Report from CALICE Beam Test 2 nd DAQ taking period and Plan for 3 rd DAQ period S. Uozumi Jul-26 2008 ScECAL meeting.

Similar presentations


Presentation on theme: "Report from CALICE Beam Test 2 nd DAQ taking period and Plan for 3 rd DAQ period S. Uozumi Jul-26 2008 ScECAL meeting."— Presentation transcript:

1 Report from CALICE Beam Test 2 nd DAQ taking period and Plan for 3 rd DAQ period S. Uozumi Jul-26 2008 ScECAL meeting

2 CALICE Beam Test 1 st period : May SiW-ECAL + AHCAL 2 nd period : July SiW-ECAL + AHCAL 3 rd period : Sep ScW-ECAL + AHCAL 4 th period : early in next year ? Important imformation can be found in the CALICE BT web page: http://www-flc.desy.de/hcal/fnaltestbeam/shift_schedule_2008.php.htm You can see on CALICE e-log what is currently ongoing : https://ttfinfo.desy.de/CALICEelog-sec/index.jsp Contact me for login-name and password.

3 Silicon-W ECAL / Analog-HCAL Fully functional at the beginning of 2 nd DAQ period. Beam

4 Beam-line setup 4 layers of chambers (from Japan) Trigger counters with area of 10x10, 100x100 mm. 2 Cerenkov conters are installed in upstream.

5 Triggers All the triggers are made with combination of 10x10, C1, C2 and 100x100 trigger signal. 10x10 [mm] minimum bias trigger Electron trigger – 10x10 & C1 & C2 Pion trigger – 10 x 10 & !C1 & !C2 100x100 [mm] muon trigger Beam-halo veto counter is also available (1mx1m with 20cm hole)

6 Beam status The beam is delivered as 4-sec spill per minute. Characteristics of the beam strongly depend on beam energy. – Spot size – Rate – e/pi fraction – Momentum spread – Fraction of multi-particle event

7

8 Accelerator conditions To the MT6, beam will be delivered for nominally 12 ~ 15 hours a day. Beam time will be (hopefully) daytime, but it may change depending on accelerator schedule. Moreover sometimes accelerator is quite unstable, which results in loss of our DAQ time. Therefore clear priorization of the DAQ programs and run scheduling with enough safety margin is necessary. Any low priority programs should be scheduled as optional plans.

9 Updates on ScECAL Beam Test Plans News : Out beam time has been changed from Sep 1 st – 26 th To Sep 3 rd – 29 th due to a schedule of safety review people. Some experts will kindly help us. Alex Kaplan (from DESY AHCAL, while period) Uwe Cornett (engineer from DESY, Sep 20-26th) Vishnu Zutshi (can give help from NIU)

10 Very Tentative Run plan 0. Commissioning run with muon and electron beams. (~7 days) 1.MIP calibration with muon beam. (3 days) – Events are triggered by 10x10 cm muon counter. – Inject 100k muons @ 30 GeV in each strip. 2.Precise MIP scan on one strip.(2 days) 3.Energy scan with electron beam. (5 days) – 1, 2,4,8,16,32 (+ higher if possible) GeV, 250k events at each beam energy. – Both in uniform and non-uniform regions. 4.Energy scan with pion beam. (2 days) – 1, 2,4,8,16,32,60 GeV, 250k events at each energy. – Central region only?

11 Very Tentative Run plan 5. Angular scan with electron beam. (4 days) – At 10, 20, 30 degrees. – 2,4,8,16,32 GeV, ~250k Events at each energy. 6. Angular scan with pion beam? (3 days) 7. Pi0 run (? days) – Put target on upstream, perform energy scan with pion beam. ~ 26 days in total without pion run. Other runs : Daily noise, LED runs during beam-off time Response curve measurement after finishing the beam period.

