Presentation is loading. Please wait.

Presentation is loading. Please wait.

Transmission investment

Similar presentations


Presentation on theme: "Transmission investment"— Presentation transcript:

0 Electricity transmission network development
FSR Workshop Improving and extending Incentive-based regulation Florence, 24 November 2006 Laurens de Vries Delft University of Technology

1 Transmission investment
Types of investment: maintenance capacity increase (existing links) network expansion (new links) Introduction Network costs Current incentives What if we are wrong? Options Conclusions

2 Current situation Transmission planning: CBA, based on load flow forecasts. Incentive based regulation (if applied) typically limited to operating & maintenance cost popular method: network revenue growth rate = CPI-X+Q the Netherlands exception: capital costs included as a consequence major investments are made only if they are exempted from the revenue cap Introduction Network costs Current incentives What if we are wrong? Options Conclusions

3 What do we want to achieve - goals
Functions of transmission: transport, reliability & trade Goal: economic efficiency, with respect to maintenance network availability (NTCs!) congestion management capacity increases network expansion Trade-offs between cost and quality Second goal: integration of national markets, increasing competitiveness? Introduction Network costs Current incentives What if we are wrong? Options Conclusions

4 Trade-off between cost and quality
reliability frontier  price/ cost willingness to pay  reliability Introduction Network costs Current incentives What if we are wrong? Options Conclusions

5 Objectives for network regulation
Incentivise network users efficient use of the network optimal balance between cost and service (in theory: marginal cost of service = marginal benefit) Incentivise the TSO optimal network management find optimal balance between cost and service regulation of monopoly rents Introduction Network costs Current incentives What if we are wrong? Options Conclusions

6 So… what are network costs?

7 Categories of network investment
In meshed AC networks  parallel flows difficult to control DC lines flows are controllable Linear/radial networks no parallel flows trade-off with generation easier to calculate In last two cases: easier to determine the right incentives  better prospects for IBR of TSOs But most investment in meshed AC networks! Introduction Network costs Current incentives What if we are wrong? Options Conclusions

8 Example: counter flows (all types of network)
Generator A: sells 500 MW to consumer B Consumer B: buys 500 MW from producer A contract: 500 MW A B Consumer A: buys 400 MW from producer B Producer B: sells 400 MW to consumer A contract: 400 MW physical flow: 100 MW  Short-term network capacity depends upon other contracts! Introduction Network costs Current incentives What if we are wrong? Options Conclusions

9 Counter flows Two transactions in opposite directions
 smaller load flow.  More transactions can take place, but only if the counter flows really take place. The network costs of a transaction can be negative! When flows in a given direction double, energy losses quadruple  cost increase not linear! Introduction Network costs Current incentives What if we are wrong? Options Conclusions

10 Example: parallel flows
B R2 Ohm’s Law: V = I  R Introduction Network costs Current incentives What if we are wrong? Options Conclusions

11 An ill-planned new power line…
P1=500 MW R1=1 A B P2=100 MW R2=3 I1=V/R1=V I2=V/R2=V/3 I1=3I2 P2=100 MW P1=300 MW Ptotal=400 MW! Introduction Network costs Current incentives What if we are wrong? Options Conclusions

12 Conclusion parallel flows
The load flow is mainly determined by the impedance (resistance) of the lines, but constrained by their capacity. Consequence: the load flow depends upon: the location of generators the location of loads and transformers to different networks the resistance of the lines. Electricity flows do not necessarily use the available capacity fully. Load flow difficult to manage operationally.  New network capacity must be coordinated with existing capacity. Introduction Network costs Current incentives What if we are wrong? Options Conclusions

13 Given these complications, what are current incentives?

14 Incentives to network users: transmission pricing
Ideal: cost-based rates in case of no congestion value-based rates in case of congestion Two groups of transmission pricing methods: Fixed, cost-based tariffs. Congestion handled separately. (Decentralized market design, typical for Europe) Locational marginal pricing (nodal pricing). (Integrated market design, typical of the USA.) Introduction Network costs Current incentives What if we are wrong? Options Conclusions

