NCSX Water Systems Larry Dudek March 21, 2003
2
Plan for FY03 Review questionable legacy equipment and verify viability for NCSX New Scope: NB support for their test
3
Status -Review of the existing documentation -Located copies of the piping schematic (sketches) - Wiring Diagrams -Inspection of the equipment -Water tank was inspected -Instrumentation vendor in to review existing I&C (Vacuum tube technology) -Missing components, (Rescued chiller from D-site) -Testing -Filled System with water and pressure tested at 100 psi for leaks for 1 hour.
4
Resource Issues -Legacy Equipment in need of repair/Replacement -DI Resin Tanks ($2700) Purchased for NB Tests -Temperature Controller including sensors ($3100) -Dewpoint transmitter and sensor ($1300)
5
Next 4 Weeks Polish water to prepare for NB tests Support NB tests with minimal cooling / DI water