Planning Habitat Restoration for Dredging Projects WEDA Midwest Chapter Conference Green Bay, Wisconsin April 27, 2012 Jack Brunner.

Similar presentations


Presentation on theme: "Planning Habitat Restoration for Dredging Projects WEDA Midwest Chapter Conference Green Bay, Wisconsin April 27, 2012 Jack Brunner."— Presentation transcript:

1 Planning Habitat Restoration for Dredging Projects WEDA Midwest Chapter Conference Green Bay, Wisconsin April 27, 2012 Jack Brunner

2 Outline Advantages of Habitat Restoration Planning Considerations Grand Calumet River: Case Study Lessons Learned Summary

3 Advantages of Habitat Restoration Wildlife and Ecosystem Benefits Community Relations Program Priority - EPA, USACE, and State Permitting Requirements Cost Savings

4 Planning Considerations: Assessment Factors

5 Planning Considerations: Project Components Stakeholders Funding/Authority Site Access Substrate Hydrology Vegetative Communities

6 Planning Considerations: Project Components Planting Strategy Performance Standards T&E Species Invasive Species Predator Control Maintenance

7 Planning Considerations

8 Grand Calumet River Great Lakes Legacy Act project EPA GLNPO, USFWS and State of Indiana Grand Calumet River AOC, Lake County, IN

9 WBGCR Reaches 1 & 2 and Roxana Marsh Restoration goals –Excavate ~109,000 CY of contaminated sediment from 19-acre marsh –Dredge river and wetland shelves –Remove invasive species –Restore native habitat –Stabilize banks Construction substantially complete: June 2012

10 West Branch Reaches 1 & 2 and Roxana Marsh

11 Roxana Marsh – Restoration Plan

12 Invasive Species Control Sprayed Phragmites in non-dredge areas Utility and other access limitations

13 Marsh Excavation Removed Phragmites root mass with contamination Used road mats for access

14 Marsh Excavation

15

16 River Dredging Undercut Phragmites along banks Removed from the site

17 Sand Capping Placed hydraulically in river Placed mechanically in marsh and wetland shelves

18 Mowing Prescribed burn restrictions Mowed after herbicide application

19 Raking or Tilling Tilled to improve seed to soil contact Depth limitations in pipeline buffer areas Raked as needed

20 Seeding and Planting Adjust planting zones based on as-built conditions Blanket seeded areas

21 Providing Habitat Structure Removed trees for site access Placed within pond and along shoreline as habitat structure

22 Bank Stabilization Used bioengineering techniques Modified design based on field conditions

23 EBGCR Reaches 4A and 4B

24

25 Lessons Learned Involve stakeholders early in planning Spray invasives before sediment removal Use prescribed burning where possible Adjust planting zones as needed Blanket seeded areas Install and maintain predator control fencing

26 Summary Consider assessment factors and project components during planning and design Employ adaptive management during project implementation Restoration takes time

27 Questions? Jack Brunner Tetra Tech jack.brunner@tetratech.com 312.201.7788