1 CEDAR Opening 26/03/2012-FH1

2 Cedar Overview 26/03/2012-FH2

3 Paperwork for Intervention The intervention is described in the WP (EDMS#1207148 ) The VIC was done Friday morning. The Intervention is approved and will be done this week. 26/03/2012-FH3

4 Preparation Work in ECN3 The relevant drawings from the original CEDAR were scanned and uploaded in EDMS. Thanks to Lau and Sylvain. The CEDAR has been shipped to ECN3, and a protective tent is rechted around. The handling tools for dismantling the nose are available. The CERN work-shop will do the modifications to the nose, i.e. – Shortening tube by 400mm – Drilling support holes for the KTAG (12xM12) – Increase groove for new joint (still to be confirmed). 26/03/2012-FH4

5 CEDAR Nose 26/03/2012-FH5

6 Leak-test done last Week Pressurize CEDAR to 5 bar using He (95%) – Measure pressure decay – Sniff He outside Results: – Overall leak rate ~ 8 x 10 -2 at operating pressure – Found two leaks on gas connectors. They will be repaired later on. – The joint on the rotating shaft is good, also while operating the diaphragm. Okay for H 2 safety, but not brilliant for stable operation 26/03/2012-FH6

7 Diaphragm Actuator Rotating shaft Diaphragm motor Rubber joints (non-static) Cedar housing Inside Cedar 26/03/2012-FH7

8 Timeline for the Intervention Leak test done last week Open and dismantle CEDAR nose (today and tomorrow) Work-shop work will take 3 days Leak test of the nose Remount the nose Mount new Beam windows. 26/03/2012-FH8