1 Part 10-2a Micropiles and self drilling rods in soil and rock engineering V-2009 (rev. II-2013) (Part 10-2a, PP 2007, animation+p/r : 2013.02.26 compr.) ready 1 Copyright notice Unauthorised copying of this presentation as whole or in parts in any form or by any means, electronic, photocopying, recording or otherwise, without prior written permision is prohibited.

2 NAJDER engineering ®NAJDER engineering ® is a consulting company as well as a specialist contractor within civil and foundation engineering. We are preparing technical concepts, design projects, analyses and performing jobs as a subcontractor. Skånska Cementgjuteriet Skanska ABTomasz Najder joined in the period of 1974-1976 Skånska Cementgjuteriet (today Skanska AB) as a member of Supervising Team on the project “Second Dry Dock in Gdynia Shipyard”. Stabilator AB Skanska Group Stabilator Sp. z o.o. Skanska Group1983-2002 Tomasz Najder gained his experiences in Stabilator AB (daughter company in Skanska Group) as site manager, project manager and internal consultant (”trouble-shooter”), 1990-1995 as Production Manager (Stabilator AB- International Division in Poland), 1995-2001 in Polish-Swedish company Stabilator Sp. z o.o. (Skanska Group) as Vice President and Executive Manager. Polibeton Sp. o.o. Najder engineering ® Polimark InternationalAnna Elżbieta Najder (wife) owned 1991-2002 Polish company Polibeton Sp. o.o. and now Swedish Najder engineering ® since 1997 (until 2005 operating as Polimark International) – operating globally. Najder engineering ®Anna Monika Najder (daughter) together with Tomasz Najder (as the President of the Board and Executive Manager) owned 2002-2009 Polish Najder engineering ® operating in Poland. since six generations.Family Najder is working within mining, tunneling and civil engineering since six generations. Family and company history in civil engineering 2 ready

3 3 3 Foundation engineering and soil investigations. Reinforcement of existing foundations (underpinning) of industrial buildings, housing estates and ancient monuments (piling, anchors, injections).Reinforcement of existing foundations (underpinning) of industrial buildings, housing estates and ancient monuments (piling, anchors, injections). Tunneling, rock stability and soil improvement (deep mixing method, high/low-pressure injection, lime-cement columns). Stabilization of slopes and embankments (geogrids, soil reinforcement, drainage, geotextiles). Sealing of existing embankments, dams, dikes and waste deposits. Flood defense. Coast protection. Biological engineering, gabion constructions. Leakage and moisture counteraction (insulations, drainages, sealing injections, dilatation repair) in concrete and brickworks structures. Field of activity ready

4 4 Daughter Anna Monika Najder 1978 -Mama Anna Najder ready Son Jan Najder 1981 - Senior Tomasz Najder 1951- Son Jan Najder 2013

5 5 ready Example 2: Example 2: underpinning of cathedral in Koszalin (Poland)

6 6 ready Location of the project

7 7 Soviet Army Köslin (today Koszalin) before “rendez-vous” with Soviet Army in 1945 ready

8 8 Soviet Army Köslin before “rendez-vous” with Soviet Army in 1945 ready

9 9 Köslin (today Koszalin) in 1945

10 cathedral excavation for catristy 10 ready TITAN Underpinning system with TITAN micropiles

11 11 Excavation for catristy ready

12 12 Underpinning system of the cathedral before excavation for new underground catristy – plan the cathedral ready new underground catristy

13 ready 13 TITAN TITAN – micropiles, anchors and soil nails. Rotary or rotary - ”light percussive” drilling methods (”slow and low pressure jet-grouting”) Example of self-drilling rods

14 14 TITAN TITAN self-drilling rods with sacrificial drill bits ready

15 drill bit drill rod = pile shaft cuttings cement grout soil ready 15 TITAN TITAN micropile final shape of grouted pile body

16 anchoring plate pile shaft D = 1,54 d drill ready 16 TITAN TITAN micropile performed by Najder engineering (2004)

17 17 press ready

18 micropile steel bar concrete beam stones(grouted) load streetcellar micropile excavation concrete beam Load transmission to new micropiles – longitudinal concrete beams 18 ready prestressing forces press

19 19 Underpinning system of the cathedral before excavation for new underground catristy – cross-section ready press

20 20 Shoring system – “Berlin wall” (details) ready

21 21 Lowest part of the brick wall and existing foundation of the cathedral after local excavation – before underpinning ready

22 22 Drilling of Titan micropiles outside the cathedral ready

23 23 Lowest part of the brick wall and existing foundation of the cathedral after local excavation – under underpinning works ready top plate on Titan micropiles the plastic casing for prestressed bar

24 24 Underpinning system of the cathedral foundation longitudinal concrete beam prestressed bar inside the plastic casing ready grouting hose for corrosion protection of the prestressed bar

25 25 Titan micropile – details top plate on Titan micropile ready

26 longitudinal beam prestressed bar inside the plastic casing 26 Underpinning system of the cathedral foundation – cont. ready

27 longitudinal concrete beam prestressed bar 27 ready Underpinning system of the cathedral foundation – prestressing of GWS bars press

28 28 Underpinning system of the cathedral foundation (interior of the church) Titan micropile top plate on Titan micropile ready prestressed bar inside the plastic casing top plate on Titan micropile press grouting hose for corrosion protection of the prestressed bar

29 29 Underpinning system of the cathedral before excavation for new underground catristy – plan the cathedral ready new underground catristy

30 30 Secant-pile-wall by Titan micropiles ready

31 31 Excavation for the catristy (shoring system of modified “Berlin wall”) ready

32 32 Final construction works at the catristy ready

33 33 “Catacombs” almost ready ready

34 34 The same place in 2011 (11 years later) ready

35 35 ready Location of the project Example 3: underpinning of Racibórz Castle (Poland)

36 36 Location of the castle ready press

37 37 Castle in Rattibor (today Racibórz in Poland) ready

38 38 Part of the castle with largest settlements ready

39 39 Soviet Army Castle before “rendez-vous” with Soviet Army in 1945 ready

40 40 Soviet Army The castle after “rendez-vous” with Soviet Army in 1945 ready

41 41 Part of the castle with largest settlements ready

42 42 press ready Excavations, core drilling and drilling of Titan micropiles Mounting of transversal steel supporting beams Core drilling and inserting GWS prestressing bars Mounting of longitudinal steel supporting beams, GWS bars prestressing press Load transmission to new TITAN micropiles: – longitudinal and transversal steel beams

43 43 Working procedure: stage 1 – excavations and core drilling ready

44 44 Excavations and core drilling press ready

45 45 Working procedure: stage 2 – drilling of Titan micropiles ready

46 46 Drilling of Titan micropiles foam cement grout ready

47 47 Working procedure: stage 3 – mounting of steel supporting beams ready

48 Load transmission to new TITAN micropiles: – longitudinal and transversal steel beams transversal steel beams longitudinal steel beam micropile 48 before after ready

49 49 Part of the castle with largest settlements after partial renovation (1995) ready

50 50 Part of the castle with largest settlements after 17 years (2012) ready

51 Thank You for Your attention! ready 51 THE END

52 ready Welcome to www.najder.se 52

53 53 These works had nothing to do with… ready


Download ppt "Part 10-2a Micropiles and self drilling rods in soil and rock engineering V-2009 (rev. II-2013) (Part 10-2a, PP 2007, animation+p/r : 2013.02.26 compr.)"