Presentation is loading. Please wait.

Presentation is loading. Please wait.

Purposes of Inventory 1. To maintain independence of operations. 2. To meet variation in product demand. 3. To allow flexibility in production scheduling.

Similar presentations


Presentation on theme: "Purposes of Inventory 1. To maintain independence of operations. 2. To meet variation in product demand. 3. To allow flexibility in production scheduling."— Presentation transcript:

1 Purposes of Inventory 1. To maintain independence of operations. 2. To meet variation in product demand. 3. To allow flexibility in production scheduling. 4. To provide a safeguard for variation in raw material delivery time. 5. To take advantage of economic purchase- order size.

2 Basic Fixed-Order Quantity Model and Reorder Point Behavior Exhibit 13.3 R = Reorder point Q = Economic order quantity L = Lead time L L QQQ R Time Number of units on hand

3 Inventory Costs Holding (or carrying) costs. –Costs for storage, handling, insurance, etc. Setup (or production change) costs. –Costs for arranging specific equipment setups, etc. Ordering costs. –Costs of someone placing an order, etc. Shortage costs. –Costs of canceling an order, etc.

4 Cost Minimization Goal Ordering Costs Holding Costs Q OPT Order Quantity (Q) COSTCOST Annual Cost of Items (DC) Total Cost By adding the item, holding, and ordering costs together, we determine the total cost curve, which in turn is used to find the Q opt inventory order point that minimizes total costs.

5 Basic Fixed-Order Quantity (EOQ) Model Formula Total Annual Cost = Annual Purchase Cost Annual Ordering Cost Annual Holding Cost ++ TC =Total annual cost D = Demand C = Cost per unit Q = Order quantity S = Cost of placing an order or setup cost R = Reorder point L = Lead time H = Annual holding and storage cost per unit of inventory

6 Fixed-Order Quantity Model with Safety Stock Formula R = Average demand during lead time + Safety stock

7 Determining the Value of  L The standard deviation of a sequence of random events equals the square root of the sum of the variances.

8 ABC Classification System Items kept in inventory are not of equal importance in terms of: – dollars invested – profit potential – sales or usage volume – stock-out penalties 0 30 60 30 60 A B C % of $ Value % of Use So, identify inventory items based on percentage of total dollar value, where “A” items are roughly top 80 %, “B” items as next 15 %, and the lower 5% are the “C” items.

9 Schedule Performance Measures Meeting due dates of customers or downstream operations. Minimizing the flow time (the time a job spends in the process). Minimizing work-in-process inventory. Minimizing idle time of machines or workers.

10 Principles of Work Center Scheduling 1. There is a direct equivalence between work flow and cash flow. 2. The effectiveness of any job shop should be measured by speed of flow through the shop. 3. Schedule jobs as a string, with process steps back-to-back. 4. A job once started should not be interrupted.

11 Principles of Job Shop Scheduling (Continued) 5. Speed of flow is most efficiently achieved by focusing on bottleneck work centers and jobs. 6. Reschedule every day. 7. Obtain feedback each day on jobs that are not completed at each work center. 8. Match work center input information to what the worker can actually do.

12 Principles of Job Shop Scheduling (Continued) 9. When seeking improvement in output, look for incompatibility between engineering design and process execution. 10. Certainty of standards, routings, and so forth is not possible in a job shop, but always work towards achieving it.

13 Just-In-Time (JIT) Defined JIT: an integrated set of activities designed to achieve high-volume production using minimal inventories (RM, WIP, FG). JIT involves: – the elimination of waste in production effort. –the timing of production resources (e.g., parts arrive at the next workstation “just in time”).

14 JIT Demand-Pull Logic Customers Vendor Sub Fab Final Assembly

15 Minimizing Waste: Inventory Hides Problems Work in process queues (banks) Change orders Engineering design redundancies Vendor delinquencies Scrap Design backlogs Machine downtime Decision backlogs Inspection backlogs Paperwork backlog Example: By identifying defective items from a vendor early in the production process the downstream work is saved. Example: By identifying defective work by employees upstream, the downstream work is saved.

