K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 1 Phase 1 FPix Mechanics Plans for module assembly Phase 1 design objectives: 1.Reduce # of module.

Similar presentations


Presentation on theme: "K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 1 Phase 1 FPix Mechanics Plans for module assembly Phase 1 design objectives: 1.Reduce # of module."— Presentation transcript:

1 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 1 Phase 1 FPix Mechanics Plans for module assembly Phase 1 design objectives: 1.Reduce # of module types and interfaces 2.Integrate CO2 cooling and lightweight support 3.Improve cooling and cable routing and move the control electronics to high η 4.Improve the geometry to maximize 4 pixel hit η range Kirk Arndt Purdue University

2 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 22 Phase 1 Mechanics R&D tasks at Purdue Continue study of module, cooling tube and electronics layout with FNAL to optimize mechanical design Identify candidate adhesives/thermal interface materials and test radiation effects Begin integration of optics, vacuum, and glue dispensing to motion control system for semi-automated module assembly Assemble mechanical grade module prototypes to evaluate adhesives, interconnects, and develop assembly tooling and procedure

3 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 33 Module development - Adhesives study Requirements for adhesive: –Thermal conductivity: > 0.2 W/m-K –Soft: shear modulus < 50 N/mm^2 –Conformable to 50 micron non-flatness –Radiation hard –Electrically non-conductive –Curing at room temperature –Not flowing during application: adhesive confined within chip –Good wetting properties –Not creeping after curing –Allow integrated module replacement without damaging the support Status –Begun a market survey of adhesives for pixel integrated module assembly with potential to meet requirements for SLHC (including adhesives used in current LHC detectors – ALICE, ATLAS, CMS, LHCb and TOTEM) –6 primary candidate adhesives selected for further testing so far –Building mechanical grade samples using candidate adhesives for evaluation of mechanical properties before and after irradiation FPIX adhesive sample for tensile testing after irradiation

4 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 44 Radiation resistance of adhesives Extensive work has been carried out on radiation effects in polymers, mainly for nuclear reactor applications and radiation processing. Radiation damage studies of organic materials (at CERN in the 1990’s) produced the table above with approximate radiation levels up to which category adhesives can be used. The relative radiation resistance of a number of different materials indicates that high temperature resins are extraordinarily resistant to radiation. The adhesive-substrate interface (composed of ionic and physical bonds) is not usually sensitive to radiation – typically no degradation is observed until the polymer itself (covalent bonds) degraded. This is a general guideline - environmental conditions such as temperature, humidity, and dose rate, as well as additives influence the radiation behavior of materials. 10 yrs LHC 10 yrs SLHC

5 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 55 Mechanical tests of adhesives Two types of mechanical tests are planned: –shear tests on lap-joint samples with symmetric single lap geometry (shown above) –peel tests on adhesive tapes Lap-joint samples are made with aluminum or fiberglass reinforced epoxy thickness is controlled in order to obtain 100 +/-30 micron thick adhesive layers Adhesive tapes are assessed by means of peel tests: the tapes are glued to an aluminum plate Shear or peel strength will be measured using an Instron machine

6 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 66 Automated module assembly Will use robotic ‘pick-and-place’ machine with optics and glue dispensing for upgrade module assembly Could also be used for module placement on upgrade panels Robotics will help in almost any large scale Inner Detector upgrade scenario Smaller ‘standing army’, shorter production time Leads to uniformity of production techniques Status –Installed and programmed new encapsulation dispensing robot (pictured left) –Gantry Positioning System ordered (shown above), delivery expected late Summer 2009 –Will integrate optics, pattern recognition software, vacuum pick-up tool and glue dispensing to the motion control system –Lots of code development, process development, and prototyping before production module assembly begins

7 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 77 Mechanical grade module prototypes Status –Three options for module “stack-ups”  BPIX modules (HDI with TBM on top of the module) probably easier to assemble and test (option A) –Obtaining materials and tooling for prototype module assembly –Once a baseline conceptual design for modules is set for FPIX, we will assemble mechanical grade module prototypes to evaluate adhesives, interconnects, and develop assembly tooling and procedure

