21 January 2016 1 Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.

Similar presentations


Presentation on theme: "21 January 2016 1 Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till."— Presentation transcript:

1 21 January 2016 1 Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till ½FEB Final consideration EHN1 civil engineering project status (DEC+½JAN) Neutrino Platform General Meeting N.Lopez – M.Manfredi

2 Done (1/2): (1) PITS EXECUTION Excavation/Execution second ties level: (100% completed). Pit B in tension. Internal DW surface Leveling / Reparation: (50%=>95% completed). Last points to be fixed. - Phase 4: done - (...). Pits ground excavation: (60%=>100% completed). Both pits done end-December. Pits’ lower drainage system: (0%=>95% completed). Connection to drainage pit is missing. Pits’ slab system: (0%=>33% completed). I° part of pit A done. Pit B ongoing. Erection internal wall: (0% completed). Follows completion Pit B slab. EHN1 civil engineering project status (DEC+½JAN) 21 January 2016 2 Neutrino Platform General Meeting N.Lopez – M.Manfredi

3 Done (2/2): Swallow trenches execution: (0%=>50% completed). East side ongoing S2 S1 S5 S4 S3 -S3, S4 starting execution delayed 2 nd half of January- -S1, S2, S5, S6 ongoing - Related to -S1, S2, S5, S6 - portions only Backfilling between slabs: (0% completed). Upper slab concreting process: (0% completed). Earthworks allowing site preparation: (100% completed). Walls above DW’s crown beam, around pits: (50%=>70% completed). S6 Inner slab and trenches drainage system: (50%=>100% completed). Lower slab concreting process: (90%=>100% completed). UPPER BACKFILL (2) SLAB SYSTEM LOWER EHN1 civil engineering project status (DEC+½JAN) 21 January 2016 3 Neutrino Platform General Meeting N.Lopez – M.Manfredi

4 Next Steps: Activities scheduled till ½FEBRUARY (1) PITS:  (A+B) Connection both pits’ drainage system towards pumping station in Pit B.  (B) Concreting slab and side wall for connection with Pit A. Completion by 2 nd half of January.  (A+B) Erection/Installation internal walls. Start after previous task. Concreting Pit A remaining part in parallel. All during February. (2) SLAB SYSTEM:  S3, S4 lower slab and drainage system to start 2 nd half of January.  East side trenches completion by end-January. Backfilling process starts afterwards. 18/01/201507/12/2015 EHN1 civil engineering project status (DEC+½JAN) 21 January 2016 4 Neutrino Platform General Meeting N.Lopez – M.Manfredi

5 Final Consideration: CE planning still in line with the 9 weeks of delay announced in November for the WP1 activity. Planning has been reviewed given priority to the execution of the pits’ internal walls (critical path). Following re-organization of some tasks and possibility of several superimpositions with WP2, contractors estimate to potentially retrieve 3 weeks at most. Thus, CE Handover is shifted by 6 weeks (half-August 2016), according to the new planning. WP2 starts early in March. Work site situation normalized after defects reparation of the DWs complex. Coordination of the CE integration issues ongoing (e.g. 3D Catia model updating, ECR drafting/circulation, EL/CV services in the TG/Pumping station, etc..) will be finalized. Technical and on-site support to the MOE, coordination with CERN group, analysis/review of technical documents/drawings, weekly and monthly reports on-going. Next status of the works 2 nd half of February. EHN1 civil engineering project status (DEC+½JAN) 21 January 2016 5 Neutrino Platform General Meeting N.Lopez – M.Manfredi