“Saving York Factory” Project 2007 Hydrology Report LeeAnn Fishback Scientific Coordinator Churchill Northern Studies Centre January 15, 2008.

Similar presentations


Presentation on theme: "“Saving York Factory” Project 2007 Hydrology Report LeeAnn Fishback Scientific Coordinator Churchill Northern Studies Centre January 15, 2008."— Presentation transcript:

1 “Saving York Factory” Project 2007 Hydrology Report LeeAnn Fishback Scientific Coordinator Churchill Northern Studies Centre January 15, 2008

2 Overall Project York Factory NHS Overall project goal: to determine a method(s) for stabilizing the riverbank to protect the NHS. Investigate hydrological process affecting riverbank erosion “Saving York Factory”2007 Hydrology Report

3 Hydrology Project Goals Examine surface hydrology across site Elevation model to determine potential water flows on site Explore subsurface flows with groundwater wells Monitor hydrological components year round Investigate links with historic drains on site “Saving York Factory”2007 Hydrology Report

4 2007 Hydrology Project Goals Scope of work for borehole installations Equipment purchases Site locations for boreholes Installation of boreholes Data acquisition for elevation model Workplan and ideas for future “Saving York Factory”2007 Hydrology Report

5 Monitoring Well Equipment Onset Hobo Water Level Loggers Remote point interval measurements Pro: Easy to install and cost effective Con: Can’t be frozen

6 Site Locations for Boreholes “Saving York Factory”2007 Hydrology Report

7 Site Locations for Boreholes “Saving York Factory”2007 Hydrology Report Map by David Walker, Parks Canada

8 Site Locations for Boreholes “Saving York Factory”2007 Hydrology Report Map by David Walker, Parks Canada

9 Borehole Installation Boreholes installed by Paddock Drilling 8 boreholes on YF site and 1 off-site Field Work: September 19 – 24, 2007 Total Depth drilled for Hydrology – 18.44 m 58 samples collected from the boreholes “Saving York Factory”2007 Hydrology Report

10 Hydrology Borehole Off-Site

11 Hydrology Boreholes 1 and 2

12 Hydrology Borehole 3

13 Site Locations for Boreholes “Saving York Factory”2007 Hydrology Report Map by David Walker, Parks Canada

14 Hydrology Borehole 4

15 Hydrology Borehole 6

16 Hydrology Borehole 8

17 Borehole Installation 30 cm increments Water levels Samples bagged and labelled Borehole record kept 2” mesh pipe installed with solid riser at top Back fill with sand and bentonite Capped for future equipment install “Saving York Factory”2007 Hydrology Report

18 Sample Processing Borehole samples arrived in Churchill post drilling All samples arrived at Churchill Northern Studies Centre around October 10, 2007 Sorted into various “projects” Samples have been weighed in plastic bags and frozen for further analysis “Saving York Factory”2007 Hydrology Report

19 Data Acquisition for DEM Digital elevation model (DEM) for site mapping and making hydrological model Working with Manitoba Hydro to get required information “Saving York Factory”2007 Hydrology Report

20 Wish List for 2008 Hire student for hydrology project Spring snowmelt for surface hydrology Installation of equipment in boreholes Groundwater tests Identify areas for additional measurements Survey of borehole locations Historical drains on site DEM extraction Processing borehole samples “Saving York Factory”2007 Hydrology Report

21 2008 Wish Visits 5 visits to site 2008 – April – Late May/early June – Early July – End of August – mid to late September Would like a winter visit in 2009 or 2010 “Saving York Factory”2007 Hydrology Report

22 Acknowledgements “Saving York Factory” Project staff and Parks Canada Staff Everett Olson Diana Good Mike Hawkins Paddock Drilling Churchill Northern Studies Centre “Saving York Factory”2007 Hydrology Report


Download ppt "“Saving York Factory” Project 2007 Hydrology Report LeeAnn Fishback Scientific Coordinator Churchill Northern Studies Centre January 15, 2008."