8 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 8 Possible Blade Readout (option B) Use two separate readout loops for each 2x8 module, and to send a combined stream to a single electro-optical driver One TBM reads out two 2x8 Modules and sent upstream by one optohybrid channel and readout by one FED channel Output data is sent to a “Port Card” via a flex cable, similar to the existing extension cable Flex Cable length should be 50-60 cm and has a connector or is permanently attached to the HDI; it will have a right angle bend Flex Cable carries Bias voltage, Power voltages, and all controls and data signals Estimates show the existing Extension Cable has a 3db/m attenuation at 320 MHz, sufficient for digital data transmission; confirmed recently in a bench test CONS: HDI is a thermal barrier, commit two modules for every HDI Fold line 2x8 Port Card TBM 320 MHz

9 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 9 Integrated Module/Panel Concept ROCs mounted directly on high heat transfer/stiff material (ex. Thermal Pyrolytic Graphite) Wirebond connections from ROCs to HDI through slots in rigid panel/heat spreader (TPG) Connects two modules to a single TBM AND avoids locating HDI between ROCs and TPG heat spreaders (i.e. thermal path to edge cooling) Leaves pixel sensor uncovered for scanning with pulsed laser Flip chip module REMOVABLE, leaving bus structure (HDI) intact for replacement module 2x8 BBM TBM TPG HDI 2x8 BBM TPG HDI pigtail

10 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 10 Integrated Modules in half-disk with “edge cooling” Each Panel has a single readout/power cable that exits the half-disk on side away from the IP = simple cable routing CO2 flow Heat flow Heat flows radially from ROCs through TPG substrates to outer and inner rings with CO2 cooling Heat flow is not interrupted by slots in substrates for wirebonds Heat flow

11 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 11 Integrated Module assembly 1.HDI and standoff rails glued to TPG substrates 2.TBM mounted and wirebonded to HDI 3.Assembly flipped over 4.2x8 modules mounted on TPG substrates 5.Wirebond connections from modules to HDI through slots in TPG substrates TBM on backside of HDI Standoff rails

12 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 12 Alternative Integrated Module assembly 1.HDI glued and standoff rails glued to TPG substrates 2.Assembly flipped over 3.TBM mounted and wirebonded to HDI 4.2x8 modules mounted on TPG substrates 5.Wirebond connections from modules to HDI through slots in TPG substrates TBM “on top” of HDI, access through cutout in TPG substrate

13 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 13 Time scale and Milestones for Phase 1 Mechanics R&D Module and disk conceptual design and studies are ongoing  baseline conceptual mechanical and electrical design this Summer. Small prototype development for testing will follow. Goal to build full-scale prototypes for thermal and mechanical tests in early 2010. Note: Time scale for Phase I TDR (Spring 2010)

14 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 14 Credits This work is part of our R&D plan described in: Proposal for US CMS Pixel Mechanics R&D at Purdue and Fermilab Daniela Bortoletto, Petra Merkel, Ian Shipsey, Kirk Arndt, Gino Bolla, Simon Kwan, Joe Howell, C.M. Lei, Rich Schmitt, Terry Tope, J. C. Yun with valuable input from Lucien Cremaldi, Greg Derylo, Mikhail Kubantsev, Vesna Cuplov (http://indico.cern.ch/conferenceDisplay.py?confId=28746)http://indico.cern.ch/conferenceDisplay.py?confId=28746

15 Backup slides K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 15

16 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 16 Summary - Mechanics R&D status at Purdue Action itemStatus Continue study of module, cooling tube and electronics layout with FNAL to optimize mechanical design BPIX/FPIX envelope defined. Determining optimal segmentation of readout chain. Moving from design alternatives to a baseline conceptual mechanical and electrical design. Test candidate adhesives/thermal interface materials Completing market survey. Candidate adhesives identified. Begun building mechanical test samples. Evaluation of properties after irradiation will follow. Begin integration of optics, vacuum, and glue dispensing to motion control system for semi- automated module assembly Gantry Positioning System ordered, delivery in ~3 months. Beginning purchase and integration of optics, pattern recognition software, vacuum pick-up tool and glue dispensing to the motion control system. Prepare to assemble mechanical grade module prototypes to evaluate adhesives, interconnects, and develop assembly tooling and procedure Identified three module “stack-up” options. Obtaining materials and tooling for prototype module assembly. Purchased and installed new glue and encapsulation dispensing robot. Will assemble mechanical grade module prototypes to evaluate adhesives, interconnects, and develop assembly tooling and procedure (once baseline design is set).

