Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce.

Similar presentations


Presentation on theme: "Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce."— Presentation transcript:

1 Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce

2 WPCF Background Need for Current Project Recommended Plan Project Cost Estimate Schedule Farmington WPCF Upgrade2 Agenda

3 Originally Constructed 1960s Expanded in 1970  Additional Capacity Upgrade & Expansion 1994  Additional Capacity  Effluent Ammonia Limits Continuous operation Farmington WPCF Upgrade3

4 WPCA Goals  Capacity for projected flows and loads  Upgrade aging infrastructure  More stringent permit limits  Nitrogen (Protect Long Island Sound)  Phosphorus (Protect Farmington River)  BOD 5 /TSS  Improve Energy Efficiency  Provide additional odor control 4Farmington WPCF Upgrade

5 5

6 PROJECT COMPONENTCOST CONSTRUCTION$47,460,000 CONSTRUCTION CONTINGENCY (5%)$2,370,000 TECHNICAL SERVICES (13.0%)$6,170,000 MATERIAL TESTING (0.5%)$240,000 ASBESTOS & LEAD PAINT ABATEMENT-$50,000 LEGAL / ADMINISTRATIVE / FINANCING$950,000 ENGINEERS ESTIMATE OF COST$57,240,000 6 Farmington WPCF Upgrade

7 CWF eligible funding $57,240,000 Anticipated grant (21.5%)-$12,306,600 Design (WPCA) -$ 2,893,000 Local share$42,040,400 Anticipated Assessments  Farmington @ 78.1%$ 32,833,552  Avon @ 9.5%$ 3,993,838  UCHC @ 6.8%$ 2,858,747  Burlington @ 4.8%$ 2,017,939  Canton @ 0.8%$ 336,552 7Farmington WPCF Upgrade

8 Annual Debt Service $1,991,100 (net of Assessments) Increase to Tax Rate.57 Mills Average Assessment $ 232,074 Tax Impact $132.58/Year 8

9 9Farmington WPCF Upgrade July 8 th Council Agenda – Set Public Hearing August 12 th Council Agenda  Public Hearing  Section 8-24 Referral  Bond Resolution  Set Special Town Meeting August through October – Project Information to Public Special Town Meeting – Oct. 25 th Referendum – Nov. 4 th

10


Download ppt "Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce."