Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call June 20, 2008.

Similar presentations


Presentation on theme: "Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call June 20, 2008."— Presentation transcript:

1 Lead from the front Texas Nodal http://nodal.ercot.com 1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call June 20, 2008

2 Lead from the front Texas Nodal http://nodal.ercot.com 2 Agenda Outage Scheduler –Antitrust Admonition –Release 9.2 update –Q&A and Roll Call Appendix

3 Lead from the front Texas Nodal http://nodal.ercot.com 3 ERCOT Anti-Trust Admonition ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

4 Lead from the front Texas Nodal http://nodal.ercot.com 4 Update on Outage Scheduler Current Status The URL to access the Outage Scheduler is https://nodaleds.ercot.com/misportal/ https://nodaleds.ercot.com/misportal/ Testing window expanded until 6/30 Next Weeks Market Test Schedule STEC – TSP ((6/23) 1 – 3 PM) Calpine – QSE ((6/24) 9 – 11 AM) Westar ((6/24) 1 – 3 PM) Completed UI Test LCRA (TSP & QSE), Fulcrum Power Services LP, IPA Market Inc., ANP Funding LLC, BPTX, BTU (TSP & QSE), FPL, Oncor, Constellation, Calpine, City of San Antonio, Direct Energy, Centerpoint, Reliant Energy, Coral Power, Tenaska, Suez Energy, Brazos (TSP & QSE), NRG, Luminant, CPS, Topaz, AEP (TSP), STEC (QSE), City of College Station, Austin Energy, EnergyCo, Greenville Electric, Westar, City of Denton, Rayburn (QSE), Brownsville, Occidental, Eagle Energy, Formosa, TNMP, Magic Valley, AEP (QSE), City of Garland (TSP & QSE), J Aron, Rayburn, Exelon, Greenville Electric Future updates All future releases (web services and UI updates) will be published along with the ERCOT integrated program schedule.

5 Lead from the front Texas Nodal http://nodal.ercot.com 5 Q&A / Open Forum Roll-Call

6 Lead from the front Texas Nodal http://nodal.ercot.com 6 -Release 9.2 Information -Connectivity information -Links to Key Documentation -Metrics -Data preparation APPENDICES

7 Lead from the front Texas Nodal http://nodal.ercot.com 7 Follow-up to question on Outage Scheduler timeline EDS 4.9.2: MP Involvement EDS Phase DescriptionStartEndMP participation 9.2.1Forced Outage DetectionApr 15, 2008 May 23, 2008 Not required 9.2.2Connectivity / Submission testApr 15, 2008 Jun 30, 2008 Yes – 2 hour testing window per MP 9.2.3Validation of PerformanceJu1 01, 2008 Jul 15, 2008 Yes - submit outages from 9AM – 11AM for up to 2 weeks 9.2.4Validation of Outage Evaluation in EDS Jun 02, 2008 Aug 01, 2008 Not required 9.2.5Validation of Outage Scheduler Interfaces Apr 29, 2008 Aug 01, 2008 Not required 9.2.6Validation of Outage Postings in MIS May 02, 2008 Aug 01, 2008 Yes - MPs are required to download and validate Outage Scheduler reports posted on MIS

8 Lead from the front Texas Nodal http://nodal.ercot.com 8 Outage Scheduler EDS 4.9.2: Objectives EDS Phase DescriptionPhase Objectives 9.2.1Forced Outage DetectionVerify the ability of the EMS to receive outage list from OS Verify the automation and timing of information from the OS to the EMS Verify the FOD capability of the EMS 9.2.2Connectivity / Submission test Verify MIS connectivity (if applicable) Verify EWS connectivity (if applicable) Verify MP’s ability to enter outages Verify ERCOT’s ability to approve single and group outages Verify QSE/TSP ability to receive updates on outage status 9.2.3Validation of PerformanceVerify OS ability to receive a specified quantity of data from multiple sources simultaneously via both the RUI and the EWS Verify OS data available for real-time reports 9.2.4Validation of Outage Evaluation in EDS Verify OS ability to send outage requests for the time period defined by the EMS user. Verify OS ability to receive outage status changes from the OE 9.2.5Validation of Outage Scheduler Interfaces Verify outage transfers from the OS into the DA TSA Verify outage transfers into RUC Verify outage transfers to all other uses of OS information 9.2.6Validation of Outage Postings in MIS Verify outage transfers from the OS into the MIS Validate MIS Secure Area access to Market Participants with the appropriate Digital Certificate Verify performance

9 Lead from the front Texas Nodal http://nodal.ercot.com 9 Appendix - Outage Scheduler 4.9.2 Testing: Basic Communications Test Prior to this test QSEs and TSPs using External Web Services will need to have their network and security teams make the following changes: –QSE’s / TSP’s Outage Scheduler system must be able to access: https://nodaleds.ercot.com:80/2007-08/Nodal/eEDS/EWS/ NOTE: this SSL URL is on port 80 https://nodaleds.ercot.com:80/2007-08/Nodal/eEDS/EWS/ –Market Participants must be able to receive / send transactions to/from the following IP ranges: 66.128.16.0/24 66.128.17.0/24 66.128.18.0/24

10 Lead from the front Texas Nodal http://nodal.ercot.com 10 QSEs and TSPs using MIS (RUI) will need to have their network and security teams make the following changes: –Ports will be 80 and 443 –Market Participants must be able to receive / send transactions to/from the following IP ranges: 66.128.16.0/24 66.128.17.0/24 66.128.18.0/24 Appendix - Outage Scheduler 4.9.2 Testing: Basic Communications Test

11 Lead from the front Texas Nodal http://nodal.ercot.com 11 Key Documentation Key documents are available at http://nodal.ercot.com/readiness/eds4/documents/index.htmlhttp://nodal.ercot.com/readiness/eds4/documents/index.html

12 Lead from the front Texas Nodal http://nodal.ercot.com 12 Outage Scheduler 4.9.2 Tracking: Readiness Metrics TPTF approved MP20 to track MP ability to submit outages to the Nodal Outage Scheduler. Execution –MP’s that have met readiness metric MP20 by 6/13/08 are GREEN –MP’s that have attempted readiness metric MP20 by 6/13/08 are AMBER –MP’s that have not yet attempted readiness metric MP20 by 6/13/08 are RED ERCOT is calling all MPs that have not signed up for EDS4.9.2

13 Lead from the front Texas Nodal http://nodal.ercot.com 13 Wan Testing WAN Testing  Complete: Private WAN will have nodaleds.ercot.com added to DNS.  If you will not be able to cut over your systems to the private WAN on Monday, please notify eds4@ercot.com with expected dateeds4@ercot.com  Objectives of Testing: - Evaluate whether large reports and MIS will also be made available over the WAN - Goal is to validate our sample capacity tests with the base transactions  If issues are found, ERCOT will roll back the DNS entry and notify the market via a market notice  Reminder: Notifications will remain over the internet only until supporting infrastructure is in place. ETA - TBD

14 Lead from the front Texas Nodal http://nodal.ercot.com 14 Appendix- Outage Scheduler 4.9.2 Reference: TSP/QSE Data Preparation If QSEs or TSPs need their equipment list to verify xml submissions, please email to EDS4@ercot.comEDS4@ercot.com ERCOT is unable to post the information online for all QSEs and TSPs because of the size of the file


Download ppt "Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS 4.9.2 Market Call June 20, 2008."