Caernarvon Freshwater Diversion Advisory Committee 2015 Meeting Tuesday, November 17, 2015 Caernarvon Freshwater Diversion Advisory Committee.

Similar presentations


Presentation on theme: "Caernarvon Freshwater Diversion Advisory Committee 2015 Meeting Tuesday, November 17, 2015 Caernarvon Freshwater Diversion Advisory Committee."— Presentation transcript:

1 Caernarvon Freshwater Diversion Advisory Committee 2015 Meeting Tuesday, November 17, 2015 Caernarvon Freshwater Diversion Advisory Committee

2 INTRODUCTION – History – Features – Goals – Project map w/pre-post lines Caernarvon Freshwater Diversion Advisory Committee

3 U.S. Congress -Flood Control Act of 1965 Water Resources Development Act of 1974, 1986, and 1996 Re-introduce freshwater, sediments, and nutrients into the marshes and bays of the Breton Sound estuary USACE constructed; CPRA operated with oversight and advice from Technical Work Group and Caernarvon Interagency Advisory Committee Located on the east bank of the Mississippi River (mile 81.5) in Plaquemines Parish Five, 15-ft gated box culverts 8,000 cfs Operations began August 1991 Caernarvon Freshwater Diversion Advisory Committee

4

5

6

7 Enhancement of emergent marsh vegetation growth Reduction of marsh loss Increase significant commercial and recreational fisheries productivity Increase significant commercial and recreational wildlife productivity Caernarvon Freshwater Diversion Advisory Committee

8 2014 Data Results 2015 Operations and Maintenance 2016 Proposed Operation Plan Caernarvon Freshwater Diversion Advisory Committee

9

10

11

12

13

14

15

16 Salinty (ppt) Discharge/1000 cfs

17 Mean Monthly Salinities

18

19

20

21 Data Results 2014 Oysters continue to be of concern All other fisheries/wildlife within historical ranges and consistent with natural variations Caernarvon Freshwater Diversion Advisory Committee

22

23

24 Caernarvon Freshwater Diversion Advisory Committee 2014

25

26 2014-2015 Operation Changes Change to 14d moving average Established primary gauges for each isohaline Set some parameters for operations Black Bay near Stone island online May 2014 Fresh year, limited operations Caernarvon Freshwater Diversion Advisory Committee

27

28

29

30

31

32

33

34

35 2015-Issues Affecting Operations Braithwaite Levee Construction – Completed 08/2015 – Low operations only while levees were degraded/under repair (water levels) Caernarvon Freshwater Diversion Advisory Committee

36 Proposed 2016 Operation Plan TWG met 09/22/2015 and 10/29/2015 LDWF input: coordinate during spring brown shrimp migration, continue to consider oyster development 14-day moving average. Daily, 30-day, and running annual salinities monitored Black Bay (15ppt) and Crooked Bayou (5ppt) Long-Term Averages utilized Operations not to exceed 7500 cfs Caernarvon Freshwater Diversion Advisory Committee

37 December-May: 15ppt line Black Bay nr Snake Island (Black Bay) Gauge Bay Gardene and Black Bay nr Stone Island (Stone Island) utilized for supporting information and guidance Caernarvon Freshwater Diversion Advisory Committee

38

39 June-November: 5ppt line Crooked Bayou Cow Bayou Gauge utilized as support and guidance- but heavily influenced by MR Caernarvon Freshwater Diversion Advisory Committee

40

41

42 2016 Operational Considerations Coordination with LDWF during brown shrimp migration period Education and PR visits (outside normal operations) – NTE 5000 cfs, return to appropriate output within 2 hours Maintenance, Repair and Local issues – Evaluated on case-by-case basis – Notification to TWG/CIAC members BS-16 Construction coordination Caernarvon Freshwater Diversion Advisory Committee

43 2015-2016 More transparency in operations (http://coastal.la.gov/diversion-operations/)http://coastal.la.gov/diversion-operations/ Forecast Model Monitoring – Coastwide monitoring program (SWAMP) Coordination with LDWF Caernarvon Freshwater Diversion Advisory Committee