1 Rick Soucy GZA GeoEnvironmental, Inc.
Compliance with New Air Pollution Regulations for Boilers and Emergency Generators - The Basics of What Every Facilities Manager Should Know NEHES Fall Conference October 1, 2013 Rick Soucy GZA GeoEnvironmental, Inc.

2 Overview Recent Federal Regulations Impact Hospital Operations
Affected Equipment – Boilers, Emergency Generators, Chiller Engines, Cogeneration Engines Regulations Complex Compliance Deadlines Looming Basics to Know Applicability Compliance Requirements, i.e., How to Comply Compliance Schedule, i.e., When to Comply By

3 Regulatory Background
CAAA of 1990 (Title III) Mandated EPA to Develop Rules to Reduce Emissions of Hazardous Air Pollutants (HAPs) National Emission Standards for Hazardous Air Pollutants for Source Categories (NESHAPs) a.k.a. “MACT” (Maximum Achievable Control Technology) Standards Promulgated at Federal Level by EPA Enforcement May Be Delegated to States

4 Why Regulate HAP Sources?
Known or Suspected to Cause Cancer and Other Serious Health Effects Aggravate Respiratory and Cardiovascular Disease Changes in Lung Function Adverse Effects on Child Development Premature Deaths

5 HAPs and MACT Standards
187 HAPs Currently Regulated MACT Standards for 133 Source Categories to Date Today’s Focus: Area Source Boiler MACT Rule - 40 CFR Part 63, Subpart JJJJJJ (“6J”) Stationary RICE (Reciprocating Internal Combustion Engine) MACT Rule - 40 CFR Part 63, Subpart ZZZZ (“4Z”)

6 Clarification Area Source vs. Major Source
Major HAP Source: > 10 Tons/Year of Any Single HAP or > 25 Tons/Year of Total HAPs Area HAP Source: Any Facility That is Not Major

7 Area Source Boiler MACT 40 CFR Part 63, Subpart JJJJJJ
Applies to Industrial, Commercial, and Institutional Boilers at Area Sources History First Proposed by EPA on June 4, 2010 Thousands of Comments Received Originally Finalized on March 21, 2011 Simultaneous Notice of Reconsideration Another Notice of Reconsideration and Proposed Amendments on December 23, 2011 “Final” Rule on February 1, 2013 Lawsuits Filed by Environmental and Industry Groups

8 Area Source Boiler MACT 40 CFR Part 63, Subpart JJJJJJ
Q. Why Has Boiler MACT Been So Controversial? A. There Are a Lot of Boilers ~ 1.5 million Of These, EPA Estimates: 86% Are Clean and Not Covered by the Rule 13% Are Subject to Work Practice Standards 1% Are Subject to Numerical Emission Limits Most Hospitals and Healthcare Facilities

9 What Boilers Are Exempt from Boiler MACT?
Gas-Fired Boilers EPA Definition: Gas-Fired boiler includes any boiler that burns gaseous fuels not combined with any solid fuels and burns liquid fuel only during periods of gas curtailment, gas supply interruption, startups, or periodic testing on liquid fuel. Periodic testing of liquid fuel shall not exceed a combined total of 48 hours during any calendar year.

10 What Other Boilers Are Exempt from Boiler MACT?
Residential Boilers Hot Water Heaters with Capacity < 120 gallons Hot Water Boilers (Not Generating Steam) with Heat Input Capacity < 1.6 MMBtu/hr Electric Boilers Temporary Boilers Must Be Portable Must Not Remain at Same Location More Than 12 Consecutive Months

11 Area Source Boiler MACT
Applicable Compliance Requirements Vary According to: Size (capacity) of Boiler When Constructed (before or after June 4, 2010) Type of Fuel Combusted