17 K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 17 Mechanical Design optimization status Defined Phase 1 BPIX and FPIX envelopes Converging on radial layout of 2x8 modules-in-half disk geometry for FPIX to maximize coverage with 4-layer BPIX design proposal New FPIX geometries studied using simulation  Rotated Vane geometry preserves (or slightly improves) resolution while Fresnel Lens and Inverted Cone performs worse than the current turbine blade geometry Determining constraints on the readout chain in order to optimize the segmentation and layout of 2x8 modules in half-disks Once the readout segmentation is defined, we will move from design alternatives to a baseline conceptual mechanical and electrical design. 2x8 modules in Rotated Vane geometry Current BPIX/FPIX envelope definition

18 18 Phase 1 FPIX Disk layout requirements 1.Fits within Phase 1 FPIX envelope definition 2.Modules oriented radially (requires only 2x8 modules, and slightly improves resolution) 3.Locates all outer radius sensors as far forward and out in radius as possible (to minimize the gap in 4-hit coverage between the end of the 4th-barrel layer and the forward-most disk) 4.Maximize 4-hit coverage between end of 4th layer barrel up to eta = 2.5, for particles originating at the IP +/-5cm, using a minimum number of modules 5.Individual modules and/or module-support substrates removable and replaceable without disassembling disks 6.One (or at most 2) geometry substrate(s) to support modules 7.Two (or all three) disks on each side of the I.P. identical 8.Minimizes the amount of material required for cooling and module support, where module location is repeatable and stable to <10 microns with thermal cycling and background vibrations 9.Readout requires no more than (estimated) 700 available AOH. 10.Uses identical (or at most two) geometries of HDI/pigtail cables. 11.(Highly desirable) Delta T < 5C across a single module 12.(Desirable) Separate inner from outer rings for easier replacement of individual modules (and inner radius Vanes with earlier radiation damaged modules)

19 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 19 Current Phase 1 BPIX / FPIX envelope definition

20 20 Current FPix module layout 7 module geometries 168 modules per disk (1080 ROCs per disk) Radial layout of (68 or 72) 2x8 outer and (44 or 48) 2x8 inner radius modules 1 module geometry 116 or 120 modules per disk (1856 or 1920 ROCs per disk) R 144.6 mm R 58.7 mm R ~160 mm R ~40 mm Conceptual Disk Module Layout radial and  overlaps (with 20° tilt of sensors) to cover Phase 1 FPIX region

21 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 21 ½-Disks using 2x8 modules on identical rotated “Vanes” for 6-disk system All identical 2x8 modules on identical Vanes One module on each side of 18 outer and 12 inner Vanes (and 14 in intermediate radius 3 rd Disk option) front back Full ½-Disks reduced 3rd ½-Disk option Note: More z-axis separation between neighboring Vanes needed to avoid interference at inner radius 2x8 active sensor areas shown in red

22 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 22 Current FPIX Half-Disk Minimum separation between neighboring blades is 5mm 5mm gap

23 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 23 2x8 modules on Rotated Vanes Require sufficient clearance to allow for removal and replacement of individual Vanes without having to take an entire half-disk apart More z-axis separation needed between neighboring Vanes to avoid interference at inner ends Three sets of (six) Vanes with 5mm minimum separation between neighboring Vanes

24 291 396 All Identical disks (1 st and 2 nd disks in locations to maximize 4-hit eta coverage) 6 disks = (6x72) outer + (6x48) inner = 720 2x8 modules (11520 ROCs) Note: distance units in mm current FPIX 4 disks at Z: ±355 and ±485 mm η = 1.3 η = 1.6 η = 2.1 η = 2.5 2x8s Z loc. TBD suggest 491mm from IP 30 60 161 45 64.8

25 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 25 Identical 1 st and 2 nd disks, different 3 rd disk to reduce number of modules and material 6 disks = (4x72) outer + (4x48) inner + (2x56) middle = 592 2x8 modules (9472 ROCs) 291 396 η = 1.3 η = 1.6 η = 2.1 η = 2.5 461 2x8s

26 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 26 All 2x8 modules on identical Vanes Identical 1st and 2nd ½-disks, and intermediate radius 3rd ½-disks, shown in current service cylinder This scheme uses identical modules on identical Vanes, and is potentially the lowest material solution for a 6-disk system. Identical 1 st, 2 nd and 3 rd ½-disks may be preferable.

