Presentation is loading. Please wait.

Presentation is loading. Please wait.

March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.

Similar presentations


Presentation on theme: "March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers."— Presentation transcript:

1

2 March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers

3 1 Document Conflicts The purpose of this document is to provide a general overview of the interconnection process This presentation is intended to be a summary level discussion of the information and requirements and does not include all of the detailed information For detailed information, visit PG&E’s Generation Interconnection Services website at: http://www.pge.com/mybusiness/customerservice/nonpgeutility/generateownpo wer/wholesalegeneratorinterconnection/#thesmallgeneratorinterconnectionproc eduresfortransmissionsysteminterconnectionstransmissionsgip To the extent that there are any inconsistencies between the information provided in this presentation and the requirements discussed on PG&E’s Generation Interconnection Services (“GIS”) website, the information posted on the GIS website shall govern

4 2 Wholesale Generation Interconnection Processes Overview of Wholesale Generation Interconnection Processes Overview of Interconnection Timeline –Fast Track –Independent Study –Cluster Process

5 3 Wholesale Generation Interconnection Process Application Processing Technical Scoping Meeting Technical Studies Interconnection Agreement Project Implementation Generator responsible for timely applications and timely completion of applicable processes. Not part of RFO solicitation Transmission Interconnections –Governed by California Independent System Operator Corporation (CAISO) Tariff PG&E’s transmission interconnections are for 60 kV and higher All applications must be submitted to the CAISO Distribution Interconnections –Governed by PG&E’s Wholesale Distribution Tariff (WDT) PG&E’s distribution voltage level is defined as facilities operating below 60 kV All applications must be submitted to the appropriate interconnecting utility.

6 4 Wholesale Interconnection Study Processes IOU processes vary slightly Fast Track Independent Study Process Cluster Study 2 MW on 12kV and 3 MW on 21 kV and 5 MW on higher voltages Fast Track Screens Electrical Independence Screens Commercial Operation Date Screen (CAISO) No MW limit Financial security requirements Default process, no MW limit One annual study Financial security requirements Independent Study Process and Cluster Process Interconnection Requests may apply for full capacity deliverability. Deliverability assessment will be conducted by CAISO in CAISO’s cluster process. Initial and Supplemental Review System Impact and Facilities Study Phase I and II Studies

7 5 CAISO* Cluster GroupWindowPhase IPhase II Interconnection Agreement 1 & 2ClosedCompleted Completed August 2011 Target December 2011 3ClosedCompleted Target October 2012 Target February 2013 4ClosedJanuary 2012 Target December 2012 Target February 2013 5 Oct/Nov 2011* and March 2012 Target October 2012 Target July 2013 Target November 2013 PG&E WDT ClusterWindowPhase IPhase II Interconnection Agreement 4DClosedJanuary 2012 Target December 2012 Target February 2013 5D Oct/Nov 2011** and March 2012 Target October 2012 Target July 2013 Target November 2013 Cluster Schedule – Application through Final Study Note*: PG&E does not have an October/November 2011 window but will discuss potential applications with developers. Note**: Subject to CAISO Tariff.

8 6 Fast TrackWindowInitial Review Supplemental Review Interconnection Agreement Timeline CAISO* connections No Window15BD10BD4 months~6 months PG&E connections No Window15BD10BD4 months~6 months Independent Study WindowSISFAS Interconnection Agreement Timeline CAISO* connections No Window90BD 4 months~12 months PG&E connections No Window60BD 4 months~12 months Fast Track and Independent Schedule – Application through Final Study CAISO Process applies to SCE and SDG&E as well, IOU processes vary slightly Note*: Subject to CAISO Tariff. Note: BD = business days

9 7 Post- Interconnection Agreement Post Interconnection Agreement, PG&E and Interconnection Customer will be engineering and designing, procuring, and constructing the electrical interconnection –PG&E will engineer the Capital Improvements as agreed upon in the Interconnection Agreement –Interconnection Customer will engineer the electrical system on the Interconnection Customer’s side of the meter and any upgrades that will be applicant built and deeded (if required) Post EPC, PG&E, CAISO (if applicable), and Interconnection Customer will coordinate a pre-parallel inspection and commissioning to achieve Commercial Operation Timing for implementation is project specific and could take from 6 months to 4 years


Download ppt "March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers."

Similar presentations


Ads by Google