15 The American way: nodal pricing
A different price at every node in the network You can only sell and buy electricity at the nearest node The system/market operator varies nodal prices to reflect network capacity congestion management is integrated in the process overall prices are minimized, given demand, generation bids and network constraints Introduction Network costs Current incentives What if we are wrong? Options Conclusions

16 Transmission pricing in Europe
Fixed rates (typically not related to distance) allow market parties full freedom. TSOs intervene only when necessary to maintain balance or prevent congestion. Problem: load flows unpredictable untill all trades have been closed and reported. Therefore costs are unpredictable. tariffs are not efficient Introduction Network costs Current incentives What if we are wrong? Options Conclusions

17 Current incentives to TSOs
Build more capacity (especially interconnectors) Reduce NTC on existing NTCs In case of merchant interconnectors: reduce NTCs of other interconnectors to increase price difference.  TSOs should not be in merchant projects! (like Britned) Introduction Network costs Current incentives What if we are wrong? Options Conclusions

18 Links between incentives to TSO and network users
The choice of transmission tariff, access rules, congestion management method affect the incentives to the TSO The degree of unbundling affects the interests of the TSO Introduction Network costs Current incentives What if we are wrong? Options Conclusions

19 But… incentives for what?
How much capacity expansion in anticipation of demand growth? Which network configuration is optimal? When to build network capacity, when to rely on local generation investment? What is an optimal cost level? We don’t know what is optimal Introduction Network costs Current incentives What if we are wrong? Options Conclusions

20 So the incentives are probably wrong!

21 Limits to incentives Further complication: lead time for investments  risk of investment cycle If we don’t know what is optimal, what are ‘good’ incentives? Introduction Network costs Current incentives What if we are wrong? Options Conclusions

22 Asymmetry of social costs
Cost of reliability Cost of outages Reliability  Introduction Network costs Current incentives What if we are wrong? Options Conclusions

23 What if investment is not optimal?
Asymmetry of welfare loss transmission network costs in order of 1 €/MWh VOLL in order of 1000 – €/MWh Given uncertainty, some overinvestment is prudent (insurance against much higher cost of shortage). Introduction Network costs Current incentives What if we are wrong? Options Conclusions

24 What are the options?

25 Options for providing incentives
Benchmark competition each transmission network is unique Proxy incentives for calculating NTCs for reducing congestion for estimating need for new capacity correctly Possible solution to the issue of coordination with generation: ‘auctions’ for subsidies to G (Stoft) FTRs? Introduction Network costs Current incentives What if we are wrong? Options Conclusions

26 Opportunities for incentives to TSOs
Regulation of TSO revenues  efficiency based on cost based on benchmarks Performance incentives congestion available network capacity network reliability economic performance of investments typically proxy incentives Introduction Network costs Current incentives What if we are wrong? Options Conclusions

27 Example of proxy incentives: NorNed
Dutch & Norwegian TSOs Regulated investment (rate base, not merchant) Initial business case negative TSO’s response: capacity increase 600 MW  700 MW at no cost (!) guarantees from neighboring TSOs for full utilization of cable lower connection costs Now business case neutral. Introduction Network costs Current incentives What if we are wrong? Options Conclusions

28 Incentives in NorNed Dutch regulator attached conditions to regulatory approval: incentives relating to moment that cable is operational under/over budget realisation availability of cable Introduction Network costs Current incentives What if we are wrong? Options Conclusions

29 Conclusion Options for incentive-based regulation limited
better in simple, linear networks and for DC links when theoretically optimal incentives are not feasible, proxy incentives may be a solution evolution of pragmatic regulations  credibility problem, also repeat games between sector and regulator (Joskow) The social cost of too little investment is much higher than the cost of some excess investment. Given the complexity: better safe than sorry simple regulation, slight overinvestment might be the most secure solution. Introduction Network costs Current incentives What if we are wrong? Options Conclusions


Download ppt "Transmission investment"

Similar presentations


Ads by Google