Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June.

Similar presentations


Presentation on theme: "1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June."— Presentation transcript:

1 1 Re Kgabisa Tshwane Programme

2 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June 2004 programme of action: improvement of the physical work environment for the national government in the inner city of Tshwane Re Kgabisa Tshwane programme was launched in November 2005 as a programme to improve the physical working environment of the headquarters of national government departments

3 3 What is Re Kgabisa Tshwane Programme Re Kgabisa Tshwane is a ten year two pronged programme that is aimed at: 1.Providing new and refurbished improved accommodation solutions for civil servants in the inner city of Tshwane. The new and improved accommodation is aimed at improving service delivery to our customers and ensure employee wellness. 2.The new accommodation is to be strategically located in a way that will act as a catalyst for a broader rejuvenation strategy for the inner city of Tshwane.

4 4 Programme Objectives Other objectives of the programme Minimize the cost of the improvement by maximizing the use of Government own building and related infrastructure. Improved service delivery by consolidating and clustering Government departments Ensure that the most viable option for each department is executed.

5 5 Programme Objectives cont. Secondary objectives Promote BEE Improve appearance and image of Government in Tshwane Promote heritage, culture and capital status of the city

6 6 Programme Stakeholders The programme champions are the DPW, DPSA and CTMM The DPW and the CTMM are the programme sponsors and have signed an MOU Other stakeholders include National government, Provincial government, Private sector, BEE and SMMEs, etc DPW provides long term accommodation solutions for public servants CTMM provides both infrastructure and urban management services DPSA ensures that the Batho Pele service levels are achieved National Treasury is responsible for implementation of the funding strategy

7 7 Key Deliverables A. Spatial Development Framework: A spatial development framework has been adopted by the CTMM in January 2006. Seven precincts have been identified as planning nodes. Architectural design guidelines have been developed. Heritage guidelines documents have been developed. Transport study documents have been developed but not yet finalised. Engineering/ Infrastructure documents have been developed. Next major work will be detailed precinct designs.

8 8 TICP SDF : Overall Concept is of consolidation and clustering of Gov. Offices in a series of nodes along two axes associated with key public spaces

9 9 Precincts planning

10 10 Key Deliverables cont B. Needs Assessment: Needs assessment looks at each departments needs in terms of office space, parking and the nature of the business of the department vs. location, accessibility, security etc. 98% needs assessment work has been done. Approximately one third of government headquarters will remain in their present locations. All needs assessments will be finalised end March 2006.

11 11 Key Delivery cont C. Options Analysis: Options Analysis methodology developed (Identifies the optimal accommodation solution and the financing and implementation strategy) (Treasury requirement) First options analyses for DEAT completed in December 2005 Service providers appointed for option analyses for eleven other departments, will be finalised by July 2006: Labour, Defence, SAMDI, SAPS, Arts and Culture, Transport, Minerals and Energy, Justice, Stats SA, Home Affairs and Government Printers Options analyses for remaining departments due to commence in April 2006

12 12 STATUS OF WORK PER DEPARTMENT D. Implementation DepartmentWork DoneCurrent Physical Improvement Public WorksNeeds Analysis Finalised Contracts has been awarded for phase one. Phase two is currently on planning. Cleaning of the outside building is 70 % completed. Painting of the building has commenced Floor finishes is 70% completed. South Wing toilets have been refurbished. Phase one work will be completed in November 2006.

13 13 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement The Presidency Needs assessment finalised Comprehensive information on the current infrastructure has been compiled. Master plan document of the integrated improvement has been finalised. Work on the West wing has commenced.

14 14 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement EducationNeeds assessment is complete The site for development has been finalised. Architectural designs have been approved. EIA has been approved. Financial feasibility studies have been finalised

15 15 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement DPSANeeds assessment is complete The site has been identified The architectural designs has been finalised The building has been re-altered to be in line with the needs assessment. All brick work has been completed Painting has been completed 90% flooring has been completed.

16 16 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement SAPSNeeds Analysis Finalised Awaiting outcome of OA Process

17 17 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Justice and Constitutional Development Needs Analysis Finalised Options analysis underway 8 sites shown to DG, COO. Presentation to Minister/Exco 27 Jan.

18 18 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement SAMDINeeds Analysis Finalised Interim accommodation Batho Pele.

19 19 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Home Affairs Needs Analysis Finalised Awaiting outcome of OA Process Interim accommodation solutions are underway. Two properties have been identified. To meet with DG to finalise interim solutions. Upgrade of travena in progress.

20 20 STATUS OF WORK PER DEPARTMENT DepartmentWork Done Current Physical Improvement Department of Communications Needs Analysis Finalised Awaiting outcome of OA Process., but upgrade of iParioli in progress.

21 21 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Statistics SANeeds Analysis Finalised A number of sites have been looked at with the top management but awaiting outcome of OA Process

22 22 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Transport Needs Analysis Finalised Options analysis advisors have appointed Awaiting outcome of OA Process

23 23 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Minerals & Energy Needs Analysis Finalised Initial negotiation with the MDC has began. A meeting to finalise the issues with the CTMM Awaiting outcome of OA Process

24 24 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Labour Needs Analysis Finalised Single Location. Propose development of option ahead of OA process Also focus will be on finding parking solutions for the building

25 25 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Government Printing Works Needs Analysis Finalised Awaiting outcome of OA Process. Major challenge is perimeter security that needs to be built in the process. A number of sites have been visited.

26 26 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Correctional Services Needs Analysis Finalised PPP process in progress. Choice of location is Salvakop. Meeting with Transnet on the 30/03/2006 to make an offer.

27 27 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Science & Technology Needs Analysis Finalised Options analysis finalised Building works well advanced at the CSIR

28 28 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Land Affairs Needs Analysis Finalised PPP process in progress. Land has been identified. The MDC has been approached. Awaiting a meeting with the CTMM to finalise land issues. Meeting due 10/03/2006

29 29 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Environmental Affairs & Tourism Needs Analysis Finalised PPP process in progress. Land has been identified. Land Evaluations are done. Evaluations will be table on the Land Board on the 17/03/2006

30 30 STATUS OF WORK PER DEPARTMENT DepartmentWork DoneCurrent Physical Improvement Department of Foreign Affairs Needs Analysis Finalised PPP process in progress. Land has been identified. Currently EIA processes are in place.

31 31 Thank You NGIYABONGA


Download ppt "1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June."

Similar presentations


Ads by Google