27 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 27 Conceptual Readout chain unit = “Vane” One TBM per 2x8 module on each side of the Vane = 2 TBM channels + 2 AOH per Vane A single TBM + one AOH channel per 2x8 module (16 ROCs) Two 2x8s modules per Vane (one module on each side) Could use the same module as BPix

28 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 28 Vanes cooled from edges (Rings) Consider CO2 cooling tubes in outer and inner rings to cool edges of vanes with pixel modules mounted on heat spreaders CO2 flow in CO2 flow out Heat flow

29 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 29 Study of New FPix Geometries 150um global radius direction 100um global phi direction Radial layouts of modules (using the Phase 1 PSI ROC) align the 150 micron dimension of each pixel in the radius direction and the 100 micron dimension in the phi direction. 2x8 module layout with 20° or 30° tilt to the Z-axis modules aligned radially and castellated on conical 'disks' New proposed FPix geometries were studied by Morris Swartz (JHU) using the detailed Pixelav simulation that is used to generate our reconstruction templates. Four geometries were studied: the current design, the Rotated Vane, and 20° and 30° ‘Fresnel’ options pictured below…

30 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 30 FPix GeometryRMS Res xRMS Res yRMS Res rRMS Res phi Current Geometry 8.4  m18.9  m8.4  m17.8  m Rotated Vane (20°) 13.5  m8.1  m13.5  m7.6  m Fresnel (20°) 39.4  m16.6  m37.0  m16.6  m Fresnel (30°) 27.9  m12.1  m24.1  m12.1  m Results of New FPix Geometries Study The simulation assumes the operation of a new (undamaged) sensor at 100V bias and 263K temperature in a 3.8T magnetic field. The Fresnel option was studied at the design angle of 20° with respect to the beam axis and also at 30° to assess how much the performance could be improved by increasing the angle and charge sharing. The results for tracks near the center of the acceptance are given in local and global coordinates. The local, sensor frame, coordinates are defined so that x is radial (or approximately radial) and y is azimuthal (or approximately azimuthal). They are also given in true projected r-phi coordinates to account for the effects of the rotation angles. The rotated vane works well. As in the current detector, the radial Lorentz-drift produced by the rotation angle can enhance the x-resolution (radial resolution) on both sides of the vanes and partly compensate the larger pixel size. The good azimuthal resolution is well matched to the good azimuthal resolution of the Si-strip tracker and the pixel barrel. The Fresnel options does not work as well. The nominal 20° tilts the sensors so that most tracks are nearly normal in the x-direction (radial direction), significantly reducing the charge sharing in that direction. Increasing the angle to 30° increases the Lorentz-drift induced azimuthal charge sharing and the geometrical radial charge sharing. Unfortunately, there is also a second-order Lorentz term (drift along the B-field direction) that tends to cancel the geometrical effect, worsening the resolution.

31 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 31 FPIX Options for 2013 replacement/upgrade Option 0 1 2 3 Cooling C 6 F 14 CO 2 CO 2 Readout analog 40MHz analog 40MHz analog 40MHz  -tw-pairs analog 40MHz  -tw-pairs Pixel ROC (total #) PSI46 as now (4320 – 6480) 2x buffers (4320 – 6480) 2x buffers (9472) 2x buffers (11520) Disks Current 2-3 3 new disks w/ Vanes 3 new identical disks w/ Vanes Modules 672-1008 592 720 Power as now as now? January 2009 # of TBM readout chains 288 592 720

32 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 32 Phase 1 Pixel System Concept (April 2008) Replace C6F14 with CO2 Cooling 3 Barrel Layers + 3 Forward Disks (instead of 2) Pixel integrated modules with long Copper Clad Aluminum pigtail cables Move OH Boards and Port Cards out 10 0 20 20cm4060 80100 FPIX service cylinder BPIX supply tube η = 1.18 η = 1.54 η = 2.4 OH Boards + Port Cards + Cooling Manifold moved out Long CCA pigtails

33 K. Arndt - PurdueFPix Upgrade Meeting - May 2009 33 Z axis and Radius dimensions of Disk Concepts for Short 4-layer BPIX


Download ppt "K. Arndt - PurdueTracker Upgrade Workshop - June 3, 2009 1 Phase 1 FPix Mechanics Plans for module assembly Phase 1 design objectives: 1.Reduce # of module."