Presentation is loading. Please wait.

Presentation is loading. Please wait.

Christopher Nantista ARD R&D Status Meeting SLAC February 3, 2011. …… …… …… … ….

Similar presentations


Presentation on theme: "Christopher Nantista ARD R&D Status Meeting SLAC February 3, 2011. …… …… …… … …."— Presentation transcript:

1 Christopher Nantista ARD R&D Status Meeting SLAC February 3, 2011. …… …… …… … ….

2 Powering the main linacs Reduced bunch number Low E cm operation Outline

3 RDR Configuration In the 2007 Reference Design Report (RDR), the ILC main linacs had a dual-tunnel configuration, with rf production and other equipment housed in a service tunnel running parallel to the accelerator tunnel. Every 38 m, power from a 10MW L-band klystron was brought through a penetration between the tunnels and fanned out to power 26 cavities in 3 cryomodules.

4 Change to Single Tunnels In the ensuing Technical Design Phase, to control costs, the decision has been made to eliminate the service tunnel, requiring the development of alternate powering schemes. OPTIONS: Distributed RF System (DRFS) – smaller klystrons powering 2 (4) cavities each and grouped several to a modulator included in shielded region of enlarged accelerator tunnel. Klystron Cluster Scheme (KCS) – rf power brought from surface through shafts. RDR-Like Single Tunnel Solution – RDR rf equipment moved into enlarged accelerator tunnel with added shielding.

5 KLYSTRON CLUSTER BUILDING CTO ACCELERATOR TUNNEL 2.05 km of linac powered per 2-cluster shaft. 12 shafts total for both linacs. Klystron Cluster Scheme Main linac rf power is produced in surface buildings and brought down to and along the tunnel in low-loss circular waveguide. Many modulators and klystrons are “clustered” to minimize surface presence and number of required shafts. Power from a cluster is combined and then tapped off in equal amounts at 3-cryomodule (RDR rf unit) intervals. equipment accessible for maintenance tunnel size smaller than for other options underground electrical power and heat load greatly reduced ADVANTAGES

6 Couplings ranging from ~1 to 1/33 to the TE 01 (low loss, no surface E-field) mode are required. Combining and Distributing Power CTO (Coaxial Tap-Off) For combining, the tap-offs are installed backwards. Proper phase and relative amplitude needed for match (mismatched power goes to circulators). determines coupling CTO customizable coupler feed 1feed 2 hybrid load RF Unit

7 The nominal klystron cluster is to feed 27 rf units (81 cryomodules, 702 cavities). The estimated number of 10 MW klystrons required per cluster is: 27one per rf unit as in the RDR +2for additional transmission and combining/dividing losses and to accomodate gradient spread (±20%, adopted to increase cavity yield) +2to allow one failure per cluster (added reliability). Unpowered connected klystron switched on should another fail. Combined power goes as square of fraction on, (N-1) 2 /N. +2to provide 7% (5% usable) overhead for LLRF, managed by counterphasing klystrons in pairs 33 klystrons Klystrons per Cluster (full power) TOTAL: 20×33 + 30 + 25 = 715 klystrons installed (693 on) For the e - and e + linacs combined, we need

8 Reduced Beam Current More recently, as a way to further reduce initial cost, it was decided to half the number of bunches in the ILC beam pulse for the initial installation. The direct impact on the luminosity might be ameliorated by introduction of a traveling focus scheme. In this reduced beam current “low power” scenario, site power is reduced, along with water cooling requirements. Additionally, for the high-power rf system, the amount of installed rf production equipment can be significantly reduced. The impact depends on the bunch frequency, f B, which affects: beam pulse current: I b = N e e f B beam pulse duration: t b = (n B – 1) f B -1 rf power per cavity: rf pulse duration: and thus

9 KCS Low Power KCS is very flexible. Combining tens of klystrons allows us to adjust installed power with relatively fine granularity. Simply eliminating every other bunch (halving f B ) maintains the beam duration and halves the current, cutting in half the required peak power. However, it also doubles the cavity fill time., thereby increasing the required rf pulse width at full gradient by 38%. It’s preferable to adopt parameters which allow use of the modulators and klystrons developed for full RDR beam specifications, i.e. to stay within the ~1.6 ms pulse width. This can be achieved by reducing the bunch spacing to increase the current to 0.69 I 0. The rf peak power required at the cavities is reduced from that for the full beam by this factor. Fixed t b : Fixed t rf : beamfill -- full beam -- ½ current -- retains rf pulse width (P rf → ½ P rf0, t rf → 1.38 t rf0 )  17 klystrons/cluster (P rf → 0.69 P rf0, t rf → t rf0 )  23 klystrons/cluster

10 RDR-Like Fallback Low Power With the KCS and DRFS schemes in development, an RDR-like layout w/ 10 MW klystrons, modulators, etc. in the (enlarged) single tunnel is considered the fallback plan. For half bunches operation, one could double the bunch spacing and install half the modulators and klystrons, each feeding 6 CM’s, rather than 3. This again would double the fill time, increasing the required rf pulse width by 38%. The installed modulators and klystrons would then be overspec.ed for the upgrade. FULL BEAM HALF BEAM P rf → ½ P rf0 t rf → 1.38 t rf0 every other klystron omitted

11 Alternatively, one could install 2/3 of the rf production equipment, with each klystron feeding 4 ½ CM’s. This would reduce the available power per cavity, and thus the acceleratable beam current or bunch frequency, by a factor of ~2/3 vs. RDR. The beam pulse duration (  n B /I b → ½ / 2/3) is then shortened by a factor of ¾, and the fill time increased by a factor of 3/2, yielding an rf pulse width increase of only ~3.5%. every 3 rd klystron omitted P rf → 2/3 P rf0 t rf → 1.035 t rf0

