Presentation is loading. Please wait.

Presentation is loading. Please wait.

Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L.

Similar presentations


Presentation on theme: "Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L."— Presentation transcript:

1 Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L. Blackmar, P.E. (Tetra Tech)

2 Project Team Client: Lower Fox River Remediation LLC Engineering Design & Construction: Tetra Tech Dredging & Capping: J.F. Brennan Co., Inc. Desanding & Dewatering: Stuyvesant Projects Realization Inc., affiliate of Boskalis Dolman Anchor QEA, LLC: assist with design URS: assist with modeling Numerous local construction subcontractors

3 OU 2 – 5 // 13 MILES (21 KM ) // C OMBINED R EMEDY // T HE GOAL OF THE PROJECT IS TO REMEDIATE PCB BEARING SEDIMENT BY DREDGING, CAPPING, OR COVERING // H YDRAULIC D REDGING // S EDIMENT P ROCESSING & S AND R EUSE // W ATER T REATMENT // O FFSITE T&D Project Scope

4 Processing Facility DESIGN STARTED IN MARCH 2008 // B EGAN PROCESSING A PRIL 2009 // UNIQUE SINGLE STREAM PROCESS // 150-250 IN - SITU CY / HR (190 M 3 / HR ) // 6000 GALLON / MIN. (1,400 M 3 / HR ) // 6 ACRE BUILDING (2.4 HA ) // AIR QUALITY CONDITIONED

5 Objective One objective of the Fox River processing facility is to minimize the contaminated volume disposed of at the landfill by beneficial use of the separated coarse fractions (sand) and by dewatering the fine (contaminated) fraction

6 Three phase treatment 1) P RE - CONDITIONING // 2) S AND SEPARATION AND POLISHING FOR BENEFICIAL USE ( ABOUT 19% SAND ), TWO SAND FRACTIONS ARE SEPARATED // 3) MECHANICAL DEWATERING

7 Why Separate Sand? Prevent additional wear and tear on downstream process equipment Reduce the dewatering cycle time from not having to process the sand Avoid unnecessary expense for T&D as waste Avoid consuming landfill space Various beneficial reuse opportunities

8 Separated Sand Parameters ~ 18,000 tons of sand separated in 2009 ~ 56,000 tons of sand separated in 2010 ~ 22,000 tons of sand separated in 2011 ~ 19,000 tons of sand projected for 2012 Coarse sand ranges from 150 µm to 6 mm Fine sand ranges from 63 µm to 150 µm

9 Recovered sand outside of processing facility

10 Stockpiled & covered; awaiting load-out for reuse

11 Sampling Parameters Fine & coarse sand sampled once each 1,000 cy for the first 10,000 cy Then one sample/10,000 cy for 10,000 to 50,000 cy Then one sample/50,000 cy thereafter 2009 chemistry: 27 fine sand samples and 10 coarse sand samples 2010 chemistry: 39 fine sand & 32 coarse sand 2011 chemistry: 11 fine sand & 12 coarse sand

12 Chemical Testing Criteria for Sand Proposed ConstituentsProject-Specific Maximum Allowable Contaminant Concentrations (mg/kg) PCB, Total.0.49 (mg/kg) Total 2,3,7,8 TCDD0.19 (ug/kg) Total 2,3,7,8 TCDF0.19 (ug/kg) DDT (and its metabolites DDD & DDE)1.0 Arsenic9.8 Barium500 Cadmium7.8 Chromium14.5 Copper150 Cyanide100 Iron20,000 Lead50 Manganese1100 Mercury4.7 Nickel250 Selenium63 Zinc1500

13 Additional Notes – Sand Testing Criteria Geotechnical Properties  For information only: – Grain size – Percent solids – Total organic carbon – Moisture content WDNR provided Project Specific Maximum Allowable Contaminant Concentrations in December 2008  The concentrations shown pertain to sand that is not capped in place, and are therefore conservative if applied to sand that will be capped.

14 Chemical Characteristics Average PCB Concentration (ppm) vs. target of 0.49 ppm 200920102011 Fine sand (63 µm to 150 µm) 0.2620.1810.137 Coarse sand (150 µm to 6 mm) 0.3530.1110.075 Running average (combined fractions) 0.2800.1480.100

15 Beneficial Reuse Process Prepare and submit Low Hazard Waste Exemption Request naming specific offsite projects (*one Request per project) Public works projects are preferred Address WDNR comments to the Request Participate in public meeting concerning the Request Finalize commercial arrangements Provide appropriate temporary erosion controls at the beneficial reuse site Track and report on sand shipped for beneficial reuse.

16 Win - Win for 2 Major Regional Projects


Download ppt "Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L."

Similar presentations


Ads by Google