Campus Plan Roosevelt Island campus > Laboratory of innovation > Open and inviting to the public > Sustainable and energy-efficient
2
BLOOMBER G CENTER
4
Public Open Space > More than 20% of the Site > No Gates, Walls or Barriers > Public Programming
5
Public Open Space > Laboratory of innovation > State of the art technologies > Sustainable and energy-efficient Bloomberg Center > Collaborative Work Environment > Net-Zero Goal > Public Café, Art and Programming
6
The Bridge > Co-Location Space for Companies > Cornell Tech Studio Space > Common Spaces for Programming
7
Residential Building > First High Rise Passive House in the World > Housing for Students, Faculty & Staff
8
2017 Phase One
9
Project Schedule Start of DemolitionJanuary 2013 End of DemolitionJune 2015 Start of SiteworkDecember 2014 Start of Bloomberg Ctr.March 2015 Start of The BridgeMay 2015 Start of Residential June 2015 Phase I OpeningSummer 2017
10
December 2014
11
January 2015
12
February 2015
13
March 2015
14
April 2015
15
May 2015
16
June 2015
17
July 2015
18
August 2015
19
September 2015
20
October 1, 2015
21
Bloomberg Center
22
October 1, 2015 Bloomberg Center The Bridge (Co-Location)
23
October 1, 2015 Bloomberg Center The Bridge (Co-Location) Residential Building
24
October 1, 2015
25
Current & Upcoming Work Sitework Utility installation on East and West roads (closed to public) Utility installation on campus Completion of CUP structure & start of equipment installation North Road to re-open by the week of October 12 Bloomberg Center Steel structure started September Façade/enclosure to start in January 2016 The Bridge (Co-Location) Steel structure to start in early October Façade/enclosure to start in Winter 2016 Residential Superstructure to start in mid October Façade/enclosure to start in Winter 2016
26
September 2015 Utilities & Roadways
27
September 2015 Utilities & Roadways
28
September 2015 Bloomberg Center
29
September 2015 Bloomberg Center
30
September 2015 Bridge (Co-Location)
31
September 2015 Bridge (Co-Location)
32
September 2015 Residential
33
September 2015 Residential
34
Construction Commitments Reduce truck traffic through largest voluntary barging effort in NYC history Minimum 17% MWBE participation in construction Union labor on all construction projects On-site air monitoring for duration of the project Extensive roadway & utility improvements Close communication with Roosevelt Island stakeholders
35
Barging for Demolition Reduction of more than 12,000 truck trips on Main Street
36
September 2015 Barging for Demolition
37
Barging for Construction
42
September 2015 Barging for Construction 1 3 2 4
43
Upcoming Milestones Reopening of North Loop Road Relocation of West Road fence to facilitate road reconstruction Steel construction at Bloomberg Center & The Bridge Concrete superstructure at Residential Building Start of geothermal wellfield
44
2017