12 250 GeV/beam # of bunches bunch spacing beam current beam duration rf peak power fill time, t i rf pulse duration full beam2625369.2 ns9 mA0.969 ms294.2 kW0.595 ms1.564 ms ½ bunches A1313738.5 ns4.5 mA0.969 ms147.1 kW1.190 ms2.159 ms (up 38%) ½ bunches B KCS 1313535.1 ns6.21 mA0.702 ms203.0 kW0.862 ms1.564 ms ½ bunches B RDR 1313553.8 ns6 mA0.727 ms196.1 kW0.893 ms1.619 ms (up 3.5%) -- full beam 0% -- ½ bunches A 40.6% -- ½ bunches B (KCS) 1.9% -- ½ bunches B (RDR) 5.5% @ 31.5 MV/m cryo load increase * * Only includes dynamic load of fundamental rf in cavity. Additional contributions come from coupler (linear w/ power and time) and HOM (current dependent). Parameter Summary Parameter choice also impacts cryogenic load.

13 HPRF heat load distribution (from slide 9): above ground – 68.3% below ground – 31.2% (65.7% fixed, 34.3% power dependent) HPRF heat load reduction factor: above ground – 0.69 below ground – (0.657 + 0.343×0.69) = 0.894 Total – (0.683×0.69 + 0.312×0.894 ) = 0.750 -- full beam -- ½ bunches A -- ½ bunches B (KCS) -- ½ bunches B (RDR) Heat Load Breakdown for KCS The rf energy deposited per pulse into the cavity reflection loads (circulator loads), being the product of P rf (  I b ) and t i (  I b -1 ), is, for a given gradient, constant across the parameter sets. For the RDR-like layout the total reduction is the same, 0.75, all below ground.

14 Low E CM Operation Another design change was the relocation of the undulator for positron production from the middle to the end of the electron linac, closer to the damping rings. This poses a problem. For sufficient positron production, the e - beam needs to be @  150 GeV. The physics specifications for the ILC call for running at various center-of-mass energies: 500 GeV, 350 GeV, 250 GeV, 230 GeV, and 200 GeV. Previously, for the operation points < 300 GeV c.o.m., the e - beam could be decelerated from 150 GeV after the undulator; with the undulator at the end, it can’t. Solution: For 250 GeV c.o.m. and below, run e- linac at double rep. rate, 10 Hz, alternating between 150 GeV pulses for e+ production and half the desired E CM for collisions.

15 To retain luminosity for E CM ≤ 250 GeV (≤125 GeV/beam), run e - linac @ 10Hz, alternating between 150 GeV for e + production and the desired collision energy. In this scheme, because the cavity couplers are mechanical, Q L cannot be optimized for both gradients, but is set for the 150 GeV gradient (150/250 × 31.5 MV/m = 18.9 MV/m). For flat gradient during the alternating lower cavity voltage (V L ) pulses the needed input power and the residual cavity reflection are given by: P L = ¼ (1 + V L /V 150 ) 2 P 150 = 0.8403, 0.7803, 0.6944 P 150 @ 125, 115, 100 GeV P r = ¼ (1  V L /V 150 ) 2 P 150 = 0.694%, 1.36%, 2.78% P 150 @ 125, 115, 100 GeV Fill: const. power, P L,  OR const. fill time, t i,  P Li = (V L /V 150 ) 2 P 150 = 0.8745, 0.8210, 0.7370 t i150 @ 125, 115, 100 GeV = 0.6944, 0.5878, 0.4444 P 150 @ 125, 115, 100 GeV To fill the cavity by beam arrival, one must also either toggle the timing or step the power level during the pulse (between fill and beam). 10 Hz Running

16 Impact on Power Requirements I b = KV a 3/2, P mod = I b V a = KV a 5/2 SLAC/KEK Toshiba 10 MW MBK For 125 GeV beam, one needs 5 MW per tube (vs. 10 MW for 250 GeV),  V mod can be lowered from 117kV to 94kV, reducing modulator peak power to (94/117) 5/2 =.579 × the nominal value. Also, pulse width is reduced by a factor of to [(125/250)×.595ms +.969ms]/1.564 ms = 0.810  pulse energy reduced by factor of ~0.469. For the 150 GeV pulses, V mod = 99.5kV, and this factor becomes.667×.848 = 0.565. So the total power load factor for running at 10 Hz is about 0.469 + 0.565 = 1.034, a slightly increased demand. This can be avoided by running at 9.7 Hz, instead.

17 At lower gradients, reduce modulator voltage and increase pulse rate so that nominal average modulator input power not exceeded. → charging power supplies would see the same or smaller load (which is roughly constant), and the AC power capacity would not have to be increased. Effect on Modulator Charging Discharge less energy per pulse at increased rep rate. Time Modulator Cell Voltage Same Slope Discharge Level Differs Every Other Pulse 5 Hz10 Hz Additional line ripple introduced by alternating discharge levels would need to be reduced in the site electrical distribution system.

18 Assumptions At lower gradients, reduce modulator voltage and increase pulse rate so nominal average modulator input power not exceeded - thus the charging power supplies would see the same or smaller load (which is roughly constant), and the AC power capacity would not have to be increased. Time Modulator Cell Voltage Same Slope Discharge Level Differs Every Other Pulse Additional line ripple introduced by alternating discharge levels would need to be reduced in the site electrical distribution system. 5 Hz10 Hz


Download ppt "Christopher Nantista ARD R&D Status Meeting SLAC February 3, 2011. …… …… …… … …."

Similar presentations


Ads by Google