1 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 1 Status of BepiColombo Harri Laakso ESA/ESTEC, Code SRE-OS, Noordwijk, The Netherlands.

Similar presentations


Presentation on theme: "1 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 1 Status of BepiColombo Harri Laakso ESA/ESTEC, Code SRE-OS, Noordwijk, The Netherlands."— Presentation transcript:

1 1 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 1 Status of BepiColombo Harri Laakso ESA/ESTEC, Code SRE-OS, Noordwijk, The Netherlands H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009

2 2  Launcher: Ariane 5  Launch date: 21-Jul-2014  MOI date: 21-May-2020 (5.8 year cruise to Mercury by electric propulsion)  Backup: 06-Aug-2015  31-Oct-2021 (6.2 years)  Launch strategy: Direct escape  1-year Earth-to-Earth transfer  Earth, 2 Venus, 4 Mercury flybys/gravity assists  Gravity capture into Mercury orbit / Final Mercury orbit adjustment by chemical propulsion  Science operations: 1 year nominal plus 1 year extended Mission Design Overview

3 3 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 Experiment IPDR Assessment BELAISAMERMAGMERTISMGNSMIXSMOREPHEBUSSERENA SIMBIO- SYS SIXS DESIGN STATUS ? SCI. PERFORM. INTERFACES - EID B RESOURCES FOPS - OB S/W PA PROGRAMME FUNDG. / SCHEDULE Delta IPDR YESNO (PA) NOYESNO (YES) NO Summary of IPDR Results

4 4 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 ExperimentAllocation [kg] EID B Dr 3 CBE [kg] Declared Margin Post IPDR Alloc. [kg] Margin to Alloc. Remarks BELA 12.0 13.315% 13.012% latest est. 13.5 - 14 kg, savings being identified ISA5.35.7 0%6.0 5% savings to be identified MERMAG1.8 17%1.817% power supply redundancy expected to reduce margin MERTIS3.3 8%3.38% - MGNS5.2 7%5.27% regarded small MIXS7.3 7.3*7%8.87% regarded small 1.5 kg base plate added MORE3.5 15%3.515% - PHEBUS6.67.5 6%7.5 6% savings to be identified SERENA5.45.6 0%6.312% marginal for consortia SIMBIO-SYS8.3 10.1**10% 10.6**15% significant design optimisation pending SIXS1.32.013%2.013% Local radiator added TOTAL 60.0 65.3 8.5% 68.010% regarded small * excl. 1.5 kg MIXS base plate; ** excl. thermal straps (S/C) Experiment unit interconnection harness (ca. 6 kg) not included MPO Payload Resources - Mass

5 5 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 MPO Payload Resources - Power ExperimentAllocation [W] EID B Dr 3 CBE [W] Re-Allocation (TBC) Remarks (allocation is on orbital average) BELA 49 3638orbital average, full mode 49 W; re-allocation possible ISA 6 1210power driven by thermal control MERMAG 5 4.65- MERTIS 81312re-allocation TBD MIXS121614value is for full mode MGNS 4 4.5 - MORE3037 only for orbits with GS contact PHEBUS 4 3.84orbital average, full mode 23 W SERENA2122 22.4 W for full science mode SIMBIO-SYS2325 32.5 W for full science mode SIXS 2 2.5 - TOTAL 164139/176142/179operations may be seasonally constraint Operational scenarios under study by SOC; re-allocation pending further assessment Limitation to 100 W baseline for perihelion or certain mission phases

6 6 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009 Experiment EID B Status BELA Draft 3 finalised and signed as PDR reference, detailed mech. update pending ISA Draft 3 finalised and signed MERMAG Draft 3 finalised and signed MERTIS Draft 3 finalised and signed MGNS Draft 3 finalised and signed MIXS Draft 3 finalised and signed, update required for base-plate implementation MORE Draft 3 finalised and signed PHEBUS Draft 3 finalised and signed SERENA Draft 3 finalised and signed, possible update needed for optimised accommodation SIMBIO-SYS Draft 3 finalised and signed, significant update expected for potential new configuration SIXS Draft 3 finalised and signed, Draft 4 for radiator optimisation in work EID B Issue 1 with configuration control to come by summer / early autumn this year !! MPO Payload EID-B Status

7 7 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009  Open P/L procurement issues:  Solutions to be addressed without delay  Firm up and finalise P/L experiment interface definition for H/W phase:  Partly achieved, but still missing elements  Consolidation to be addressed without delay  P/L accommodation and local interfaces to be confirmed and detailed:  Ongoing activity, as part of PDR with minor adjustments only  H/W phase comes upon us, and requires significant more attention to detailed work and close interaction and reporting  In view of the above and the observed IPDR results:  Please stop “nice-to-have” optimisation dreams  Keep momentum and intensify P/L work  Adopt the “Yes We Can” attitude – also we got to get out of a crisis ! MPO Payload Priorities

8 8 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009  The Critical Equipment Review was held between September-December 2008  Critical technological elements were reviewed  Highly useful exercise and confirmed many technologies that are not considered critical any more  Some remained open and were further studied in spring 2009, such as solar arrays, antenna pointing mechanism and wave guide  The CER board met on 18 December 2008  Recommended to start the PDR activity  Recommended that Collocation Meeting should be organized only after the test results on the solar array are available  Gave critical notes on the mass traceability and maturity of technology for solar array, antenna pointing mechanism and waveguides Critical Equipment Review - 2008

9 9 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009  The PDR Kick-Off was held on 10 March  The CER Board provided guidance to the review team and recommendations on work by the Prime before collocation  The SPC Tracking Committee follows the PDR and advises the SPC  Major items were:  Overall mass budget with increasing trend remains a major concern (10% margin!)  S/W and AOCS complexity and development schedule  AIV (accessibility of equipment, schedule)  Solar Array  Contamination risk by thruster plumes  Collocation meeting with Astrium on 4 – 7 May  The PDR Board meeting on 29 May PDR Activities and Issues

10 10 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009  Preliminary draft recommendations of the PDR board are not yet public  The PDR Board recognized significant development accomplished during the past 12 months  The board believes strongly that BepiColombo will fly  Solar arrays are adequate for the Mercury environment and are currently tested for at 200 C for 10 000 hrs at 230 C for 5 000 hrs  The results confirmed the expectations of solar cell aging  The PDR Board will reconvene in September to discuss the remaining key issues, such as mass and solar array  Final PDR meeting in November is for closing the RIDs and AIs  The BepiColombo CaC needs to be confirmed after the summer in order to issue the SPC paper in September for the SPC meeting on 2 October 2009 PDR Results

11 11 H. Laakso, SERENA - HEWG meeting, Mykonos, Greece, 8-11 June 2009  Manufacturing of STM is in final stage at JAXA, test preparations on-going  Tests on EM are on-going  On-board S/W requirements review completed  Launcher coupled load analysis confirmed acceptable notching profile  Characterization tests of thermal hardware and solar cells are on-going  Issue: Solar array appears to have too little margin to cover UV degradation, temperature uncertainties and modified cosine law. Addition of one solar cell string is under consideration (MMO height increase of 16 cm) MMO Status