycled. No issues thereafter. STEC QSE was unable to read their base points from us. AEP QSE link was up, but no data was available. AEN TSP performed a site failover at the same time as the test. They came back up after a few minutes. Since the test: –QSE & TSP ICCP Associations Completed Working through outstanding issues with three MPs –ICCP High Availability Completed

5 5 5 TPTF8/11/2008 Met Data from WGRs Individual detailed letters were distributed to WGRs on Aug 7 th –Letters provided Meteorological data status by resource –Requested response by August 14 th on how they will correct the issues –Deadline for issue correction is October 31 st Current Status on next two slides

6 6 6 TPTF8/11/2008 Wind Telemetry MMS UI Feedback –Concerned about the amount of work needed to view/update COPs, etc. for multiple resources. Current UI allows user to view multiple days for one unit, not multiple units for one day –Concerned about the way error and confirmation messages display (not implemented yet) –Concerned about raw.xml displaying on the Awards tab (not implemented yet)

7 7 7 TPTF8/11/2008 Wind Telemetry

8 8 8 TPTF8/11/2008 Focused State Estimator Testing Dates Start Date and TimeEnd Date and TimeDuration August 6 12:00 amAugust 6 11:59 pm24Hrs August 12 12:00 amAugust 14 11:59 pm72Hrs August 19 12:00 amAugust 21 11:59 pm72Hrs August 26 12:00 amAugust 28 11:59 pm72Hrs September 2 12:00 amSeptember 4 11:59 pm72Hrs September 8 12:00 amSeptember 12 11:59 pm120Hrs  Please reference the market notice on July 25 titled Focused State Estimator Support Date and Requirements and Continuing SCED Input Requirements Results from 8/6 – lower than non-focused days –EDS team will communicate through multiple channels prior to the next testing date –ERCOT is reinforcing roles / responsibilities internally

9 9 9 TPTF8/11/2008 QSE Telemetry

10 10 TPTF8/11/2008 TSP Telemetry

11 11 TPTF8/11/2008 Load Observability  AEP were very proactive in providing telemetry and still more to come.  ONCOR have provided majority of their telemetry  All remaining issues are being actively worked by MPs and ERCOT * All buses included in this list have a load

12 12 TPTF8/11/2008 State Estimator- Convergence Rate – June ERCOT Software Upgrade caused convergence issue  Monthly Convergence: 83.49%

13 13 TPTF8/11/2008 State Estimator- Convergence Rate – July  Monthly Convergence: 85.33%

14 14 TPTF8/11/2008 MP10 Status MP10 forms were due to ERCOT by April 15, 2008 Initiation of network model change process (Transmission Data Forms as needed) target date of two weeks of ERCOT request Status of 179 sites 70% are complete 8% need to submit Transmission Data Forms or review corrected packages 16% are waiting on feedback/corrections by ERCOT 6% are non-responsive Submittals to include MP10 Form w/ all boxes checked if approved If not approved, briefly write issues on MP10 form If ERCOT model change required: Complete ERCOT Transmission Data Form Send correct updated operational (non-relaying) one-line for facility

15 15 TPTF8/11/2008 MP10 – Next Steps  Updated MP10 Metric Criteria  The Readiness Team will review documentation that verifies that all participating resources in the Texas Nodal Market have completed their mapping of Resources to Resource Nodes and Resources to EPS Meters.  Readiness will be achieved when each resource has either mapped their Resources or have accepted the existing default configuration.  It is the intent of this metric to ensure that the settlement of Resources involved in a net metering configuration can be executed as specified by the Nodal Protocols.  Target Completion: Receipt of Network Model One-Line (NMO) + 30 Days

16 16 TPTF8/11/2008 MP11 Status Review/Validation process and timing Business review by WCS (may need immediate corrections by MP in order to load into RARF database) EDS critical data review continues with feedback to MP Technical review by data consumers within ERCOT in progress Status of 221 sites 77% Tier 1 Validation is complete 18% Contain missing or inaccurate data 2% Missing critical data 3% Non-responsive

17 17 TPTF8/11/2008 MP-11 - Ongoing Registration Data Screening

18 18 TPTF8/11/2008 MP11 – Next Steps  Updated MP11 Metric Criteria  The intent of this metric is that ERCOT has all registration related data for all market participants intending to participate in the Nodal Market on record.  Updated MP 11 Metric Criteria: To work towards final acceptance of Resource Registration documents to include: Acceptance of RARF Acceptance of Resource Network Topology Registration Non-Modeled Generation Declaration Resource Decision Making Authority Attestation  Target Completion: December 31, 2008


Download ppt "August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote."

Similar presentations


Ads by Google