Presentation is loading. Please wait.

Presentation is loading. Please wait.

Status Report Beam Working Group 11 February 2005 Alternative optics MAMUD CEDAR Fluka simulations Main topics treated since December:

Similar presentations


Presentation on theme: "Status Report Beam Working Group 11 February 2005 Alternative optics MAMUD CEDAR Fluka simulations Main topics treated since December:"— Presentation transcript:

1 Status Report Beam Working Group 11 February 2005 Alternative optics MAMUD CEDAR Fluka simulations Main topics treated since December:

2 Niels presented first results on a study of an alternative 2-stage optics. Normally a charged beam is designed with two big bends in the same direction, the first one creating the dispersion that allows momentum selection and the second one recombining the selected momenta. The I229 design has been based on a achromat consisting of 4 dipoles. A priori the muon background situation looked more advantageous in the traditional 2-stage design, however halo studies show that in the end muon backgrounds are in fact harder to control. Also the 2-stage design is incompatible with NA60 (time-scale!) and would require a displacement of the blue tube and Helium tank, the spectrometer and the Liquid Krypton calorimeter. In view of the tremendous practical implications of the 2-stage optics, we agreed that we would not pursue it for the moment, but see whether some of the good aspects of this optics can be integrated in the achromat-based design. The question can be reconsidered in case the Liquid Krypton would not be used. Alternative beam optics and design

3 Niels Doble

4 Proposed Dipole configuration Pole gap is 2x11 cm V x 30 cm H Coils cross section 10cm x 20cm M.Losasso New design of MAMUD

5 Magnet rough parameters Total weight≈ 150 ton Overall Dimension2.6 m x 2.8 m x 5.25 m (WxHxL) Number of iron plates(2x) 150 Coil Current≈ 3.6 KA Total power dissipation≈ 0.43 MW Field integral on axis (from -1 m to +6.2 m) 6.25 T m Magnetic field into a “good field region” (by 10 cm x 10 cm) ≈ 1.1 T M.Losasso Better treatment of forces

6 Main results of simulation Magnetic field at magnet centre Field integral on axe - Packing factor is 0.54 30 cm 22 cm M.Losasso

7 1. A realistic timescale of the magnet project is something about 3 y.  6 months for conductor development, 1 y for coil production, 1 y for coils assembly, 6 months for contingency 2. Depending on personnel activities at the specified time, the coils could be produced at CERN with tools and machines that are mostly already available (the saving in costs however is relatively low) 3.The assembly costs (and time) shall not be overlooked. For such a construction my rough approximation is that 20% of the total have to be added to take care for these charges. 4. The operating costs have to be evaluated (power, cooling,..) with reference to different scenarios (duration of experiment, projected cost of the electricity and of other infrastructures). 5. A structural analysis have to be done to define a practical way of keeping in position the constructed plates (under g and em forces M.Losasso

8 Preliminary cost analysis Iron  300KEuro approximately Coils  120 KEuro (cost of Al coil construction + a ‘guesswork’ amount to keep into account the welds and the higher complexities of the winding) Cu conductor  cost is to be evaluated, but my first guess is that will be around 150 KEuro (100KE was the AL conductor cost) M.Losasso

9 ONLINE Preliminary

10 OFFLINE PRELIMINARY

11 + Adapt to new layout of MAMUD + Take away beam pipe

12 CEDAR Suggestion to use H 2 instead of He: less X o (N.Doble) First discussions with SC/GS have taken place No showstopper yet Realization that 50 MHz per PM is untolerable (A.Placci) Have to divide rates over many detectors. A.Placci suggests 3 alternatives to PM’s: - Microchannel PM’s with 64 anodes of 6x6 mm2 each but only few out of 64 channels would be hit - Linaear Array Multi-Anode PM’s - Silicon PMT’s (Dolgoshein et al) with 1000 pixels of 30  m 2 Original construction drawings have been recuperated Optics simulation studies are under way (L.Gatignon)

13

14 Nicely matched dimensions and # channels But : common dynode, cost

15 Looks very suitable. But very high noise rate (up to 1 MHz/mm 2 ) at room temp. Has to be cooled to about -70 o C. Remains to be optimized for blue light (wave length shifter?)

16

17 Some validations for CEDAR-N SituationR diaphr  diaphr Spot PM Monochromatic pencil beam K + 100.00.3337 x 24 mm Monochromatic pencil beam  + 103.00.341 Monochromatic pencil beam protons909.00.314 Beam spot 10 mm  in each plane100.00.330 Beam divergence 0.1 mrad in each plane100.00.5177x24 mm Momentum spread 1%100.00.3437x24 mm ‘Nominal beam’ (1%, 0.1 mrad, 10 mm)100.00.5247x24 mm Cedar-N, 10.69 bar of Helium, 75 GeV/c, diaphragm 10 mm PM plane at Z = 706 mm, diaphragm at 1251 mm, quartz window at 851 mm Monochromatic pencil beam K + 100.00.3337 x 24 mm ‘Nominal beam’ (1%, 0.1 mrad, 10 mm)100.00.5247x24 mm For Hydrogen at 2.61 bar:

18 3 mm Ring at correct position  -K separation as expected:

19 8 Condensors “focus” the photons on the PM’s Simulation allows to calculate the image size and to optimise location of the photon detectors

20 Next steps for CEDAR: Complete simulation studies Include dependence of Cerenkov angle (deliberately ignored so far) Detailed analysis of performance with Hydrogen gas Add detailed simulations of multianode PM’s and Silicon detectors Try to organise some tests See whether one can borrow or buy a Hamamatsu PM (cost!) Organise a test of some Silicon PM’s Think about electronics and readout Fast “OR” or more complicated ‘majority logic’?

21 FLUKA Studies for vacuum requirements Ingredients: 1) FLUKA: hadron-nucleus interaction with Oxygen p-O, p-O, K-O 2) TOY Monte Carlo: propagate final state particles across geometry of 1st Straw plane + 15 Veto planes ie. 14 large angle anti + {medium angle PV,LKr,SAC} 3) basic analysis with generated variables (no resolution smearing) G.Collazuol

22

23 Assuming no particle identification Gain order of magnitude with CEDAR CEDAR is really required !!! Demanding !!! Leak rate in straws? Stainless steel tank? …..

24 Final remarks Updated beatch geometry listings are available on te WEB First discussions on possibilities for neutral beam for 2006 Work will and must continue


Download ppt "Status Report Beam Working Group 11 February 2005 Alternative optics MAMUD CEDAR Fluka simulations Main topics treated since December:"

Similar presentations


Ads by Google