12 Summary of Requirements
Summary of Area Source Boiler MACT Emission Limit and Work/Management Practice Requirements Subcategory Summary of Requirements Existing large area source boilers i.e., commenced construction or reconstruction of the boiler on or before June 4, 2010; greater than or equal to 10 MMBtu/hr Gas (all types) No requirements (not covered by the rule) Coal (excluding limited-use boilers) Numeric emission limits for mercury (Hg) and carbon monoxide (CO) One-time energy assessment Biomass or Oil Initial tune-up Subsequent tune-ups every other year or every 5 years No numeric emission limits Limited-use Coal Subsequent tune-ups every 5 years No energy assessment Existing small area source boilers i.e., commenced construction or reconstruction of the boiler on or before June 4, 2010; less than 10 MMBtu/hr Coal, Biomass or Oil

13 Summary of Requirements
Summary of Area Source Boiler MACT Emission Limit and Work/Management Practice Requirements Subcategory Summary of Requirements New large area source boilers i.e., commenced construction or reconstruction of the boiler after June 4, 2010; greater than or equal to 10 MMBtu/hr Gas (all types) No requirements (not covered by the rule) Coal (excluding limited-use boilers) Numeric emission limits for Hg, CO, and particulate matter (PM) Biomass or Oil (excluding limited-use and seasonal boilers) Numeric emission limit for PM* Tune-up every other year or every 5 years Limited-use Coal Tune-up every 5 years No numeric emission limits Limited-use and Seasonal Biomass or Oil New small area source boilers i.e., commenced construction or reconstruction of the boiler after June 4, 2010; less than 10 MMBtu/hr Coal, Biomass or Oil *New oil-fired boilers that combust only oil with no more than 0.50 % sulfur (or a mixture of 0.50 % sulfur oil with other fuels not subject to a PM emission limit) are not subject to a PM emission limit provided they do not use emission controls (except a wet scrubber) to reduce PM or SO2 emissions.

14 Boiler MACT Tune-up Requirements
Conduct According to EPA Specifications Tune-up on Fuel That Provided the Majority of the Heat Input to the Boiler Over Last 12 Months Inspect Burner – Clean and Replace Components, as Necessary Inspect Flame Pattern and Adjust Burner to Optimize Inspect Air-to-Fuel Ratio Controller, if Equipped Optimize CO Emissions Consistent with Manufacturer’s Specifications Measure the Exhaust Concentration of CO and O2 Before and After Any Adjustments Made Maintain Report That Identifies Measured Concentrations and Corrective Actions

15 Boiler MACT Energy Assessment Requirements
Must Be Performed By a Qualified Energy Assessor Assessment Must Include: Visual Inspection of Boiler System Evaluation of Operating Characteristics and Specifications of the Boiler System Inventory of Major Energy Use Systems Consuming Energy from the Boiler Review of Architectural/Engineering Plans, Operations and Maintenance Procedures/Logs, and Fuel Usage List of Major Energy Conservation Measures Within the Facility’s Control List of the Energy Savings Potential of Energy Conservation Measures Comprehensive Report Detailing Ways to Improve Efficiency, Cost of Specific Improvements, and Payback Periods

16 Boiler MACT Energy Assessments -Other Things to Know-
On-Site Technical Labor Hours Can be Limited – Depends on Total Annual Heat Input Capacity of the Boiler Requirement Satisfied if Already Had Assessment Done After 1/1/2008 and if Met EPA Specifications Requirement Satisfied if Facility Operates Under an Energy Management Program Compatible with ISO That Includes the Affected Boiler

17 Boiler MACT -Other Requirements-
Submit Notifications (as applicable) Keep Records of Fuel Usage Prepare Compliance Certification Reports Boilers with Emission Limits: Performance Tests Fuel Analyses Continuous Monitoring Systems

18 Boiler MACT Compliance Dates
Initial Notification: January 20, 2014 or Within 120 Days of When a New Boiler Becomes Subject Initial Tune-ups and Energy Assessments: March 21, 2014 Emission Limits: March 21, 2014 (Performance Testing Required Within 180 Days) Notification of Compliance Status for Tune-Ups and Energy Assessments: July 19, 2014 Prepare Annual Compliance Certifications by March 1 of Every Year Note: Notifications may have to be sent electronically using CEDRI Interface.