16 Kanban Japanese word for card –Pronounced ‘kahn-bahn’ (not ‘can-ban’) Authorizes production from downstream operations –‘Pulls’ material through plant May be a card, flag, verbal signal etc. Used often with fixed-size containers –Add or remove containers to change production rate

17 Minimizing Waste: Kanban Production Control Systems Exhibit 10.6 Storage Part A Machine Center Assembly Line Material Flow Card (signal) Flow Withdrawal kanban Production kanban

18 Characteristics of JIT Vendor Partnerships Few, nearby suppliers Long-term contract agreements Steady supply rate Frequent deliveries in small lots Buyer helps suppliers meet quality Suppliers use process control charts Buyer schedules inbound freight

19 Respect for People Level payrolls Cooperative employee unions Subcontractor networks Bottom-round management style Quality circles (Small group involvement activities)

20 JIT Implementation Issues Level the Facility Load Eliminate Unnecessary Activities Reorganize Physical Configuration Introduce Demand-Pull Scheduling Develop Supplier Networks

21 Goldratt’s Rules of Production Scheduling Do not balance capacity balance the flow. The level utilization of a nonbottleneck resource is not determined by its own potential but by some other constraint in the system. Utilization and activation of a resource are not the same. An hour lost at a bottleneck is an hour lost for the entire system. An hour saved at a nonbottleneck is a mirage.

22 Goldratt’s Rules of Production Scheduling (Continued) Bottlenecks govern both throughput and inventory in the system. Transfer batch may not and many times should not be equal to the process batch. A process batch should be variable both along its route and in time. Priorities can be set only by examining the system’s constraints. Lead time is a derivative of the schedule.

23 Goldratt’s Theory of Constraints (TOC) Identify the system constraints. Decide how to exploit the system constraints. Subordinate everything else to that decision. Elevate the system constraints. If, in the previous steps, the constraints have been broken, go back to Step 1, but do not let inertia become the system constraint.

24 Saving Time Bottleneck Nonbottleneck What are the consequences of saving time at each process? Rule: Bottlenecks govern both throughput and inventory in the system. Rule: An hour lost at a bottleneck is an hour lost for the entire system. Rule: An hour saved at a nonbottleneck is a mirage.

25 Drum, Buffer, Rope ABCDEF Bottleneck (Drum) Inventory buffer (time buffer) Communication (rope) Market Exhibit 17.9

26 Quality Implications of synchronous manufacturing More tolerant than JIT systems – Excess capacity throughout system. Except for the bottleneck – Quality control needed before bottleneck.

27 Inventory Cost Measurement: Dollar Days Dollar Days is a measurement of the value of inventory and the time it stays within an area. Dollar Days = (value of inventory)(number of days within a department) Example

28 Benefits from Dollar Day Measurement Marketing – Discourages holding large amounts of finished goods inventory. Purchasing – Discourages placing large purchase orders that on the surface appear to take advantage of quantity discounts. Manufacturing – Discourage large work in process and producing earlier than needed.

29 Comparing Synchronous Manufacturing to MRP MRP uses backward scheduling. Synchronous manufacturing uses forward scheduling.

30 Comparing Synchronous Manufacturing to JIT JIT is limited to repetitive manufacturing JIT requires a stable production level JIT does not allow very much flexibility in the products produced

31 Comparing Synchronous Manufacturing to JIT (Continued) JIT still requires work in process when used with kanban so that there is "something to pull." Vendors need to be located nearby because the system depends on smaller, more frequent deliveries.


Download ppt "Purposes of Inventory 1. To maintain independence of operations. 2. To meet variation in product demand. 3. To allow flexibility in production scheduling."

Similar presentations


Ads by Google