12  0 run Target should be put at 280cm upstream from the ECAL surface (=CAL inner radius with GLD-prime detector). On beamline, drift chamber support frame is located at that point. Target will be ~6cm Iron? How many events we will collect at which energy?  + or  - for secondary beam ? Is it really possible to reconstruct the  0 even in low energy region? Simulation study is indispensable to make the run plan, but time is quite limited. Need more extensive study to make  0 run plan. Otherwise should we just make it as an optional plan? Or expect 4 th beam time in next year?

13  0 run The iron target should be put here In drift chamber frame

14 Shift plan During Sep 1th-26 th, we will arrange 2 shifts per a day, 7-9 hours for each shift. 1-3 people for a shift from the ScECAL group. Shifters are responsible to : – Follow run plan given by run coordinator – contact accelerator control to request desired beam. – Running DAQ and checking data with online monitor – Monitor detector status – Logging everything into e-log – Report any news or problems to experts immediately.

15 Data flow, Analysis Very quick analysis is done by online display. Raw data files are buffered on RAID disk at MT6, and transferred to GRID disks at DESY and LLAL. After the copy, raw data are converted to LCIO on GRID. -> Need to have the GRID account to access to the lcio data. Data size : 50~60 kB/event -> 10-15 GB for 250k events. -> 1-2 TB for whole DAQ program? For a quick analysis, we will create simple root ntuples from those raw or lcio data. During the data taking, everyone must be involved to the analysis with the simple ntuples on analysis PC. (need to setup analysis environment on the analysis PC.)

16 Radioactive source It will not be easy to borrow it at FNAL, since we need: – Special request to borrow, – Arrangement of delivery, – Additional training and exam to handle. So far no rad. source is used for the CALICE beam test. Hopefully we would NOT like to use the rad. source at FNAL. -> Dead channel check have to be done in Japan. Or should we prepare to borrow it anyway?

17 Participants / period AugustSeptember 171819202122232425262728293031123456789101112131415161718192021222324252627282930123 Satoru Uozumi Katsushige Kotera Adil Kahn Miho Nishiyama Takayuki Sakuma Yuji Sudo Toshinori Ikuno Yusuke Takahashi Daniel Jeans ? Tohru Takeshita ? Kiyotomo Kawagoe Donghee Kim Daejung Kong ? Some of us are trying to change returning flight to Oct-3.

18 Getting Fermi-ID and Trainings First fill web form to have Fermi-ID number. (if you already have the ID number, you still need to renew it from the same page.) https://computing.fnal.gov/cgi-bin/remedy/Remote.pl PLEASE DO IT ASAP, if you have not yet done it! After having the ID-number, you have to take an orientation training. http://www-esh.fnal.gov/pls/default/esh_home_page.page?this_page=22009 http://www-esh.fnal.gov/pls/default/esh_home_page.page?this_page=22009 -> Training Materials -> New Employee Orientation and then follow instructions. There is an online test. You have to get 35 / 40 points to pass. Also finish GERT training from http://www-esh.fnal.gov/pls/default/class_sched.html -> type your ID and select “Visitor”, chose “Safety Training”, go next page, and click “GERT”. Also there is an online test with 10 questions. Finish those online tests before you visit to FNAL.

19 Getting Fermi-ID and Trainings (2) After your arrival to FNAL, you will go to users office (wilson hall first floor) and submit Fermi-ID request form and medical insurance form. MEDICAL INSURANCE COVERAGE IS REQUIRED TO HAVE THE FERMI-ID! PLEASE MAKE SURE YOU ARE COVERED FOR ANY INJURIES DURING THE BEAM TEST! Then you have to take Rad-worker training on Aug-19 th morning. It includes instruction class and challenge exam (need 32 points / 40 questions to pass) After finishing the rad-worker training, you also need to take controlled access training. (10 questions) Prepare for the exams, do not fail ! After finishing those trainings you can finally get TLD badge.

20 Some more things to do If you have a laptop, please bring it to FNAL. There is no public terminal you can use on beamline. Both wired and wireless network are available at FNAL. All the computer have to be kerberized. You need to install kerberos client on your machine to log-on to analysis PC. If sshd is running on your machine, you must stop it. Please get GRID account as much as possible. Sooner or later GRID access is necessary for later data analysis.