19 Helpful Web Sites for Boiler MACT
EPA Region 1 List of Qualified Energy Assessors General Information and Compliance Tools

20 RICE MACT 40 CFR Part 63, Subpart ZZZZ
Applies to Stationary Engines of All Types and Sizes Existing and New Emergency and Non-Emergency Compression Ignition (CI) Spark Ignition (SI) Does Not Apply to Non-Road Engines or Motor Vehicle Engines

21 RICE MACT History Originally Proposed by EPA on December 19, 2002: RICE > 500 HP at Major Sources Revised and Expanded: January 18, 2008, March 3, 2010, August 20, 2010, March 9, 2011 “Final” Amendments on January 30, 2013 Notice of Reconsideration: September 5, 2013

22 RICE MACT Applicability to Hospitals and Healthcare Facilities
Emergency Engines (Generators and Fire Pump Engines) Gas-Fired Chiller Engines Gas-Fired Cogeneration Engines Focus: Compliance Requirements at Area Sources

23 RICE MACT Compliance Requirements for Emergency Engines
GOOD NEWS !! Existing Institutional Emergency Engines are Exempt BUT…

24 RICE MACT Compliance Requirements for Emergency Engines
Must Operate in Accordance with EPA Definition of an Emergency Stationary RICE, i.e., Maximum 100 hr/yr Total for Maintenance/Testing, Emergency Demand Response, and > 5% Voltage/Frequency Deviations 50 Hours of the 100 hr/yr Allocation Allowed for Non-Emergency Situations (excluding peak shaving or financial arrangements, with limited exceptions) Must Not Operate (or be contractually obligated to operate) More Than 15 hr/yr for Emergency Demand Response (EDR) * and >5% Voltage/Frequency Deviations * “Energy Emergency Alert Level 2” Per Reliability Coordinator

25 RICE MACT Compliance Requirement for Emergency Engines
- No Limit on Emergency Operations - WARNING! Your State or Local Air Pollution Control Authority May Have More Stringent Operating Limits and Compliance Requirements

26 RICE MACT – Emergency Engines
What if Your Emergency RICE Operates or is Contractually Obligated >15 hr/yr for Emergency Demand Response? ULS Fuel (<15 ppm) by January 1, 2015 Operate/Maintain Engine According to Manufacturer’s Instructions Subject to Management Practices Change Oil/Filter Every 500 Operating Hours, or Annually Inspect Air Cleaner Every 1,000 Operating Hours, or Annually Inspect Hoses and Belts Every 500 Operating Hours, or Annually Inspect Spark Plugs Every 1,000 Operating Hours, or Annually

27 RICE MACT – Emergency Engines
What if Your Emergency RICE Operates or is Contractually Obligated >15 hr/yr for Emergency Demand Response? If >100 HP, Submit Annual Report Engine Rating/Model Year Latitude/Longitude of Engine Location Identify Contractual Obligations Operating Hours for EDR and Voltage/Frequency Deviations (Dates, Start Times, Stop Times) Reason for Each Dispatch First Report Due 3/31/2016 for Calendar Year 2015

28 RICE MACT – Emergency Engines
What If Allowable Non-Emergency Operations Exceed 100 hr/yr? SEVERE CONSEQUENCES Management Practices (oil changes, inspections, etc.) Emission Limits or Emission Reduction Requirements Install Emission Control Equipment Conduct Emission Performance Tests Monitor Exhaust Catalyst Performance Parameters Semi-Annual Compliance Reports Notifications to EPA and State Authority

29 RICE MACT Applicability to “New” Emergency Engines
“New” If Construction Commenced On or After 6/12/2006 Must Instead Comply with Federal NSPS 40 CFR Part 60, Subpart IIII for CI Engines 40 CFR Part 60, Subpart JJJJ for SI Engines General NSPS Requirements Purchase a Certified Engine Emission Performance Tests (Non-Certified SI) Operate According to Emergency Engine Limitations Non-Resettable Hour Meter ULS Fuel (CI) Install/Operate/Maintain According to Manufacturer’s Instructions

