1 USAEE/IEAA North American Conference Pittsburgh, PA October 28, 2015 Energy Infrastructure Plenary: Natural Gas Pipelines Donald F. Santa President & CEO Interstate Natural Gas Association of America (INGAA)
2
2 U.S. Natural Gas Transmission Pipelines: A Robust Infrastructure Source: Interstate Natural Gas Association of America, Pennwell MapSearch
3
3 Pipelines 101
4
4 4 The Proliferation of Shale Plays: Marcellus and Utica
5
5 Flow Shifts and Demand Drivers
6
6 6 INGAA Foundation Report assesses US and Canadian midstream infrastructure needs through 2035 including natural gas, NGL, and oil. North American Midstream Infrastructure through 2035: Capitalizing on Our Energy Abundance The detailed presentation can be found at www.INGAA.org/2035report.aspx
7
7 (months) Natural Gas Pipeline Project Timeline Develop Study Corridor Approve Pre-Filing Request (at least 6 months before filing) -6 -5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 Conduct Scoping & Direct Preparation of Resource Reports Issue Draft EIS File At FERC Issue Order Prepare Resource Reports Issue Final EIS Applicant Activities FERC Activities (length of study period determined by the Applicant) Analyze Project Construction can take ~1-2 years
8
8 Natural Gas Pipeline Permitting
9
9 9 Activist Opposition
10
10 Pipelines Make It Possible For more information, please visit www.ingaa.org/construction/www.ingaa.org/construction/