DG ENV Environmental assessment procedures for energy infrastructure projects of common interest (PCIs)

Similar presentations


Presentation on theme: "DG ENV Environmental assessment procedures for energy infrastructure projects of common interest (PCIs)"— Presentation transcript:

1 DG ENV Environmental assessment procedures for energy infrastructure projects of common interest (PCIs)

2 Legislative background Regulation (EU) No 347/2013 on guidelines for trans- European energy infrastructure (New TEN-E Regulation) adopted on 17 April 2013

3 The new TEN-E regulation Process to identify projects of common European interest, with involvement of all stakeholders Accelerated permit granting Improved Regulatory treatment Financial support Benefits 3.5 years One stop shop Incentives Cost allocation Financial instru- ments Grants Public participati on

4 Accelerated permit granting: Time-limits (Art. 10) One-stop-shop approach, national competent authority (Art. 8) Transparency and public participation (Art. 9) By 16 May 2014, MS had to publish manual of procedures for the permit granting process of PCIs, accessible to public Project promoter has to develop and submit concept for public participation for approval of the competent authority Cross-border public consultation Project promoter or competent authority shall establish website with relevant information on PCIs Streamlining environmental assessment procedures (Art. 7)

5 EC DG ENER/ ENV5 Environmental assessments required under Union law Environmental Impact Assessment (EIA) Directive Strategic Environmental Assessment (SEA) Dir. Birds and Habitats Directives Water Framework Directive (WFD) Marine Strategy Framework Directive (MSFD) Seveso II and Seveso III Directives Industrial Emissions Directive replacing the Integrated Pollution Prevention and Control (IPPC) Directive UNECE Conventions : Espoo Convention on EIA in a transboundary context SEA Protocol to the Espoo Convention Aarhus Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters

6 Environmental Assessments Policies Plans & Programmes covered by SEA Directive (2001/42) Projects (public - private) covered by EIA Directive (2011/92) Habitats and Birds Directives Waste Framework Directive Landfill Directive Carbon Capture Storage Directive IED Directive Water Framework Directive

7 Recommendations : Early planning, "roadmapping" and scoping of assessments Early and effective integration of environmental assessments and of other environmental requirements Procedural co-ordination and time limits Data collection, sharing and quality control Cross-border co-operation Early and effective public participation

8 Recommendation 6: Early and effective public participation Early information and involvement is crucial!! When? Ideally at conceptual stage – when all options are open. Roadmapping should set out different stages of public consultation in the overall process (e.g. public scoping events). As for assessments, there should be efficient tiering of public participation to avoid both gaps and overlaps. It is strongly recommended to consult the concerned public also about possible impacts to Natura 2000 sites.

9 Guidance – relevant phases

10 The Environmental Assessment Procedures Scope and level of detail (obligatory under the SEA) The “Report” (including a non- technical summary) Public, environmental authorities, other MSs/countries... Takes account of env. report and consultations End of EIA/SEA process Scoping Decision Information on decision EIA Report Screening (for Annex II projects) Information and Consultation Monitoring For projects screened out(shorter procedure) Using screening criteria listed in Annex III Only for SEA, as of 2017 for EIA

11 11 Screening – Principles Information of the EIA Report – Art.5(1)  Mirroring the changes in Article 3 (scope of EIA).  To avoid duplication, the developer has to take into take into account the results of other relevant assessments [SEA, Habitats, Water Directives].  Specific information to be provided by developer: description of the project (site, design, size and other relevant features); description of the likely significant effects; description of the features and/or measures of the project envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects; description of the reasonable alternatives studied by the developer relevant to the project and its specific characteristics, and an indication of the main reasons for the option chosen; non-technical summary; additional information specified in Annex IV. Scoping EIA report Consultation Decision Information on decision Screening Monitoring

12 12 Screening – Principles Consultation – Articles 6 and 7  Broadened scoped: local and regional authorities clearly spelled out as bodies to be consulted.  Reinforced modalities: Public to be informed electronically and by public notices (Art.6 (5)) Relevant information electronically accessible to the public, through at least a central portal or easily accessible points of access, at the appropriate administrative level (Art. 6 (5)) Reasonable time-frames for the different phases of the decision-making (Art. 6(6)). Time-frame for consulting the public concerned on the EIA report - at least 30 days (Art. 6(7)).  Transboundary consultations: Consultations may be conducted through an appropriate joint body (Art.7(4)). Time-frames for public consultation to be set (Art. 7(5)). Scoping EIA report Consultation Decision Information on decision Screening Monitoring

13 13 Screening – Principles NEW: EIA one-stop shop (Art.2(3))  Coordinated/integrated procedure, where appropriate, for assessments under EIA and/or Habitats/Birds Directives (only!).  For assessments under EIA and other Union legislation (e.g. SEA, Water Framework, IED, Waste Framework, Seveso, listed in recital 37) possibility to apply one-stop shop.  Short explanations of coordinated/integrated procedures.  COM to issue guidance on coordinated/integrated procedures. Scoping EIA report Consultation Decision Information on decision Screening Monitoring

14 14 Screening – Principles Information on the final decision – Article 9 No significant changes:  Obligation to inform the public and relevant (environmental and local/regional) authorities promptly;  Obligation to make available to the public relevant (environmental and local/regional) authorities specific information: Content of the final decision (no change). Main reasons (no change). NEW: Summary of the results of the consultations and the information gathered and how those results have been incorporated or otherwise addressed, in particular the comments received from the affected Member State(s), shall be made available as well. Scoping EIA report Consultation Decision Information on decision Screening Monitoring

15 Thank you for your attention!


Download ppt "DG ENV Environmental assessment procedures for energy infrastructure projects of common interest (PCIs)"