1 Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Wednesday, January 28, 2009 2:00 to 3:00 p.m. ET

2 22 Agenda Creating a Request from OATi ATC Offerings Processing Time of Short Term Firm Requests ATC Narratives Posted as Outage Postings Designated Network Resources Business Practice 3.J – Rollover Rights Transmission Service Annulments OATi webOASIS 3.4.08 Upgrade Wrap-up

3 3 Creating a Request from OATi webOASIS ATC Offerings

4 4 Creating a Request from the OATi webOASIS ATC Offerings Using OATi webOASIS to create a TSR from ATC Offerings MW Amount will default to the full Capacity Available for that Increment (in this case the daily amount of firm available is 232MW)

5 5 Creating a Request from OATi webSweep ATC Offerings Clicking on the PostingRef brings the user to the Offering for the specified Service, Path & Term. The offering is for the full Capacity Available for that Increment. User access to webSweep is through OATi ETS

6 6 Creating a Request from WebSweep ATC Offerings Creating a TSR from the Offering Detail returns to a TSR Entry form with a Blank or Null MW field.

7 7 Creating a Request from OATi ATC Offerings Given the demonstration of the tools, is there sufficient value to warrant asking for a change?

8 8 Processing Time of Short Term Firm Requests Transmission Service Requests that start beyond 9 days from current date or of a duration covering more than one week beyond the 9 th day, requires additional analysis –All requests have been processed within the Tariff timing requirements IE will evaluate ways to further expedite the processing of Short Term Firm

9 9 ATC Narratives Posted as OATi webOASIS Outage Postings Utilizes Outage Posting to post narratives for changes in ATC/TTC as required by FERC –Links the TTC change to a narrative Working with OATI to develop an alternative solution

10 10 Designated Network Resources Revised On System and Off System DNR Forms –FERC Order 890B Requirements –CFR 37.6 (Total Installed Capacity, Electrical Location, and Geographical Location) –Information Required Consistent with OATT 29.2 and 30.3 More information (next 2 slides provide details) –Ease of Use Forms Consolidated - On & Off System / One Form –Improved “How to” Guide / Instructions

11 11 Designated Network Resources New or Changed fields –Network Customer (NITSA Holder) –Agent Name (Scheduling on behalf of Network Customer) –Separate sections for Owned Generation and PPA Section 1 – Owned Generation Section 2 – Power Purchase Agreement (PPA) –Name of agreement “PPA with Southern Wholesale” –“SOCO” as an identifier is not acceptable

12 12 Designated Network Resources New or Changed fields –Section 5 – Valid Customer –Section 6 – Attestation Checkbox –Customer agrees to Attestation –Person agreeing to the Attestation is an authorized Company Officer or Agent Timing for receipt of the DNR Request Form –A DNR request on OASIS will be deemed invalid if a completed DNR request form is not received by 5pm ET the day the request is queued –Business Practice change Business Practice 6B.i.

13 13 Designated Network Resource Business Practice Changes Business Practice 4.C –Tagging 7-FN Generation is Firm (G-F) Transmission must be Firm from the point the Customer takes title of the power Business Practice 6B.i. –Receipt of the DNR Request Form EOB same day as request for service is queued

14 14 Business Practice 3.J Rollover Rights Duke Energy Carolinas modified the conditions for granting Rollover Rights –Effective date for change is 4-1-2009 –PTP Reservations with a duration of 5 yrs or more RENEWAL must be queued 1 yr prior to end of the existing reservation –Network Reservations (NITSA must be for 5 years) RENEWAL must be queued 1 yr prior to end of the existing reservation Service Agreements queued prior to 4-1-2009 –Subject to the current 1yr/60day requirement until the first rollover date on or after 4-1-2009, then subject to new requirements

15 15 Transmission Service Annulments Business Practice 3.A.xi –Business Practice became effective 11/12/2008 –Doesn’t change current situation where Annulments are granted –Provides Audit Trail for both the Customer and Provider Minor Process Requirement Changes –Complete Annulment Form –Phone Call to the Duke TA 651-632-8708 REMINDER- The Annulment Form –This reservation is NOT scheduled or upon annulment, I will remove references to this reservation from e-Tag allocations –Failure to adhere will result in Unreserved Use penalties. Business Practice 7B.iv

16 16 How to Request Nullification of Transmission Service Point-to-Point and Non-Designated Network –Business Practice 3.A.xi. Customer submits Annulment Request Form IE processes Annulment Non-Firm Redirects –Business Practice 3.H.ii.b. Customer would submit a RELEASE request on OASIS (Annulment not needed) “RELEASE” will become “RELINQUISH” 1-29-2009 Firm Designated Network Requests –Business Practice 6.E. Undesignation of Network Resource Request Form IE processes annulment or recall

17 17 OATi webOASIS 3.4.08 Upgrade Compliance with FERC Order 676-C 1-29-09, 11:10am ET webOASIS Release Notes v3.4.08 –http://www.oatioasis.com/releasenotes/v3.4.08_OASIS %20Release%20Notes%20.pdfhttp://www.oatioasis.com/releasenotes/v3.4.08_OASIS %20Release%20Notes%20.pdf OATi Help Desk: 763-201-2020

18 18 OATi webOASIS 3.4.08 Upgrade OATi webOASIS Changes –Assignment of Ownership (NAESB Business Practice WEQ 001-12) FULL_TRANSFER –Assigns Ownership of the Parent Reservation and encumbrances (Redirects, Resales, etc) to a New Owner –Approval required by Reseller, Assignee and Duke PART_TRANSFER –Assigns a portion of the Parent Reservation to a new Owner –Encumbrances (Redirects, Resales) may not be Reassigned –Approval required by Reseller, Assignee and Duke –RESALE (NAESB Business Practice WEQ 001-11) Duke Business Practices do not Change (see DUKE BP 3.A.vii) OATi webOASIS now permits posting of any price (in $/MWH reserved) Permits Reseller to Post for Resale in increments e.g.; Daily, Weekly or Monthly –Check for capacity is done when Assignee makes the RESALE Request Resale reservation has the same scheduling attributes as the Parent –Redirects on a Non-Firm Basis (NAESB Business Practice WEQ 001-10) Replaces RELEASE request type with RELINQUISH for Non-firm (Secondary) Redirects

19 19 Wrap-up Proposed Next Quarterly Stakeholder Meeting –Tuesday, April 21, 2009 – 2 p.m. to 3 p.m. ET Customer Suggested Topics? –This is the forum for discussing emergent topics (Upcoming changes, stakeholder input) Questions and Comments

20 20 Attachments Table of Contents Slide 22 – Designated Network Resource Form Slide 23 – Business Practice 3.A.xi – Customer Request for Annulment Slide 24 – Annulment Request Form Slide 25 – Undesignation of Network Resource Form

21 21 Designated Network Resource Form

22 22 Business Practice 3.A.xi – Customer Request for Annulment

23 23 Annulment Request Form

24 24 Undesignation of Network Resource Form