30 RICE MACT Compliance Requirements for Existing Non-Emergency Engines
Gas-Fired Chiller Engines Gas-Fired Cogeneration Engines Five Gas-Fired Engine Categories 2SLB 4SLB < 500 HP 4SRB < 500 HP 4SLB > 500 HP 4SRB > 500 HP

31 RICE MACT Compliance Requirements Existing Non-Emergency 2SLB Engines
Change Oil/Filter Every 4,320 Operating Hours, or Annually Inspect Spark Plugs Every 4,320 Operating Hours, or Annually (Replace as Necessary) Inspect Hoses/Belts Every 4,320 Operating Hours, or Annually (Replace as Necessary) Operate to Minimize Emissions

32 RICE MACT Compliance Requirements Existing Non-Emergency 2SLB Engines (continued)
Maintain Engine and Control Device According to Manufacturer’s Instructions, or Develop Maintenance Plan Minimize Idling Time During Start-up Limit Start-up Time to 30 Minutes Keep Maintenance Records Must Comply by October 19, 2013

33 Compliance Date: October 19, 2013
RICE MACT Compliance Requirements Existing Non-Emergency 4SLB and 4SRB Engines < 500 HP Same Requirements as for 2SLB, Except: Maintenance Interval = Every 1,440 Operating Hours, or Annually Compliance Date: October 19, 2013

34 RICE MACT Compliance Requirements Existing Non-Emergency 4SLB Engines > 500 HP
Initial Notification Was Due on February 16, 2011 Install Oxidation Catalyst by October 19, 2013 Conduct Initial Compliance Demonstration by April 18, 2014 Must Demonstrate: Average CO Emission Reduction > 93%, or Average CO Concentration < 47 ppmvd at 15% O2 Submit Notification of Intent at Least 60 Days Prior to Test Submit Notification of Compliance Status Within 60 Days After Initial Compliance Demonstration Subsequent Annual Compliance Demonstrations

35 RICE MACT Compliance Requirements Existing Non-Emergency 4SLB Engines > 500 HP (continued)
Install CPMS for Catalyst Inlet Temperature or Automatic Shutdown Device if Catalyst Inlet Temperature > 1,350˚F (by October 19, 2013) If CPMS, Maintain 4-hour Rolling Average Inlet Temperature Between 450 ˚F and 1,350˚F Submit Semi-Annual Compliance Reports

36 Same Requirements as for 4SLB > 500 HP, Except:
RICE MACT Compliance Requirements Existing Non-Emergency 4SRB Engines > 500 HP Same Requirements as for 4SLB > 500 HP, Except: Must Install NSCR (3-Way Catalyst) by October 19, 2013 Must Demonstrate: Average CO Emission Reduction > 75%, or Average CO Concentration < 270 ppmvd at 15% O2, or Average THC Emission Reduction > 30% Install CPMS for Catalyst Inlet Temperature or Automatic Shutdown Device if Catalyst Inlet Temperature > 1,250˚F If CPMS, Maintain 4-Hour Rolling Average Inlet Temperature Between 750˚F and 1,250˚F

37 RICE MACT Applicability to “New” Cogeneration or Chiller Engines
“New” if Construction Commenced On or After 6/12/2006 Instead Comply with NSPS – 40 CFR 60, Subpart JJJJ Purchase a Certified Engine (if you can) Non-Certified Engines Requirements Depend on Size, Type, and Manufacture Date Emission Limits (NOx, CO, VOC) Initial and Subsequent Performance Tests Notifications, Recordkeeping, and Reporting

38 Helpful Web Sites for RICE MACT
General Information and Compliance Tools EPA Region I – New England EPA Technology Transfer Network

39 Questions ???

40 Compliance with New Air Pollution Regulations for Boilers and Emergency Generators – The Basics of What Every Facilities Manager Should Know NEHES Fall Conference October 1, 2013 Contact: Rick Soucy GZA GeoEnvironmental, Inc. 655 Winding Brook Drive, Suite 402 Glastonbury, CT 06033 Phone: (860) Fax: (860)