ECE 4006B Fall, 2002, Group 1, Mei Chan Progress Report Period (November 22-December 5, 2002) Receive and complete assemble 2 nd PCB board Complete the.

Similar presentations


Presentation on theme: "ECE 4006B Fall, 2002, Group 1, Mei Chan Progress Report Period (November 22-December 5, 2002) Receive and complete assemble 2 nd PCB board Complete the."— Presentation transcript:

1 ECE 4006B Fall, 2002, Group 1, Mei Chan Progress Report Period (November 22-December 5, 2002) Receive and complete assemble 2 nd PCB board Complete the alignment tolerance test on 1 st transmitter board Complete transmitter testing on 2 nd board with connectorized components on both design Complete the final report Progress to date: Planned Work: Return all the hardware components to Dr. Brooke Complete and turn in the course survey

2 Final Board Layout Receiver board Tx board design 1 Tx board design 2

3 Improved First Tx board Patch Cord, our ReceiverPatch Cord, Receiver box 100m fiber, our Receiver 100m fiber, Receiver box

4 Second Tx board Testing Patch cord, our Receiver Patch cord, Receiver box 100m fiber, our Receiver100m fiber, Receiver box

5

6 Have a great time in this class Good luck on your other finals !