Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.

Similar presentations


Presentation on theme: "Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles."— Presentation transcript:

1 Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles

2 Construction Activities Phase 1 – Dam and Spillway Renovation Phase 2 - In-Lake Construction Sediment Retention Basins Sediment Removal Shoreline Armoring Universally Accessible Fishing Pier Phase 3 – Boat Ramp and Parking Lot

3 Progress – Phase 1 History 1991 – Voids filled under spillway 2007 – Contracted French- Reneker Associates to determine cause 2008 – F-R concluded leak in weathered bedrock Solution: Remove weathered bedrock Status F-R Design complete and permitted for construction Funding has been secured Currently out for bids – Letting date October 21, 2010

4 Timeline – Phase 1 Winter 2010 Early Start Date: December 1, 2010 Portion of dam to be removed Tree Clearing Concrete Removal

5 Timeline – Phase 1 Spring-Summer 2011 Excavate Core Trench Construct Principal Spillway Outlet/Drawdown Pipe Place Embankment Fill

6 Timeline – Phase 1 Summer-Fall 2011 Place Embankment Fill Construct Principal Spillway Inlet Auxiliary Spillway Grading Close Drawdown Pipe Winter 2011 – No Construction Spring 2012 Final Grading Project Complete: May 31, 2012

7 Progress – Phase 2 Sediment Retention Basins Upper Arm Basin Preliminary Design Designed as a Sediment Pond Filled with Dredge Material 1-2 feet deep State Contract for completion Finish Design Apply For Permit Wetland Mitigation Plan

8 Progress – Phase 2 Sediment Retention Basins Campground Arm Design Complete Increasing Dam Height Same function as Upper Arm Basin

9 Progress – Phase 2 Sediment Removal Design Complete Removing sediment via mechanical means Scrapers, Bulldozers, Excavators, Etc. Shoreline Armoring Design Complete Placing Riprap in normally inaccessible locations Universally Accessible Fishing Pier Design 95% Complete

10 Timeline – Phase 2 Winter 2010 Design and permit application complete January 1 Wetland mitigation Spring 2011 Bid Letting: March 17, 2011 Early Start Date: May 1, 2011 Summer-Fall-Winter 2011 Construction Spring 2012 Final Grading and Seeding Project Completion: March 15, 2012

11 Progress – Phase 3 Boat Ramp and Parking Lot Design is 25% complete Schedule dependant on Phase 2 1-2 Months for construction

12 Construction Obstacles RAIN!!! Dam construction would slow Large storms can severely erode a partially constructed dam Sediment removal would stop Green Valley <10% complete

13 Construction Obstacles Perspective: Annual Precipitation for Brighton (inches) 1991 / 2008 1992 / 2009 1993 / 2010 44.0” 30.2” 55.3” 40.5” 54.3” 48.4”

14 Conclusion Dam construction begins in December Phase 2 starts Spring 2011 Boat Ramp starts Fall 2011 or Spring 2012 All phases should be complete and the lake nearly full by the end of May 2012


Download ppt "Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles."